COMMUNITY RESILIENCE TO CLIMATE AND DISASTER RISK IN SOLOMON ISLANDS PROJECT

Abstract*

The development objective of the Community Resilience to Climate and Disaster Risk Project for Solomon Islands (CRISP) is to increase the capacity of selected rural communities to manage natural hazards and climate change risks. The project has four components. The first component, integration of climate change adaptation (CCA) and disaster risk reduction (DRR) in government policies and operations objective is to support policy development, capacity...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase the resilience of selected rural communities to the impacts of natural hazards and climate change

Key Details

Project Details

  • P112613

  • Closed

  • Tevi Obed

  • Solomon Islands

  • Solomon Islands

  • March 6, 2014

  • (as of board presentation)

    March 6, 2014

  • April 1, 2014

  • US$ 9.10 million

  • Ministry of Environment, Climate Change, Disaster Management and Meteorology

  • East Asia And Pacific

  • 2014

  • US$ 9.10 million

  • B

  • August 15, 2024

  • May 28, 2020

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Environment Facility (GEF) 7.30
Global Facility for Disaster Reduction and Recovery 1.80

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 9.10
Total Project Cost** 9.10

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2020-05-30
Overall Implementation Progress (IP) Moderately Satisfactory 2020-05-30
Summary Global Objective Rating Moderately Satisfactory 2020-05-30
Procurement Satisfactory 2020-05-30
Project Management Moderately Satisfactory 2020-05-30
Financial Management Moderately Satisfactory 2020-05-30
Overall Safeguards Rating Satisfactory 2020-05-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 10-28-2020
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-12-2021PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of beneficiaries in areas targeted under the program that benefit from CCA and/or DRR investments (with a target of at least48% of the total beneficiaries being female)Value1000.0068878.0053400.00
    DateJune 1, 2014May 28, 2020May 30, 2018
    Comment
  • Percentage of targeted communities which demonstrate capacity to implement CBDRM/V&A plans to manage the impact of natural hazards and climate change.Value0.0097.000.00
    DateJune 1, 2014May 28, 2020
    Comment
  • Number of ministries with activities in their annual work programs including resilience measures for climate and disaster riskValue0.003.000.00
    DateJune 1, 2014May 28, 2020
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • The NDC and the NDC Committees are operating and are effectiveValueCommittees exists in NDRMP but not operationalThe NDC and the NDC Committees are operating and a
    DateJune 1, 2014May 28, 2020
    Comment
  • Volcano/Seismic early warning systems are installed and operating.Value0.007.007.00
    DateJune 1, 2014May 28, 2020May 30, 2019
    Comment
  • Number of subprojects completed under the community-led DRR/CCA investmentsValue0.0065.0059.00
    DateJune 1, 2014May 28, 2020May 30, 2019
    Comment
  • The PCC is meeting at least once per year and provides oversight on the project.Value0The PCC continues to meet
    DateJune 1, 2014May 28, 2020
    Comment
  • MECDM data base for Risk Information Management system strengthenedValueSome data is being assembled into MapInfoMECDM data base for Risk Information Management sy
    DateJune 1, 2014May 28, 2020
    Comment
  • Number of sub-projects completed under Provincial Government led DRM/CCA investments.Value0.005.000.00
    DateJune 1, 2014May 28, 2020
    Comment
  • Program components are managed and monitored effectively.ValueNilProgram components are managed and monitored effec
    DateOctober 11, 2019May 28, 2020
    Comment
  • National Disaster Council adopts the Framework for Resilient Development outlined in the 2017 NDM Plan for integration of climate and disaster riskValueSeparate DRM and CCA strategies/ plansNational Disaster Council adopts the Framework forNational Disaster Council adopts the Framework for
    DateJune 1, 2014May 28, 2020May 30, 2018
    Comment
  • Number of Community Based Disaster Risk Management (CBDRM) Plans developed.Value0.0070.0059.00
    DateJune 1, 2014May 28, 2020May 30, 2018
    Comment
  • Percentage of women involved in decisions during preparation and implementation of community-led projectsValue0.0038.000.00
    DateJune 1, 2014October 11, 2019
    Comment