Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IDA Fund | 70.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 3.15 |
Global Environment Facility (GEF) | 7.49 |
Borrower/Recipient | 16.85 |
P112061
Closed
Edward Bresnyan
N/A
April 24, 2009
(as of board presentation)
August 4, 2009
November 12, 2009
US$ 97.49 million
N/A
2010
US$ 7.49 million
C
Not Applicable
August 31, 2013
BANK APPROVED
April 10, 2014
Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IDA Fund | 70.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 3.15 |
Global Environment Facility (GEF) | 7.49 |
Borrower/Recipient | 16.85 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 7.49 |
Total Project Cost** | 97.49 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2013-06-20 |
Overall | Low | 2013-06-20 |
Summary Global Objective Rating | Satisfactory | 2013-06-20 |
Project Management | Satisfactory | 2013-06-20 |
Financial Management | Satisfactory | 2013-06-20 |
Monitoring and Evaluation | Satisfactory | 2013-06-20 |
Overall Implementation Progress (IP) | Satisfactory | 2013-06-20 |
Counterpart Funding | Satisfactory | 2013-06-20 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-25-2014 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |