China Wuhan Second Urban Transport

Abstract*

The development objective of the Wuhan Second Urban Transport Project for China is to assist the municipality of Wuhan to enhance mobility for passenger trips within and to the central area of Wuhan in an environmentally sustainable, integrated, and safe manner. There are five components to the project. The first component of the project is public transport. This component improvements including: (i) strengthening public transport route rationalization...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to assist the Borrower's Municipality of Wuhan to enhance mobility for passenger trips within and to the central area of Wuhan in an environmentally sustainable, integrated and safe manner.

Key Details

Project Details

  • P112838

  • Closed

  • Arturo Ardila Gomez

  • People's Republic of China

  • China

  • February 25, 2009

  • (as of board presentation)

    March 30, 2010

  • September 7, 2010

  • US$ 1173.30 million

  • Wuhan Urban Construction Utilization of Foreign Investment Project Management Office

  • East Asia and Pacific

  • 2010

  • US$ 50.00 million

  • B

  • July 15, 2021

  • August 31, 2018

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 510.71
International Bank for Reconstruction and Development 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 50.00
IDA Commitment N/A
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 1173.30

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 15, 2015 IBRD-78640 Int Charges 191,646.66
Feb 19, 2014 IBRD-78640 Loan Disb 3,581,680.80
Mar 15, 2014 IBRD-78640 Int Charges 101,588.18
Aug 8, 2014 IBRD-78640 Loan Disb 3,121,341.00
Nov 26, 2014 IBRD-78640 Loan Disb 4,141,562.00
Dec 10, 2013 IBRD-78640 Loan Disb 2,078,546.00
Nov 6, 2013 IBRD-78640 Loan Disb 5,735,100.50
Sep 15, 2013 IBRD-78640 Int Charges 7,391.81
Sep 15, 2013 IBRD-78640 Int Charges 92,688.80
Feb 19, 2014 IBRD-78640 Loan Disb 2,822,067.00
Mar 30, 2010 IBRD-78640 Loan Commitment 100,000,000.00
Mar 15, 2023 IBRD-78640 Int Charges 65,371.61
Mar 15, 2023 IBRD-78640 Int Charges 1,301,765.50
Mar 15, 2023 IBRD-78640 Loan Repay 3,575,565.20
Sep 15, 2023 IBRD-78640 Int Charges 20,524.55
Sep 15, 2023 IBRD-78640 Int Charges 1,412,771.10
Sep 15, 2023 IBRD-78640 Loan Repay 3,575,565.20
Mar 15, 2024 IBRD-78640 Int Charges 25,737.09
Mar 15, 2024 IBRD-78640 Int Charges 1,462,840.60
Mar 15, 2024 IBRD-78640 Loan Repay 3,575,565.20
Sep 15, 2021 IBRD-78640 Int Charges 233,935.14
Sep 15, 2021 IBRD-78640 Loan Repay 3,575,565.20
Mar 15, 2022 IBRD-78640 Int Charges 208,173.11
Mar 15, 2022 IBRD-78640 Loan Repay 3,575,565.20
Sep 15, 2022 IBRD-78640 Int Charges 479,305.00
Sep 15, 2022 IBRD-78640 Loan Repay 3,575,565.20
Sep 15, 2019 IBRD-78640 Int Charges 1,280,225.20
Sep 15, 2019 IBRD-78640 Loan Repay 3,575,565.20
Mar 15, 2020 IBRD-78640 Int Charges 965,540.75
Mar 15, 2020 IBRD-78640 Loan Repay 3,575,565.20
Sep 15, 2020 IBRD-78640 Int Charges 446,564.30
Sep 15, 2020 IBRD-78640 Loan Repay 3,575,565.20
Mar 15, 2021 IBRD-78640 Int Charges 266,831.12
Mar 15, 2021 IBRD-78640 Loan Repay 3,575,565.20
Sep 15, 2017 IBRD-78640 Loan Repay 2,909,917.80
Mar 15, 2018 IBRD-78640 Int Charges 764,645.30
Mar 15, 2018 IBRD-78640 Loan Repay 3,320,130.20
Feb 2, 2018 IBRD-78640 Loan Disb 5,108,329.00
Dec 20, 2017 IBRD-78640 Loan Disb 4,192,528.00
Aug 27, 2018 IBRD-78640 Loan Disb 989,137.50
Sep 15, 2018 IBRD-78640 Int Charges 11,112.03
Sep 15, 2018 IBRD-78640 Int Charges 1,197,458.50
Sep 15, 2018 IBRD-78640 Loan Repay 3,532,636.80
Mar 15, 2019 IBRD-78640 Int Charges 1,440.85
Mar 15, 2019 IBRD-78640 Int Charges 1,262,699.40
Mar 15, 2019 IBRD-78640 Loan Repay 3,575,565.20
Mar 23, 2017 IBRD-78640 Loan Disb 2,189,863.80
Jun 21, 2017 IBRD-78640 Loan Disb 2,767,880.20
May 5, 2017 IBRD-78640 Loan Disb 1,684,579.90
Jun 1, 2017 IBRD-78640 Loan Disb 5,873,369.00
Mar 15, 2017 IBRD-78640 Int Charges 487,934.34
Mar 15, 2017 IBRD-78640 Loan Repay 2,239,131.50
Oct 24, 2017 IBRD-78640 Loan Disb 1,602,370.00
Oct 24, 2017 IBRD-78640 Loan Disb 1,862,549.80
Oct 20, 2017 IBRD-78640 Loan Disb 2,597,860.80
Sep 15, 2017 IBRD-78640 Int Charges 11,647.11
Sep 15, 2017 IBRD-78640 Int Charges 680,765.00
Sep 15, 2015 IBRD-78640 Loan Repay 1,731,818.10
Mar 25, 2016 IBRD-78640 Loan Disb 3,430,624.20
Mar 15, 2016 IBRD-78640 Int Charges 237,880.14
Mar 15, 2016 IBRD-78640 Loan Repay 1,841,553.40
Mar 25, 2016 IBRD-78640 Loan Disb 900,952.06
Sep 15, 2016 IBRD-78640 Int Charges 372,590.62
Sep 15, 2016 IBRD-78640 Loan Repay 2,082,309.90
Jun 13, 2016 IBRD-78640 Loan Disb 2,412,304.50
Jan 23, 2017 IBRD-78640 Loan Disb 4,952,702.00
Dec 12, 2016 IBRD-78640 Loan Disb 4,238,421.50
Sep 15, 2014 IBRD-78640 Int Charges 2,774.97
Sep 15, 2014 IBRD-78640 Int Charges 123,047.54
Mar 15, 2015 IBRD-78640 Int Charges 144,880.28
Apr 8, 2015 IBRD-78640 Loan Disb 3,407,669.80
Mar 15, 2015 IBRD-78640 Int Charges 1,976.86
Apr 14, 2015 IBRD-78640 Loan Disb 1,211,775.80
Oct 19, 2015 IBRD-78640 Loan Disb 3,189,977.50

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2018-06-28
Overall Implementation Progress (IP) Satisfactory 2018-06-28
Procurement Satisfactory 2018-06-28
Project Management Moderately Satisfactory 2018-06-28
Progress towards achievement of PDO Satisfactory 2018-06-28
Financial Management Satisfactory 2018-06-28
Monitoring and Evaluation Satisfactory 2018-06-28
Overall Safeguards Rating Moderately Satisfactory 2018-06-28

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2019
OutcomesModerately Satisfactory
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-18-2019PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • 4. Average peak hour travel time by bus along targeted PT corridorsValue29.5025.0026.50
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 1. Modal share of public transport (bus and metro) on targeted PT corridorsValue29.0033.0033.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 2. Average number of fatalities per year on four Road Safety corridorsValue22.0018.0010.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 3. Average peak hour travel time on Jiefang Avenue (Huangpu Road to Dibian Road), on Jiefang Avenue Extension (Dibian Road to the 3rd Ring Road), and on the Shuidong Section of the 2nd Ring Road.Value26.0018.0013.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 5. Wuhan city develops and integrated public transport strategyValueNoYesYes
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 6. Wuhan City develops a strategy for environmentally friendly construction, maintenance, and operation of urban mobility infrastructureValueNoYesYes
    DateDecember 31, 2008August 31, 2017March 31, 2019
    Comment
  • 4.1 on Heping Avenue (sub-indicator)Value35.0030.0033.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 4.2 on Hanyang Avenue (sub-indicator)Value24.0020.0020.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 1.2. Hanyang Avenue (sub-indicator)Value31.0035.0035.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 1.1. Heping Avenue (sub-indicator)Value27.0031.0031.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 3.1 on the Shuidong Section of the 2nd Ring Road (sub-indicator)Value22.0015.005.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 3.2 on Jiefang Avenue (Huangpu Road to Dibian Road) (sub-indicator)Value45.0035.0030.00
    DateDecember 31, 2008August 31, 2018May 31, 2018
    Comment
  • 3.3 on Jiefang Avenue Extension (Dibian Road to the 3rd Ring Road) (sub-indicator)Value11.005.00500.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1. % of bus stops targeted on PT corridors with enhanced accessibility for vulnerable usersValue66.4096.5096.50
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 2. Number of public transport terminals, interchanges and transfer facility completedValue0.002.002.00
    DateDecember 31, 2008August 31, 2017March 31, 2019
    Comment
  • 3. Number of intersections with traffic signals with pedestrian phase on RS corridorsValue7.0038.0048.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 4. Number of unsignalized zebras on RS corridors converted to non-conflicting crossings (including signalized mid-block crossings, footbridges and underpasses)Value0.009.0017.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 5. Length of road with improved or new constructed physical separation between motorized and non-motorized vehicle flow on RS corridorsValue0.009.309.30
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 6. Length of roads improved/constructed of three key links (Shuidong Road, Jiefang Avenue Extension, and Shuidong Section of the 2nd Ring Road) completedValue0.0013.6513.29
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 7. % of systems installed for traffic management on four Yangtze River bridges and three Hanjiang River bridgesValue0.00100.00100.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 8. Definition and adoption of a bus route optimization strategyValueNo strategyyesyes
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 9. Definition and adoption of systematic parking pricing policy and a hierarchical parking zonal systemValueNo systematic parking pricing policy and a hierarcyesyes
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 10. Number of staff trained on selected topics (in line with capacity building program) with positive assessment of training (Person*day)Value0.001000.001200.00
    DateDecember 31, 2008August 31, 2017May 31, 2018
    Comment
  • 11. Non-motorized vehicles study completedValueNoYesYes
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 1.2 Hanyang Avenue (sub-indicator)Value56.00100.00100.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 1.1 Heping Avenue (sub-indicator)Value76.0093.0093.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 3.4 Baishazhou Avenue (sub-indicator)Value0.007.0013.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 3.3 Xudong Avenue/No. 2 Yangtze Bridge (sub-indicator)Value0.002.005.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 3.2 Hanyang Avenue (sub-indicator)Value4.0010.008.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 3.1 Heping Avenue (sub-indicator)Value3.0019.0022.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 4.4 Baishazhou Avenue (sub-indicator)Value0.004.004.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 4.3 Xudong Avenue/No. 2 Yangtze Bridge (sub-indicator)Value0.001.001.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 4.2 Hanyang Avenue (sub-indicator)Value0.003.006.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 4.1 Heping Avenue (sub-indicator)Value0.001.006.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 5.4 Baishazhou Avenue (sub-indicator)Value0.004.004.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 5.3 Xudong Avenue/No. 2 Yangtze Bridge (sub-indicator)Value0.003.503.50
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 5.2 Hanyang Avenue (sub-indicator)Value0.002.802.80
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 5.1 Heping Avenue (sub-indicator)Value0.003.003.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 6.3 Shuidong Section of the 2 Ring Road (sub-indicator)Value0.000.890.89
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 6.2. Jiefang Avenue (Huangpu Road – Dijiao Garden Road) (sub-indicator)Value0.009.369.00
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment
  • 6.1. Shuidong Road (sub-indicator)Value0.003.403.40
    DateDecember 31, 2008August 31, 2017August 31, 2018
    Comment