Financier | Commitments |
---|---|
HIPC-Transfers from IDA grants | 1.00 |
Afghanistan Resilience Trust Fund | 60.00 |
P111943
Closed
Fanny Missfeldt-Ringius , Jie Li
Ministry of Finance,Islamic Republic of Afghanistan,GOVERNMENT OF ISLAMIC REPUBLIC OF AFGHANISTAN
October 22, 2008
(as of board presentation)
October 22, 2008
March 19, 2009
US$ 61.00 million
Da Afghanistan Breshna Sherkat (DABS),Da Afghanistan Breshna Sherkat (DABS),Da Afghanistan Breshna Sherkat,MEW - Ministry of Energy and Water
2009
US$ 61.00 million
B
Not Applicable
May 31, 2017
BANK APPROVED
February 28, 2022
Financier | Commitments |
---|---|
HIPC-Transfers from IDA grants | 1.00 |
Afghanistan Resilience Trust Fund | 60.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 1.00 |
IBRD + IDA Commitment | 1.00 |
Lending Instrument | |
---|---|
Grant Amount | 60.00 |
Total Project Cost** | 61.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2017-06-30 |
Project Management | Moderately Satisfactory | 2017-06-30 |
Financial Management | Moderately Satisfactory | 2017-06-30 |
Monitoring and Evaluation | Moderately Satisfactory | 2017-06-30 |
Procurement | Moderately Unsatisfactory | 2017-06-30 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2017-06-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-20-2018 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-18-2019 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Unsatisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Modest | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Distribution lines constructed or rehabilitated under the project | Value | 0.00 | 626.00 | 737.00 |
Date | March 30, 2009 | May 31, 2017 | May 31, 2017 | |
Comment |
Increase in the number of households with metered connections to the grid in the target areas of Charikar, Gulbahar and Jabul-es-Seraj | Value | 0.00 | 12500.00 | 13321.00 |
Date | March 30, 2009 | May 31, 2017 | May 31, 2017 | |
Comment |
Increase in the number of households with metered connections to the grid in the target area of Pul-e-Khumri | Value | 0.00 | 5500.00 | 6987.00 |
Date | March 30, 2009 | May 31, 2017 | May 31, 2017 | |
Comment |
Satisfactory completion of project activities and closing of contracts on time and within budget. | Value | No | Yes | No |
Date | March 30, 2009 | May 31, 2017 | May 31, 2017 | |
Comment |
Total power supply outages in a year as a result of Naghlu switchyard. | Value | 18.00 | 3.00 | 0.00 |
Date | December 31, 2014 | May 31, 2017 | May 31, 2017 | |
Comment |
Distribution lines rehabilitated under the project | Value | 0.00 | 626.00 | 737.00 |
Date | March 30, 2009 | May 31, 2017 | May 31, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Progress in installation work at Charikar, Gulbahar and Jabul-es-Seraj | Value | 0.00 | 23000.00 | 24667.00 |
Date | March 30, 2009 | May 31, 2017 | May 31, 2017 | |
Comment |
Progress in installation work at Pul-e-Khumri | Value | 0.00 | 17000.00 | 17335.00 |
Date | March 30, 2009 | May 31, 2017 | May 31, 2017 | |
Comment |
Timely submission of quarterly progress reports and quarterly interim unaudited financial management reports acceptable to the Bank | Value | No | Yes | Yes |
Date | March 30, 2009 | May 31, 2017 | May 31, 2017 | |
Comment |
Switchyards rehabilitated with all equipment installed. | Value | 1.00 | 2.00 | 2.00 |
Date | December 31, 2014 | May 31, 2017 | May 31, 2017 | |
Comment |