Palestinian Recovery & Development Plan MDTF

Development Objective

The main objective of the PRDP TF is to provide budget and development support for the Palestinian Authority's (PA) policy agenda as expressed ion the PRDP in the period from 2008 to 2010. Other additional objectives include, but are not limited to, the following items: a) pooling of different donor funds intoone administrative mechanism that will reduce the transaction costs for the PA; and b) helping alleviate the PA fiscal pressure by providing reliable disbursements on a regular basis.

Key Details

Project Details

  • P110690

  • Closed

  • Mark Ahern

  • Ministry of Finance

  • West Bank and Gaza

  • April 11, 2008

  • (as of board presentation)

    April 11, 2008

  • April 11, 2008

  • US$ 641.00 million

  • C

  • Not Applicable

  • June 1, 2017

  • BANK APPROVED

  • May 14, 2019

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
West Bank & Gaza - Non IBRD Funded 641.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 641.00
Total Project Cost** 641.00

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2017-03-21
Overall Implementation Progress (IP) Satisfactory 2017-03-21
Progress towards achievement of PDO Satisfactory 2017-03-21
Procurement Satisfactory 2017-03-21
Project Management Satisfactory 2017-03-21
Financial Management Satisfactory 2017-03-21

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 08-29-2019
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Disbursements from the PRDP TF are linked to the Development Policy Grant and its indicators.ValueYesYesYes
    DateApril 18, 2008June 30, 2017June 27, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • macroeconomic outlook is adequateValueYesYesYes
    DateApril 18, 2008June 30, 2017June 27, 2016
    Comment