Financier | Commitments |
---|---|
IDA Grant | 50.00 |
P110762
Closed
Yasuhiko Matsuda
N/A
April 4, 2008
(as of board presentation)
May 6, 2008
September 19, 2008
US$ 50.00 million
N/A
2008
US$ 50.00 million
C
Not Applicable
June 30, 2014
BANK APPROVED
August 28, 2014
Financier | Commitments |
---|---|
IDA Grant | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 50.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 6, 2008 | IDA-H3670 | Loan Commitment | 50,000,000.00 |
Jul 1, 2015 | IDA-H3670 | Loan Cancel | 12,591.54 |
Aug 19, 2013 | IDA-H3670 | Loan Disb | 360,487.40 |
Aug 19, 2013 | IDA-H3670 | Loan Disb | 108,906.26 |
Oct 31, 2014 | IDA-H3670 | Loan Disb | -0.01 |
Oct 31, 2014 | IDA-H3670 | Loan Disb | 0.01 |
Oct 3, 2013 | IDA-H3670 | Loan Disb | 858,052.00 |
Dec 9, 2013 | IDA-H3670 | Loan Disb | 58,588.77 |
Feb 27, 2014 | IDA-H3670 | Loan Disb | 1,464,857.60 |
Aug 7, 2013 | IDA-H3670 | Loan Disb | 126,374.29 |
Aug 14, 2013 | IDA-H3670 | Loan Disb | 602,497.25 |
Dec 27, 2013 | IDA-H3670 | Loan Cancel | 13,058,577.00 |
Mar 7, 2014 | IDA-H3670 | Loan Disb | 1,246,152.00 |
Oct 31, 2014 | IDA-H3670 | Loan Disb | -512,340.80 |
Oct 31, 2014 | IDA-H3670 | Loan Cancel | 1,160,460.10 |
Jul 1, 2015 | IDA-H3670 | Loan Disb | -12,591.54 |
Aug 29, 2013 | IDA-H3670 | Loan Disb | 785,714.20 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2014-06-21 |
Procurement | Satisfactory | 2014-06-21 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2014-06-21 |
Counterpart Funding | Satisfactory | 2014-06-21 |
Project Management | Moderately Satisfactory | 2014-06-21 |
Financial Management | Satisfactory | 2014-06-21 |
Monitoring and Evaluation | Satisfactory | 2014-06-21 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-24-2014 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-16-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Negligible To Low | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Beneficiaries of Labor Market programs - Other (number) | Value | 0.00 | 3030.00 | 25000.00 |
Date | September 19, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
Beneficiaries of Labor Market programs - Female (number) | Value | 0.00 | 1197.00 | 7500.00 |
Date | September 19, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
Conflict affected ppl receiving benefits in 1st yr of proj. effectiveness–female | Value | 0.00 | 4444.00 | 4700.00 |
Date | September 19, 2008 | November 30, 2012 | June 30, 2014 | |
Comment |
At least 95% of identified eligible families of the deceased and widows receive cash payments following the project operational guidelines | Value | zero (no receipt of benefits) | 14,200 families of the deceased received payment4 | At least 95 % (of estimated eligible 14,800 famili |
Date | July 30, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
At least 90% of eligible conflict-affected widows, orphans, those disabled in the conflict, families of those killed in the conflict, families of the disappeared, Internally Displaced Persons (IDPs), | Value | zero (no services provided) | 14,770 (59%) | At least 90% of eligible (estimated 25,000) confl |
Date | July 30, 2008 | December 31, 2013 | June 30, 2014 | |
Comment |
At least 90% of surveyed recipients are satisfied with MOPR benefit delivery process (cash payments and rehabilitation services) | Value | 0.00 | 87.00 | 90.00 |
Date | July 30, 2008 | July 9, 2013 | June 30, 2014 | |
Comment | As per the third monitoring exercise carried out in February 2012. | At least 90% for cash benefits recipient and 80% for rehabilitation services recipient are satisfied with the delivery process |
Summary payment information to families of the deceased and widows is available on the MOPR website and district disclosure boards and updated quarterly | Value | No website payment information | Records and information of the deceased and widows | Summary payment information to families of the dec |
Date | July 30, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
Grievance mechanism operational | Value | no grievance mechanism | 2 Officers designated as grievance focal points | Grievance mechanism operational |
Date | July 30, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
Beneficiaries of Labor Market programs (number) | Value | 0.00 | 3030.00 | 25000.00 |
Date | September 19, 2008 | November 30, 2012 | June 30, 2014 | |
Comment |
Conflict affected people receiving benefits in 1st year of project effectiveness | Value | 0.00 | 12000.00 | 14800.00 |
Date | September 19, 2008 | February 15, 2010 | June 30, 2014 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Consultations for development of guidelines for rehabilitation services held with stakeholders (beneficiaries, civil society and donors and other line ministries) | Value | No guidelines, no consultations | Several consultations held with stakeholders | Consultations held with stakeholders |
Date | July 30, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
Operational guidelines for services to conflict affected groups endorsed by NPTF Secretariat | Value | No guidelines | Guidelines for employment services to conflict aff | Operational guidelines for services to conflict a |
Date | July 30, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
Guidelines/directives for families of the deceased and widows payments endorsed by NPTF Secretariat | Value | No guidelines | BPOG for widows approved and endorsed by NPTF Secr | Guidelines/directives for families of the deceased |
Date | June 30, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
MOPR communication strategy developed and deployed | Value | No strategy | Outreach strategy for ESES approved by MOPR | MOPR communication strategy developed and deployed |
Date | July 30, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
Beneficiary Assessments conducted | Value | None conducted | Second third party monitoring ongoing | At least two Beneficiary Assessments completed |
Date | June 30, 2008 | December 31, 2013 | June 30, 2014 | |
Comment |
Social audits conducted | Value | None conducted | Second social audit report submitted to client | At least two social audit exercises completed |
Date | July 30, 2008 | December 31, 2013 | June 30, 2014 | |
Comment |
MIS system operational | Value | No central MIS | MIS for ESES completed | MIS system core elements operational |
Date | July 30, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
Grievance/complaints mechanism introduced and staffed | Value | No grievance/complaints mechanism | 2 Officers designated as grievance focal points | Grievance/complaints mechanism fully functional fo |
Date | July 30, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
Number of disclosure boards established | Value | No disclosure boards | Using the discloser of DAO and DDC: 100% in place | At least 70% of ESES locations establish disclosur |
Date | July 30, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |
Third party monitoring conducted annually | Value | No independent monitoring | Second TPM under way | At least 3 third party monitoring conducted |
Date | July 30, 2008 | December 31, 2013 | June 30, 2014 | |
Comment |
Monitoring and evaluation plan developed | Value | No monitoring and evaluation plan | Components of M&E plan identified. M&E Plan approv | Project Monitoring and Evaluation Plan extends to |
Date | July 30, 2008 | June 17, 2013 | June 30, 2014 | |
Comment |