Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
P112369
Closed
Sawkut Rojid
N/A
Mauritius
February 19, 2009
(as of board presentation)
March 31, 2009
May 22, 2009
US$ 100.00 million
N/A
2009
US$ 100.00 million
N/A
August 22, 2023
December 31, 2011
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 100.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 100.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 15, 2015 | IBRD-76790 | Int Charges | 62,133.16 |
Jun 15, 2015 | IBRD-76790 | Loan Repay | 2,497.50 |
Jun 15, 2018 | IBRD-76790 | Loan Repay | 1,236,015.20 |
Dec 15, 2018 | IBRD-76790 | Int Charges | 172.40 |
Dec 15, 2018 | IBRD-76790 | Int Charges | 68,794.31 |
Dec 15, 2018 | IBRD-76790 | Loan Repay | 2,132.71 |
Dec 15, 2018 | IBRD-76790 | Loan Repay | 850,949.50 |
Dec 15, 2018 | IBRD-76790 | Int Charges | 317.87 |
Dec 15, 2018 | IBRD-76790 | Int Charges | 126,829.15 |
Dec 15, 2018 | IBRD-76790 | Loan Repay | 2,926.92 |
Dec 15, 2018 | IBRD-76790 | Loan Repay | 1,167,841.10 |
Dec 15, 2018 | IBRD-76790 | Loan Repay | 2,522.65 |
Dec 15, 2018 | IBRD-76790 | Loan Repay | 1,006,536.20 |
Jun 15, 2019 | IBRD-76790 | Loan Repay | 1,175,653.80 |
Jun 15, 2019 | IBRD-76790 | Int Charges | 163.89 |
Jun 15, 2019 | IBRD-76790 | Int Charges | 65,398.27 |
Jun 15, 2019 | IBRD-76790 | Int Charges | 154,993.50 |
Jun 15, 2019 | IBRD-76790 | Loan Repay | 2,946.50 |
Jun 15, 2019 | IBRD-76790 | Loan Repay | 2,128.65 |
Jun 15, 2019 | IBRD-76790 | Loan Repay | 849,328.40 |
Jun 15, 2019 | IBRD-76790 | Loan Repay | 2,517.84 |
Jun 15, 2019 | IBRD-76790 | Loan Repay | 1,004,618.60 |
Jun 15, 2019 | IBRD-76790 | Int Charges | 388.44 |
Dec 15, 2016 | IBRD-76790 | Loan Repay | 1,967.36 |
Dec 15, 2016 | IBRD-76790 | Loan Repay | 784,972.75 |
Dec 15, 2016 | IBRD-76790 | Loan Repay | 2,327.06 |
Dec 15, 2016 | IBRD-76790 | Loan Repay | 1,161,144.60 |
Dec 15, 2016 | IBRD-76790 | Int Charges | 87,672.84 |
Dec 15, 2016 | IBRD-76790 | Int Charges | 321.38 |
Jun 15, 2017 | IBRD-76790 | Loan Repay | 841,939.00 |
Jun 15, 2017 | IBRD-76790 | Loan Repay | 2,495.94 |
Jun 15, 2017 | IBRD-76790 | Loan Repay | 995,878.20 |
Jun 15, 2017 | IBRD-76790 | Loan Repay | 2,959.20 |
Jun 15, 2017 | IBRD-76790 | Loan Repay | 1,180,722.60 |
Jun 15, 2017 | IBRD-76790 | Int Charges | 265.93 |
Jun 15, 2017 | IBRD-76790 | Int Charges | 106,106.50 |
Jun 15, 2017 | IBRD-76790 | Int Charges | 194.96 |
Jun 15, 2017 | IBRD-76790 | Int Charges | 77,775.72 |
Jun 15, 2017 | IBRD-76790 | Loan Repay | 2,110.13 |
Dec 15, 2021 | IBRD-76790 | Int Charges | 49,099.36 |
Dec 15, 2021 | IBRD-76790 | Loan Repay | 2,129.78 |
Dec 15, 2021 | IBRD-76790 | Loan Repay | 849,780.80 |
Dec 15, 2021 | IBRD-76790 | Loan Repay | 2,519.18 |
Dec 15, 2021 | IBRD-76790 | Loan Repay | 1,005,153.75 |
Dec 15, 2021 | IBRD-76790 | Int Charges | 102.48 |
Dec 15, 2021 | IBRD-76790 | Int Charges | 40,895.80 |
Dec 15, 2021 | IBRD-76790 | Loan Repay | 3,091.26 |
Dec 15, 2021 | IBRD-76790 | Loan Repay | 1,233,411.00 |
Dec 15, 2022 | IBRD-76790 | Int Charges | 491.17 |
Dec 15, 2022 | IBRD-76790 | Int Charges | 195,979.28 |
Dec 15, 2022 | IBRD-76790 | Loan Repay | 2,874.82 |
Dec 15, 2022 | IBRD-76790 | Loan Repay | 1,147,054.10 |
Dec 15, 2022 | IBRD-76790 | Int Charges | 49.20 |
Dec 15, 2022 | IBRD-76790 | Int Charges | 19,633.01 |
Jun 15, 2015 | IBRD-76790 | Loan Repay | 996,502.50 |
Jun 15, 2015 | IBRD-76790 | Int Charges | 75.09 |
Jun 15, 2015 | IBRD-76790 | Int Charges | 29,966.14 |
Jun 15, 2015 | IBRD-76790 | Loan Repay | 2,119.96 |
Dec 15, 2013 | IBRD-76790 | Int Charges | 114.77 |
Dec 15, 2013 | IBRD-76790 | Int Charges | 45,805.61 |
Dec 15, 2013 | IBRD-76790 | Int Charges | 371.21 |
Dec 15, 2013 | IBRD-76790 | Int Charges | 148,114.25 |
Dec 15, 2013 | IBRD-76790 | Int Charges | 179.20 |
Dec 15, 2013 | IBRD-76790 | Int Charges | 71,495.83 |
Oct 6, 2016 | IBRD-76790 | Loan Disb | -24,942,488.00 |
Oct 6, 2016 | IBRD-76790 | Loan Disb | 24,942,488.00 |
Oct 12, 2016 | IBRD-76790 | Loan Disb | 24,595,350.00 |
Oct 12, 2016 | IBRD-76790 | Loan Disb | -24,595,350.00 |
Oct 12, 2016 | IBRD-76790 | Loan Disb | 24,595,350.00 |
Oct 12, 2016 | IBRD-76790 | Loan Disb | -62,512.50 |
Oct 12, 2016 | IBRD-76790 | Loan Disb | 61,642.48 |
Dec 15, 2016 | IBRD-76790 | Int Charges | 128,229.70 |
Dec 15, 2016 | IBRD-76790 | Loan Repay | 2,910.14 |
Dec 15, 2016 | IBRD-76790 | Loan Repay | 928,496.30 |
Oct 6, 2016 | IBRD-76790 | Loan Disb | 62,512.50 |
Dec 15, 2016 | IBRD-76790 | Int Charges | 2.49 |
Dec 15, 2016 | IBRD-76790 | Int Charges | 998.78 |
Dec 15, 2016 | IBRD-76790 | Int Charges | 66.25 |
Dec 15, 2016 | IBRD-76790 | Int Charges | 26,435.83 |
Oct 6, 2016 | IBRD-76790 | Loan Disb | -62,512.50 |
Oct 6, 2016 | IBRD-76790 | Loan Disb | 62,512.50 |
Oct 6, 2016 | IBRD-76790 | Loan Disb | -62,512.50 |
Oct 6, 2016 | IBRD-76790 | Loan Disb | -24,942,488.00 |
Dec 15, 2016 | IBRD-76790 | Int Charges | 219.72 |
Dec 15, 2015 | IBRD-76790 | Loan Repay | 3,532.86 |
Dec 15, 2015 | IBRD-76790 | Loan Repay | 1,409,612.60 |
Dec 15, 2015 | IBRD-76790 | Int Charges | 195.59 |
Dec 15, 2020 | IBRD-76790 | Int Charges | 66,922.44 |
Dec 15, 2020 | IBRD-76790 | Loan Repay | 3,118.06 |
Dec 15, 2020 | IBRD-76790 | Loan Repay | 1,244,106.80 |
Jun 15, 2021 | IBRD-76790 | Loan Repay | 1,080,741.00 |
Jun 15, 2021 | IBRD-76790 | Int Charges | 89.23 |
Jun 15, 2021 | IBRD-76790 | Int Charges | 35,601.13 |
Jun 15, 2021 | IBRD-76790 | Loan Repay | 3,283.21 |
Jun 15, 2021 | IBRD-76790 | Loan Repay | 1,310,002.20 |
Jun 15, 2021 | IBRD-76790 | Int Charges | 141.12 |
Jun 15, 2021 | IBRD-76790 | Int Charges | 56,304.01 |
Jun 15, 2021 | IBRD-76790 | Loan Repay | 2,289.94 |
Jun 15, 2021 | IBRD-76790 | Loan Repay | 913,684.00 |
Jun 15, 2021 | IBRD-76790 | Loan Repay | 2,708.62 |
Jun 15, 2022 | IBRD-76790 | Loan Repay | 2,818.65 |
Jun 15, 2022 | IBRD-76790 | Loan Repay | 1,124,639.40 |
Jun 15, 2022 | IBRD-76790 | Int Charges | 106.86 |
Jun 15, 2022 | IBRD-76790 | Int Charges | 42,629.98 |
Jun 15, 2022 | IBRD-76790 | Loan Repay | 1,980.96 |
Jun 15, 2022 | IBRD-76790 | Loan Repay | 790,401.70 |
Jun 15, 2022 | IBRD-76790 | Loan Repay | 2,343.15 |
Jun 15, 2022 | IBRD-76790 | Loan Repay | 934,917.90 |
Dec 15, 2019 | IBRD-76790 | Int Charges | 154.48 |
Dec 15, 2019 | IBRD-76790 | Int Charges | 61,642.33 |
Dec 15, 2019 | IBRD-76790 | Loan Repay | 2,111.83 |
Dec 15, 2019 | IBRD-76790 | Loan Repay | 842,617.60 |
Dec 15, 2019 | IBRD-76790 | Loan Repay | 2,497.95 |
Dec 15, 2019 | IBRD-76790 | Loan Repay | 996,680.90 |
Dec 15, 2019 | IBRD-76790 | Int Charges | 348.38 |
Dec 15, 2019 | IBRD-76790 | Int Charges | 138,999.89 |
Dec 15, 2019 | IBRD-76790 | Loan Repay | 3,120.74 |
Dec 15, 2019 | IBRD-76790 | Loan Repay | 1,245,176.40 |
Jun 15, 2020 | IBRD-76790 | Loan Repay | 1,163,516.40 |
Jun 15, 2020 | IBRD-76790 | Int Charges | 147.31 |
Jun 15, 2020 | IBRD-76790 | Int Charges | 58,776.77 |
Jun 15, 2020 | IBRD-76790 | Loan Repay | 2,125.34 |
Jun 15, 2020 | IBRD-76790 | Loan Repay | 848,008.90 |
Jun 15, 2020 | IBRD-76790 | Loan Repay | 2,513.93 |
Jun 15, 2020 | IBRD-76790 | Loan Repay | 1,003,057.90 |
Jun 15, 2020 | IBRD-76790 | Int Charges | 308.41 |
Jun 15, 2020 | IBRD-76790 | Int Charges | 123,058.88 |
Jun 15, 2020 | IBRD-76790 | Loan Repay | 2,916.08 |
Dec 15, 2020 | IBRD-76790 | Loan Repay | 2,297.88 |
Dec 15, 2020 | IBRD-76790 | Loan Repay | 916,850.90 |
Dec 15, 2020 | IBRD-76790 | Loan Repay | 2,718.01 |
Jun 15, 2018 | IBRD-76790 | Loan Repay | 1,034,095.44 |
Jun 15, 2018 | IBRD-76790 | Int Charges | 185.56 |
Jun 15, 2018 | IBRD-76790 | Int Charges | 74,038.77 |
Jun 15, 2018 | IBRD-76790 | Loan Repay | 2,191.11 |
Jun 15, 2018 | IBRD-76790 | Loan Repay | 874,248.75 |
Jun 15, 2018 | IBRD-76790 | Int Charges | 282.44 |
Jun 15, 2018 | IBRD-76790 | Int Charges | 112,692.63 |
Jun 15, 2018 | IBRD-76790 | Loan Repay | 3,097.78 |
Jun 15, 2024 | IBRD-76790 | Int Charges | 5.53 |
Jun 15, 2024 | IBRD-76790 | Int Charges | 77.95 |
Jun 15, 2024 | IBRD-76790 | Int Charges | 171,914.58 |
Jun 15, 2024 | IBRD-76790 | Int Charges | 31,102.62 |
Jun 15, 2024 | IBRD-76790 | Int Charges | 888.21 |
Jun 15, 2024 | IBRD-76790 | Int Charges | 2,209.93 |
Jun 15, 2024 | IBRD-76790 | Int Charges | 354,401.25 |
Jun 15, 2024 | IBRD-76790 | Loan Repay | 2,961.89 |
Jun 15, 2024 | IBRD-76790 | Loan Repay | 2,021.69 |
Jun 15, 2024 | IBRD-76790 | Loan Repay | 806,650.80 |
Jun 15, 2024 | IBRD-76790 | Loan Repay | 2,391.32 |
Jun 15, 2024 | IBRD-76790 | Loan Repay | 954,138.00 |
Jun 15, 2024 | IBRD-76790 | Int Charges | 430.86 |
Jun 15, 2024 | IBRD-76790 | Loan Repay | 1,181,792.10 |
Dec 15, 2023 | IBRD-76790 | Int Charges | 916.96 |
Dec 15, 2023 | IBRD-76790 | Int Charges | 365,858.00 |
Dec 15, 2023 | IBRD-76790 | Loan Repay | 2,977.04 |
Dec 15, 2023 | IBRD-76790 | Loan Repay | 1,187,837.60 |
Jun 15, 2023 | IBRD-76790 | Int Charges | 16,496.18 |
Jun 15, 2023 | IBRD-76790 | Int Charges | 755.19 |
Jun 15, 2023 | IBRD-76790 | Int Charges | 301,335.56 |
Jun 15, 2023 | IBRD-76790 | Loan Repay | 2,952.68 |
Jun 15, 2023 | IBRD-76790 | Loan Repay | 1,178,118.40 |
Jun 15, 2023 | IBRD-76790 | Int Charges | 94.78 |
Dec 15, 2023 | IBRD-76790 | Int Charges | 16.28 |
Dec 15, 2023 | IBRD-76790 | Int Charges | 186,887.55 |
Dec 15, 2023 | IBRD-76790 | Int Charges | 468.40 |
Dec 15, 2023 | IBRD-76790 | Int Charges | 87.91 |
Dec 15, 2023 | IBRD-76790 | Int Charges | 35,069.98 |
Dec 15, 2023 | IBRD-76790 | Loan Repay | 2,072.90 |
Dec 15, 2023 | IBRD-76790 | Loan Repay | 827,084.80 |
Dec 15, 2023 | IBRD-76790 | Loan Repay | 2,451.90 |
Dec 15, 2023 | IBRD-76790 | Loan Repay | 978,308.06 |
Jun 15, 2022 | IBRD-76790 | Int Charges | 126.23 |
Jun 15, 2022 | IBRD-76790 | Int Charges | 50,353.59 |
Dec 15, 2021 | IBRD-76790 | Int Charges | 123.07 |
Mar 31, 2009 | IBRD-76790 | Loan Commitment | 30,000,000.00 |
Mar 31, 2009 | IBRD-76790 | Loan Commitment | 30,000,000.00 |
Mar 31, 2009 | IBRD-76790 | Loan Commitment | 40,000,000.00 |
Jun 15, 2023 | IBRD-76790 | Int Charges | 37,806.64 |
Jun 15, 2023 | IBRD-76790 | Loan Repay | 2,048.90 |
Jun 15, 2023 | IBRD-76790 | Loan Repay | 817,508.75 |
Jun 15, 2023 | IBRD-76790 | Loan Repay | 2,423.51 |
Jun 15, 2023 | IBRD-76790 | Loan Repay | 966,981.10 |
Jun 15, 2023 | IBRD-76790 | Int Charges | 343.92 |
Jun 15, 2023 | IBRD-76790 | Int Charges | 137,226.20 |
Jun 15, 2023 | IBRD-76790 | Int Charges | 41.36 |
Dec 15, 2023 | IBRD-76790 | Int Charges | 6,493.90 |
Dec 15, 2017 | IBRD-76790 | Int Charges | 241.60 |
Dec 15, 2017 | IBRD-76790 | Int Charges | 96,394.07 |
Dec 15, 2017 | IBRD-76790 | Loan Repay | 3,122.84 |
Dec 15, 2017 | IBRD-76790 | Loan Repay | 1,246,013.50 |
Dec 15, 2017 | IBRD-76790 | Int Charges | 197.37 |
Dec 15, 2017 | IBRD-76790 | Int Charges | 78,764.70 |
Dec 15, 2017 | IBRD-76790 | Loan Repay | 2,229.75 |
Dec 15, 2017 | IBRD-76790 | Loan Repay | 889,668.50 |
Dec 15, 2017 | IBRD-76790 | Loan Repay | 2,637.43 |
Dec 15, 2017 | IBRD-76790 | Loan Repay | 1,052,334.50 |
Jun 15, 2018 | IBRD-76790 | Loan Repay | 2,591.72 |
Jun 15, 2016 | IBRD-76790 | Loan Repay | 2,497.50 |
Jun 15, 2016 | IBRD-76790 | Loan Repay | 996,502.50 |
Jun 15, 2016 | IBRD-76790 | Int Charges | 384.31 |
Jun 15, 2016 | IBRD-76790 | Int Charges | 153,351.77 |
Jun 15, 2016 | IBRD-76790 | Loan Repay | 3,308.97 |
Jun 15, 2016 | IBRD-76790 | Loan Repay | 1,320,279.50 |
Jun 15, 2016 | IBRD-76790 | Int Charges | 33.68 |
Jun 15, 2016 | IBRD-76790 | Int Charges | 13,438.00 |
Jun 15, 2016 | IBRD-76790 | Loan Repay | 2,121.09 |
Jun 15, 2016 | IBRD-76790 | Loan Repay | 846,312.30 |
Jun 15, 2016 | IBRD-76790 | Int Charges | 297.40 |
Jun 15, 2016 | IBRD-76790 | Int Charges | 118,670.90 |
Oct 12, 2016 | IBRD-76790 | Loan Disb | -61,642.48 |
Oct 12, 2016 | IBRD-76790 | Loan Disb | 61,642.48 |
Oct 12, 2016 | IBRD-76790 | Loan Disb | -24,942,488.00 |
Oct 6, 2016 | IBRD-76790 | Loan Disb | 24,942,488.00 |
Dec 15, 2022 | IBRD-76790 | Int Charges | 100.57 |
Dec 15, 2022 | IBRD-76790 | Int Charges | 40,127.84 |
Dec 15, 2022 | IBRD-76790 | Loan Repay | 2,007.80 |
Dec 15, 2022 | IBRD-76790 | Loan Repay | 801,108.80 |
Dec 15, 2022 | IBRD-76790 | Loan Repay | 2,374.89 |
Dec 15, 2022 | IBRD-76790 | Loan Repay | 947,582.60 |
Dec 15, 2020 | IBRD-76790 | Loan Repay | 1,084,486.90 |
Dec 15, 2020 | IBRD-76790 | Int Charges | 9.97 |
Dec 15, 2020 | IBRD-76790 | Int Charges | 3,968.58 |
Dec 15, 2020 | IBRD-76790 | Int Charges | 150.44 |
Dec 15, 2020 | IBRD-76790 | Int Charges | 60,023.77 |
Dec 15, 2020 | IBRD-76790 | Int Charges | 167.73 |
Dec 15, 2015 | IBRD-76790 | Int Charges | 78,045.60 |
Dec 15, 2015 | IBRD-76790 | Loan Repay | 2,497.50 |
Dec 15, 2015 | IBRD-76790 | Loan Repay | 996,502.50 |
Dec 15, 2015 | IBRD-76790 | Int Charges | 54.31 |
Dec 15, 2015 | IBRD-76790 | Int Charges | 21,671.03 |
Dec 15, 2015 | IBRD-76790 | Loan Repay | 2,080.46 |
Dec 15, 2015 | IBRD-76790 | Loan Repay | 830,100.90 |
Dec 15, 2015 | IBRD-76790 | Int Charges | 406.97 |
Dec 15, 2015 | IBRD-76790 | Int Charges | 162,376.60 |
Dec 15, 2014 | IBRD-76790 | Loan Repay | 936,983.25 |
Dec 15, 2014 | IBRD-76790 | Int Charges | 143.74 |
Dec 15, 2014 | IBRD-76790 | Int Charges | 57,350.73 |
Dec 15, 2014 | IBRD-76790 | Loan Repay | 2,497.50 |
Dec 15, 2014 | IBRD-76790 | Int Charges | 51,159.89 |
Dec 15, 2014 | IBRD-76790 | Loan Repay | 2,348.34 |
Jun 15, 2014 | IBRD-76790 | Int Charges | 396.38 |
Jun 15, 2014 | IBRD-76790 | Int Charges | 158,159.05 |
Jun 15, 2014 | IBRD-76790 | Loan Repay | 3,951.05 |
Jun 15, 2014 | IBRD-76790 | Loan Repay | 1,576,467.00 |
Jun 15, 2014 | IBRD-76790 | Int Charges | 155.43 |
Jun 15, 2014 | IBRD-76790 | Int Charges | 62,006.08 |
Jun 15, 2014 | IBRD-76790 | Loan Repay | 2,559.05 |
Jun 15, 2014 | IBRD-76790 | Loan Repay | 1,021,056.50 |
Jun 15, 2014 | IBRD-76790 | Int Charges | 155.47 |
Jun 15, 2014 | IBRD-76790 | Int Charges | 62,027.90 |
Jun 15, 2014 | IBRD-76790 | Loan Repay | 2,497.50 |
Jun 15, 2014 | IBRD-76790 | Loan Repay | 996,502.50 |
Dec 15, 2014 | IBRD-76790 | Int Charges | 128.23 |
Dec 15, 2014 | IBRD-76790 | Loan Repay | 996,502.50 |
Dec 15, 2014 | IBRD-76790 | Int Charges | 409.26 |
Dec 15, 2014 | IBRD-76790 | Int Charges | 163,288.62 |
Dec 15, 2014 | IBRD-76790 | Loan Repay | 3,651.63 |
Dec 15, 2014 | IBRD-76790 | Loan Repay | 1,456,999.60 |
Jun 15, 2015 | IBRD-76790 | Int Charges | 155.72 |
Jun 15, 2015 | IBRD-76790 | Loan Repay | 845,859.90 |
Jun 15, 2015 | IBRD-76790 | Int Charges | 393.84 |
Jun 15, 2015 | IBRD-76790 | Int Charges | 157,140.27 |
Jun 15, 2015 | IBRD-76790 | Loan Repay | 3,612.58 |
Jun 15, 2015 | IBRD-76790 | Loan Repay | 1,441,421.00 |
Name | Review | Date |
---|---|---|
Program Management | Highly Satisfactory | 2010-02-25 |
Progress towards achievement of PDO | Highly Satisfactory | 2010-02-25 |
Monitoring and Evaluation | Satisfactory | 2010-02-25 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-09-2012 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Highly Satisfactory |
Borrower Performance | Highly Satisfactory |
Government Performance | Highly Satisfactory |
Implementing Agency | Highly Satisfactory |
INDICATOR | ICR REVIEW: 10-23-2012 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Highly Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Highly Satisfactory | N/a |
Borrower Performance | Highly Satisfactory | N/a |
Government Performance | Highly Satisfactory | N/a |
Implementing Agency | Highly Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | High | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduce primary spending as % GDP. | Value | 21.6 | 19.6 | 20.1 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
Reduce tax expenditures as % of GDP | Value | 3.5 | 3.1 | <3.5 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
Reduce PEFA indicator PI-2 | Value | 7.8 | <7.8 | <7.8 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
Stabilize revenue as % GDP above 19.0. | Value | 20.1 | 19.3 | > 19.0 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
Eliminate 95% of tariff lines | Value | 79 | 87 | 95 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
Unify regulatory regime across EPZ, non-EPZ sectors | Value | No | Yes, exc. labor | Yes |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
Raise exports as % of GDP | Value | 60.6 | 62.9 | >60.6 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
Achieve top ten ranking in Doing Business | Value | 32 | 27 | <10 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
Increase investment in emerging sectors- Rl. est., renting and o/ business- Transp., stor. and comm.- Fin. intermed.Time tostart business (days) | Value | 6181,1202,11946 | 6581,8082,1097 | >618>1,120>2,119<3 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
SME registrations | Value | 0 | 919 | >0 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
No. work and residency permits- professional | Value | 0 | 613 | >0 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
Raise primary completion rate | Value | 64.9 | 68 | >64.9 |
Date | June 1, 2005 | June 1, 2008 | June 1, 2010 | |
Comment |
Raise secondary completion rate | Value | 78.4 | 78.9 | >78.4 |
Date | June 1, 2005 | June 1, 2008 | June 1, 2010 | |
Comment |
Train 12,000 workers under Empowerment Programme. | Value | 0 | 821 | 12000 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
Place 600 women in jobs | Value | 0 | 45 | 600 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
Complete 5 tourist villages | Value | 0 | 0 | 5 |
Date | June 1, 2005 | June 1, 2007 | June 1, 2010 | |
Comment |
GDP growth | Value | 3.7 | 6.8 | 5 |
Date | June 1, 2005 | June 1, 2008 | June 1, 2010 | |
Comment |
Unemployment Rate | Value | 9.5 | 7.6 | <9.5 |
Date | June 1, 2006 | June 1, 2008 | June 1, 2010 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Macroeconomic Stability | Value | Satisfactory | Satisfactory | Satisfactory |
Date | June 30, 2006 | January 1, 2009 | June 30, 2010 | |
Comment |