Bangladesh Padma Multipurpose Bridge Project

Abstract*

The objective of the Padma Multipurpose Bridge Project for Bangladesh is to connect the south- western region to the rest of the country in order to stimulate economic growth by facilitating inter-regional, cross-river transport of passengers and freight, and transmission of natural gas, telecommunication and electricity in a cost effective manner. There are five components to the project, the first component being main bridge and approach roads...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to connect the south-western region to the rest of the country in order to stimulate economic growth by facilitating inter-regional, cross-river transport of passengers and freight, and transmission of natural gas, telecommunication and electricity in a cost effective manner.

Key Details

Project Details

  • P111017

  • Closed

  • Masood Ahmad

  • N/A

  • Bangladesh

  • (as of board presentation)

    February 24, 2011

  • US$ 2915.00 million

  • N/A

  • South Asia

  • 2011

  • US$ 2355.00 million

  • A

  • March 11, 2021

  • June 29, 2012

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
JAPAN: Japan International Cooperation Agency (JICA) 400.00
Borrower/Recipient 560.00
Islamic Development Bank 140.00
IDA Credit 1200.00
Asian Development Bank 615.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 1200.00
IBRD + IDA Commitment 1200.00
Lending Instrument
Grant Amount 1155.00
Total Project Cost** 2915.00

Summary Status of World Bank Financing (US$ Millions) as of December 31, 2024

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of December 31, 2024

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 24, 2011 IDA-48650 Loan Commitment 1,200,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall High 2011-08-28
Overall Implementation Progress (IP) Satisfactory 2011-08-28
Procurement Moderately Satisfactory 2011-08-28
Project Management Satisfactory 2011-08-28
Progress towards achievement of PDO Satisfactory 2011-08-28
Counterpart Funding Satisfactory 2011-08-28
Monitoring and Evaluation Satisfactory 2011-08-28
Financial Management Moderately Satisfactory 2011-08-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-24-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingNot Rated N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityNon-evaluableN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • The south-west region is connected to the rest of the countryValue0.000.00100.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Quantum of freight and passenger crossing over the bridge and transmission of gas and electricity.Value0.000.003000.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Number of Ha protected against river bank erosion and floodsValue0.000.005000.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Number of people directly benefiting from the bridge.Value0.000.007000000.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Reduction in travel time to Khulna and JessoreValue0.000.009.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Construction of 6.15 km bridgeValue0.000.00100.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Completion of RTWsValue0.000.00100.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Implementation of SAP and RAPValue0.000.00100.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Construction Supervision and Implementation Support (CSC Consultants)Value0.000.000.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Effectiveness of PMU operationsValue0.000.000.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Construction of Bridge Approach Roads, toll plazas and service areasValue0.000.00100.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Livelihood Restoration of Affected PeopleValue0.000.0090.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Independent M&E of Project Impact and of SAP and EMAPValue0.000.000.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Capacity Building of BBAValue0.000.000.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment
  • Environmental Mitigation Action PlanValue0.000.00100.00
    DateJanuary 24, 2011July 5, 2011August 31, 2016
    Comment