Financier | Commitments |
---|---|
Free-standing Single Purpose Trust Fund | 7.49 |
P112713
Closed
Stepan Anatolievich Titov
Ministry of Finance
December 16, 2009
(as of board presentation)
December 16, 2009
December 16, 2009
US$ 7.49 million
Ministry of Finance
2010
US$ 7.49 million
A
Not Applicable
May 31, 2015
BANK APPROVED
April 4, 2015
Financier | Commitments |
---|---|
Free-standing Single Purpose Trust Fund | 7.49 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 7.49 |
Total Project Cost** | 7.49 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2015-05-06 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2015-05-06 |
Progress towards achievement of PDO | Moderately Satisfactory | 2015-05-06 |
Monitoring and Evaluation | Moderately Satisfactory | 2015-05-06 |
Procurement | Moderately Satisfactory | 2015-05-06 |
Project Management | Moderately Satisfactory | 2015-05-06 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-17-2015 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Substantial |
Bank Performance | Moderately Unsatisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 06-28-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Substantial | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Modest | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
MOF publishes reports (on its website) of draft budgets, budget outturns compared to the approved and revised budgets whenever suchreports are made available to Parliament. | Value | PEFA Indcator2-C6-A7-D8-B11-B12-C+21-D | Preliminary PEFA assessment shows the following re | PEFA Indicator:2-B6-A7-C8-A11-A12-B21-C+ |
Date | December 16, 2009 | March 1, 2015 | May 31, 2015 | |
Comment |
Expenditure classification used in MTBF is consistent with the expenditure classification of the annual budget. | Value | MTBF includes forecast expenditures for the main 1 | Program classification was developed and has been | MTBF for 2015-2017 includes program classification |
Date | December 16, 2009 | March 1, 2015 | May 31, 2015 | |
Comment |
Review of the scope of all major systems of internal control in public bodies and agencies of KR which clarify the formal responsibility, processes, structure and format of instructions. | Value | No comprehensive analysis or description of the pu | "Ethical standards of internal auditors" and "Stan | Training materials and manuals produced for intern |
Date | December 16, 2009 | March 1, 2015 | May 31, 2015 | |
Comment |
Capacity | Value | Training for PFM is weak. Very few staff have core | The training plan for 2013-2014 has been implement | Consistent annual training plan in place. At least |
Date | December 16, 2009 | March 1, 2015 | May 31, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Budget Code is prepared which will include the MTBF proceedure including the regulations related to sectoral ceilings. | Value | First Draft prepared in June/July 2012 | In March 2015 a consolidated version of the Budget | Final draft of the Budget Code to be presented to |
Date | June 30, 2012 | March 6, 2015 | May 31, 2015 | |
Comment |