Financier | Commitments |
---|---|
Pacific Regional Infrastructure Facility Trust Fund | 0.50 |
Asian Development Bank | 9.70 |
IDA Grant | 17.20 |
Borrower/Recipient | 6.60 |
P113184
Closed
Natasha Beschorner
Kingdom of Tonga
May 19, 2010
(as of board presentation)
August 30, 2011
September 9, 2011
US$ 34.00 million
Ministry of Information and Communications,Tonga Cable Ltd
2012
US$ 27.40 million
B
September 19, 2022
July 23, 2018
BANK APPROVED
Financier | Commitments |
---|---|
Pacific Regional Infrastructure Facility Trust Fund | 0.50 |
Asian Development Bank | 9.70 |
IDA Grant | 17.20 |
Borrower/Recipient | 6.60 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 17.20 |
IBRD + IDA Commitment | 17.20 |
Lending Instrument | |
---|---|
Grant Amount | 10.20 |
Total Project Cost** | 34.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 30, 2011 | IDA-H7310 | Loan Commitment | 17,200,000.00 |
Sep 23, 2013 | IDA-H7310 | Loan Disb | 655,584.30 |
Nov 12, 2019 | IDA-H7310 | Loan Disb | -50,470.29 |
Nov 16, 2017 | IDA-H7310 | Loan Disb | 1,251,940.60 |
Feb 5, 2018 | IDA-H7310 | Loan Disb | 122,315.39 |
Jan 19, 2018 | IDA-H7310 | Loan Disb | 370,847.30 |
Jan 19, 2018 | IDA-H7310 | Loan Disb | 238,405.66 |
Jul 12, 2018 | IDA-H7310 | Loan Disb | 19,956.98 |
Jun 15, 2017 | IDA-H7310 | Loan Disb | 98,340.01 |
Jul 10, 2017 | IDA-H7310 | Loan Disb | 70,020.00 |
Aug 25, 2017 | IDA-H7310 | Loan Disb | 143,151.03 |
Sep 26, 2016 | IDA-H7310 | Loan Disb | 140,040.00 |
Aug 22, 2016 | IDA-H7310 | Loan Disb | 44,884.40 |
Apr 6, 2016 | IDA-H7310 | Loan Disb | 26,008.09 |
Oct 22, 2015 | IDA-H7310 | Loan Disb | 64,596.32 |
Jun 5, 2014 | IDA-H7310 | Loan Disb | 248,142.95 |
Feb 23, 2015 | IDA-H7310 | Loan Disb | 48,385.30 |
Dec 17, 2014 | IDA-H7310 | Loan Disb | 132,390.95 |
Aug 12, 2013 | IDA-H7310 | Loan Disb | 2,393,689.50 |
Feb 26, 2014 | IDA-H7310 | Loan Disb | 135,657.70 |
Aug 8, 2013 | IDA-H7310 | Loan Disb | 188,257.22 |
Oct 18, 2013 | IDA-H7310 | Loan Disb | 34,293.00 |
Sep 5, 2013 | IDA-H7310 | Loan Disb | 748,592.44 |
Nov 12, 2019 | IDA-H7310 | Loan Cancel | 110,128.67 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2017-12-07 |
Monitoring and Evaluation | Moderately Satisfactory | 2017-12-07 |
Overall Safeguards Rating | Satisfactory | 2017-12-07 |
Progress towards achievement of PDO | Satisfactory | 2017-12-07 |
Project Management | Moderately Satisfactory | 2017-12-07 |
Overall Implementation Progress (IP) | Satisfactory | 2017-12-07 |
Counterpart Funding | Satisfactory | 2017-12-07 |
Financial Management | Moderately Satisfactory | 2017-12-07 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-28-2019 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-14-2019 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increased Capacity of MEIDECC to deliver on its mandates | Value | 1.00 | 5.00 | 5.00 |
Date | July 29, 2011 | July 23, 2018 | July 23, 2018 | |
Comment |
Increased Level of Competition in the ICT sector (number of service providers) | Value | 2.00 | 6.00 | 6.00 |
Date | July 29, 2011 | July 23, 2018 | July 23, 2018 | |
Comment |
Access to Internet Services (per 100 people) | Value | 1.00 | 40.00 | 50.00 |
Date | July 29, 2011 | July 23, 2018 | July 23, 2018 | |
Comment |
Access to telephone services, mobile phone (per 100 people) | Value | 59.00 | 100.00 | 101.00 |
Date | July 29, 2011 | July 23, 2018 | July 23, 2018 | |
Comment |
International Internet Bandwidth (Mbps) | Value | 37.00 | 850.00 | 4400.00 |
Date | July 29, 2011 | July 23, 2018 | July 23, 2018 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Component 1: Length of fiber optic network built (km) | Value | 0.00 | 1217.00 | 1217.00 |
Date | July 29, 2011 | July 23, 2018 | July 23, 2018 | |
Comment |
Component 1: Direct project beneficiaries (number of people) | Value | 1000.00 | 55000.00 | 101000.00 |
Date | July 29, 2011 | July 23, 2018 | July 23, 2018 | |
Comment |
Component 2: Price of Wholesale International Capacity Link (US$/Mbps/Month) for 1 STM-1 (155 Mbps) capacity | Value | 495.00 | 150.00 | 155.00 |
Date | May 5, 2016 | July 23, 2018 | July 23, 2018 | |
Comment |
Component 2: Volume of International Traffic (Mbps) | Value | 30.00 | 750.00 | 1300.00 |
Date | July 29, 2011 | July 23, 2018 | July 23, 2018 | |
Comment |
Component 2: Average per minute cost of international call (in US$) | Value | 0.35 | 0.15 | 0.13 |
Date | July 29, 2011 | August 23, 2016 | November 1, 2017 | |
Comment |
Component 2: Retail price of Internet Services (US$/GB/Month) | Value | 75.00 | 5.00 | 3.00 |
Date | July 29, 2011 | July 23, 2018 | November 1, 2017 | |
Comment |
Component 2: TCL restructuring completed | Value | No | Yes | Yes |
Date | July 11, 2016 | July 23, 2018 | July 23, 2018 | |
Comment |
Component 2: Implementation of open access and wholesale price regulation | Value | No | Yes | Yes |
Date | July 11, 2016 | July 23, 2018 | July 23, 2018 | |
Comment |