Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 220.00 |
P111577
Closed
Thalyta Yuwono , Marcus Lee
Ministry of Home Affairs,Ministry of Finance
May 27, 2009
(as of board presentation)
June 8, 2010
January 20, 2011
US$ 220.00 million
Ministry of Public Works, Secretariat General,BPKP,Ministry of Finance,Bappenas
2010
US$ 220.00 million
B
Not Applicable
December 31, 2017
BANK APPROVED
October 1, 2020
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 220.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 220.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 220.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 220.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 14, 2016 | IBRD-84380 | Loan Disb | 15,051,592.00 |
Jun 30, 2014 | IBRD-79140 | Loan Disb | 7,225,704.50 |
Jun 25, 2014 | IBRD-79140 | Loan Disb | 41,400,576.00 |
Feb 27, 2015 | IBRD-84380 | Fee Charges | 1,250,000.00 |
Jun 18, 2015 | IBRD-79140 | Loan Disb | 6,552,777.50 |
Jun 26, 2015 | IBRD-84380 | Loan Disb | 46,153,056.00 |
Jun 12, 2015 | IBRD-79140 | Loan Disb | 41,810,196.00 |
Apr 1, 2015 | IBRD-79140 | Int Charges | 545,934.10 |
Oct 1, 2014 | IBRD-79140 | Int Charges | 0.01 |
Oct 1, 2014 | IBRD-79140 | Int Charges | 453,304.66 |
Aug 12, 2013 | IBRD-79140 | Loan Disb | 20,449,314.00 |
Aug 12, 2013 | IBRD-79140 | Loan Disb | 41,675,836.00 |
Oct 1, 2013 | IBRD-79140 | Int Charges | 215,835.88 |
Apr 1, 2014 | IBRD-79140 | Int Charges | 60,399.45 |
Apr 1, 2014 | IBRD-79140 | Int Charges | 397,266.66 |
Dec 1, 2022 | IBRD-84380 | Int Charges | 7,640,282.00 |
Dec 1, 2022 | IBRD-84380 | Loan Repay | 24,550,000.00 |
Oct 1, 2018 | IBRD-79140 | Int Charges | 3,250,960.20 |
Dec 1, 2018 | IBRD-84380 | Int Charges | 7,472,500.00 |
Jun 1, 2019 | IBRD-84380 | Int Charges | 8,543,889.00 |
Apr 1, 2019 | IBRD-79140 | Int Charges | 3,433,187.00 |
Oct 1, 2019 | IBRD-79140 | Int Charges | 3,507,909.00 |
Oct 1, 2019 | IBRD-79140 | Loan Repay | 4,769,027.50 |
Dec 1, 2019 | IBRD-84380 | Int Charges | 7,726,666.50 |
Apr 1, 2020 | IBRD-79140 | Int Charges | 2,786,961.20 |
Apr 1, 2020 | IBRD-79140 | Loan Repay | 4,878,913.00 |
Jun 1, 2020 | IBRD-84380 | Int Charges | 6,074,583.50 |
Oct 1, 2020 | IBRD-79140 | Int Charges | 1,687,637.20 |
Oct 1, 2020 | IBRD-79140 | Loan Repay | 5,010,775.50 |
Dec 1, 2020 | IBRD-84380 | Int Charges | 2,567,083.20 |
Oct 1, 2016 | IBRD-79140 | Int Charges | 1,418,804.00 |
Jun 1, 2017 | IBRD-84380 | Int Charges | 2,170,428.00 |
Jul 10, 2017 | IBRD-84380 | Loan Disb | 46,372,252.00 |
Jun 21, 2017 | IBRD-84380 | Loan Disb | 201,089,264.00 |
Apr 1, 2017 | IBRD-79140 | Int Charges | 1,833,255.20 |
Oct 1, 2017 | IBRD-79140 | Int Charges | 2,077,933.50 |
Dec 1, 2017 | IBRD-84380 | Int Charges | 4,426,267.50 |
Apr 1, 2018 | IBRD-79140 | Int Charges | 2,188,795.80 |
Jun 1, 2018 | IBRD-84380 | Int Charges | 5,358,889.00 |
Oct 1, 2015 | IBRD-79140 | Int Charges | 744,125.80 |
Dec 1, 2015 | IBRD-84380 | Int Charges | 151,920.47 |
Apr 1, 2016 | IBRD-79140 | Int Charges | 983,108.30 |
Dec 1, 2016 | IBRD-84380 | Int Charges | 1,632,432.50 |
Apr 30, 2016 | IBRD-79140 | Loan Cancel | 229,145.11 |
Jun 1, 2016 | IBRD-84380 | Int Charges | 234,611.38 |
Jun 14, 2016 | IBRD-84380 | Loan Disb | 59,329,592.00 |
Jun 14, 2016 | IBRD-84380 | Loan Disb | 132,004,248.00 |
Jun 1, 2023 | IBRD-84380 | Int Charges | 744,582.30 |
Jun 1, 2023 | IBRD-84380 | Int Charges | 11,529,093.00 |
Jun 1, 2023 | IBRD-84380 | Loan Repay | 25,150,000.00 |
Dec 1, 2023 | IBRD-84380 | Int Charges | 289,175.47 |
Dec 1, 2023 | IBRD-84380 | Int Charges | 12,792,673.00 |
Dec 1, 2023 | IBRD-84380 | Loan Repay | 25,800,000.00 |
Oct 1, 2023 | IBRD-79140 | Int Charges | 5,163,834.00 |
Oct 1, 2023 | IBRD-79140 | Loan Repay | 5,801,950.50 |
Oct 1, 2023 | IBRD-79140 | Int Charges | 106,538.20 |
Apr 1, 2024 | IBRD-79140 | Loan Repay | 5,955,790.00 |
Apr 1, 2024 | IBRD-79140 | Int Charges | 93,113.17 |
Apr 1, 2024 | IBRD-79140 | Int Charges | 5,514,899.00 |
Jun 1, 2024 | IBRD-84380 | Int Charges | 83,498.57 |
Jun 1, 2024 | IBRD-84380 | Int Charges | 12,815,818.00 |
Jun 1, 2024 | IBRD-84380 | Loan Repay | 26,450,000.00 |
Sep 30, 2014 | IBRD-84380 | Loan Commitment | 500,000,000.00 |
Jun 8, 2010 | IBRD-79140 | Loan Commitment | 220,000,000.00 |
Jun 1, 2021 | IBRD-84380 | Int Charges | 1,921,111.10 |
Apr 1, 2021 | IBRD-79140 | Int Charges | 798,455.94 |
Apr 1, 2021 | IBRD-79140 | Loan Repay | 5,142,638.00 |
Oct 1, 2021 | IBRD-79140 | Int Charges | 752,218.60 |
Oct 1, 2021 | IBRD-79140 | Loan Repay | 5,274,500.50 |
Apr 1, 2022 | IBRD-79140 | Int Charges | 679,161.06 |
Apr 1, 2022 | IBRD-79140 | Loan Repay | 5,406,363.00 |
Jun 1, 2022 | IBRD-84380 | Int Charges | 1,971,666.60 |
Jun 1, 2022 | IBRD-84380 | Loan Repay | 23,950,000.00 |
Dec 1, 2021 | IBRD-84380 | Int Charges | 1,779,166.60 |
Oct 1, 2022 | IBRD-79140 | Int Charges | 2,155,874.50 |
Oct 1, 2022 | IBRD-79140 | Loan Repay | 5,538,225.50 |
Apr 1, 2023 | IBRD-79140 | Int Charges | 246,718.77 |
Apr 1, 2023 | IBRD-79140 | Int Charges | 4,213,620.00 |
Apr 1, 2023 | IBRD-79140 | Loan Repay | 5,670,088.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2017-12-08 |
Monitoring and Evaluation | Moderately Satisfactory | 2017-12-08 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2017-12-08 |
Project Management | Moderately Satisfactory | 2017-12-08 |
Procurement | Moderately Satisfactory | 2017-12-08 |
Financial Management | Moderately Satisfactory | 2017-12-08 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-12-2018 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 08-24-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
% DAK reports submitted online through Web-Based Reporting System | Value | 80.00 | 80.00 | 100.00 |
Date | July 31, 2014 | December 31, 2018 | December 7, 2017 | |
Comment |
% of physical outputs reported, verified, and meeting eligibility criteria | Value | 87.00 | 88.00 | 77.00 |
Date | July 31, 2014 | December 31, 2017 | December 7, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of LGs that receive DAK payment 1 from MoF by March 31. | Value | 54.30 | 60.00 | 5.00 |
Date | June 30, 2010 | December 31, 2018 | December 7, 2017 | |
Comment |
Supplement of MPW Technical Guidelines on Safeguard issued by MPW Ministerial Circular letter | Value | The original MPW Technical Guidelines do not inclu | Issuance of the MPW Supplement Technical Guideline | Issued |
Date | June 30, 2010 | June 30, 2014 | December 7, 2017 | |
Comment |
MoF produce annual M&E reports for the project, mid-term evaluation report and final evaluation report | Value | N/A | Annual and quarterly project report and IFRs, Annu | PIU has submitted the LGDP impact analyses report |
Date | June 30, 2010 | December 31, 2018 | December 7, 2017 | |
Comment |
% of contracts with work completed with documented physical handover by December 31 | Value | 0.00 | 80.00 | 99.00 |
Date | June 30, 2010 | December 31, 2015 | December 7, 2017 | |
Comment |
Contracts with quality of outputs delivered according to contract by December 31 | Value | 0.00 | 45.00 | 25.00 |
Date | June 30, 2010 | December 31, 2018 | December 7, 2017 | |
Comment |
Maintain an issued Supplement of the MPW's Technical Guidelines on Environmental and Safeguards through MPW Circular Letter applicable to all Selected Local Governments in each FY | Value | 20101220 | 20150130 | 20150127 |
Date | December 20, 2010 | December 31, 2018 | January 27, 2015 | |
Comment |
% of LGs with functioning procurement unit (ULP) | Value | 73.00 | 80.00 | 99.60 |
Date | July 31, 2014 | December 31, 2018 | December 7, 2017 | |
Comment |
BPKP submits to PIU a quantitative and qualitative Verification Report consistent with the TORs for the same as specified in the Verification Arrangement by May 31 | Value | No | Yes | Yes |
Date | September 2, 2014 | December 31, 2018 | May 31, 2017 | |
Comment |
Issuance by BPKP of Verification Manual and socialization of BPKP regional representatives by February 28 of each FY | Value | No | Yes | Yes |
Date | September 2, 2014 | December 31, 2018 | March 30, 2017 | |
Comment |