Financier | Commitments |
---|---|
Development Grant Facility | 0.73 |
P110728
Closed
Maurizia Tovo
N/A
February 6, 2008
(as of board presentation)
February 6, 2008
May 5, 2008
US$ 0.73 million
N/A
2008
US$ 0.73 million
C
January 15, 2013
June 30, 2016
BANK APPROVED
Financier | Commitments |
---|---|
Development Grant Facility | 0.73 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 0.73 |
Total Project Cost** | 0.73 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2016-01-19 |
Monitoring and Evaluation | Highly Satisfactory | 2016-01-19 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2016-01-19 |
Financial Management | Satisfactory | 2016-01-19 |
Procurement | Satisfactory | 2016-01-19 |
Project Management | Moderately Satisfactory | 2016-01-19 |