Skip to Main Navigation

Kenya Informal Settlements Improvement Project (KISIP)

Abstract*

The objective of the Informal Settlements Improvement Project is to improve living conditions in informal settlements in selected municipalities in Kenya. This will be achieved by enhancing security of tenure and improving infrastructure based on plans developed in consultation with the community. This project has 4 components. Component 1 focuses on strengthening institutions and program management by supporting institutional strengthening and capacity...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve living conditions in informal settlements in selected urban centers in selected counties in Kenya.

Key Details

Project Details

  • P113542

  • Closed

  • Sheila Kamunyori , Abebaw Alemayehu

  • Republic of Kenya

  • Kenya

  • October 26, 2010

  • (as of board presentation)

    March 24, 2011

  • June 30, 2011

  • US$ 165.00 million

  • State Department of Housing and Urban Development

  • Eastern and Southern Africa

  • 2011

  • US$ 155.00 million

  • B

  • February 5, 2021

  • November 30, 2019

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 100.00
Borrower/Recipient 10.00
SWEDEN: Swedish Intl. Dev. Cooperation Agency (SIDA) 10.00
FRANCE: French Agency for Development 45.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount 55.00
Total Project Cost** 165.00

Summary Status of World Bank Financing (US$ Millions) as of January 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of January 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 15, 2019 IDA-48730 Int Charges 3,047.56
Nov 15, 2019 IDA-48730 Int Charges 331,658.20
Nov 17, 2014 IDA-48730 Loan Disb 5,273,097.00
Nov 15, 2014 IDA-48730 Int Charges 403.23
Nov 15, 2014 IDA-48730 Int Charges 403.23
Nov 15, 2014 IDA-48730 Int Charges 82,304.75
Nov 15, 2014 IDA-48730 Int Charges 82,304.75
Sep 4, 2013 IDA-48730 Loan Disb 5,867,253.00
Mar 12, 2014 IDA-48730 Loan Disb 6,500,833.00
Nov 15, 2013 IDA-48730 Int Charges 267.78
Nov 15, 2013 IDA-48730 Int Charges 267.78
Nov 15, 2013 IDA-48730 Int Charges 44,014.16
Nov 15, 2013 IDA-48730 Int Charges 44,014.16
May 23, 2014 IDA-48730 Int Charges 261.19
May 23, 2014 IDA-48730 Int Charges 261.19
May 23, 2014 IDA-48730 Int Charges 67,014.73
May 23, 2014 IDA-48730 Int Charges 67,014.73
Aug 22, 2014 IDA-48730 Loan Disb 2,453,689.00
Feb 20, 2015 IDA-48730 Loan Disb 8,214,667.50
May 15, 2015 IDA-48730 Int Charges 2,013.33
May 18, 2015 IDA-48730 Int Charges 112,312.79
May 18, 2015 IDA-48730 Int Charges 112,312.79
May 15, 2015 IDA-48730 Int Charges 2,013.33
Jun 3, 2015 IDA-48730 Loan Disb 16,352,587.00
Nov 13, 2015 IDA-48730 Loan Disb 485,212.80
Oct 16, 2015 IDA-48730 Loan Disb 247,122.20
Nov 15, 2015 IDA-48730 Int Charges 3,840.34
Nov 15, 2015 IDA-48730 Int Charges 3,840.34
Nov 15, 2015 IDA-48730 Int Charges 189,872.55
Nov 15, 2015 IDA-48730 Int Charges 189,872.55
Dec 11, 2015 IDA-48730 Loan Disb 5,159,600.00
Dec 18, 2015 IDA-48730 Loan Disb 714,200.56
Oct 9, 2015 IDA-48730 Loan Disb 5,179,325.00
Nov 5, 2015 IDA-48730 Loan Disb 487,081.03
Feb 16, 2016 IDA-48730 Loan Disb 591,183.30
Mar 24, 2011 IDA-48730 Loan Commitment 100,000,000.00
Nov 15, 2019 IDA-48730 Int Charges 331,658.20
May 15, 2020 IDA-48730 Int Charges 323.02
May 15, 2020 IDA-48730 Int Charges 323.02
May 15, 2020 IDA-48730 Int Charges 331,346.90
May 15, 2020 IDA-48730 Int Charges 331,346.90
Mar 30, 2020 IDA-48730 Loan Cancel 1,181.99
Nov 15, 2020 IDA-48730 Int Charges 340,721.80
Nov 15, 2020 IDA-48730 Int Charges 340,721.80
Nov 15, 2020 IDA-48730 Int Charges 4,579.59
Nov 15, 2020 IDA-48730 Int Charges 4,579.59
May 15, 2021 IDA-48730 Int Charges 785.43
May 15, 2021 IDA-48730 Int Charges 785.43
May 15, 2021 IDA-48730 Loan Repay 935,142.60
May 15, 2021 IDA-48730 Int Charges 341,538.88
May 15, 2021 IDA-48730 Int Charges 341,538.88
Nov 15, 2021 IDA-48730 Int Charges 339,022.70
Nov 15, 2021 IDA-48730 Int Charges 339,022.70
Nov 15, 2021 IDA-48730 Loan Repay 913,192.40
Nov 15, 2021 IDA-48730 Int Charges 8,925.06
Nov 15, 2021 IDA-48730 Int Charges 8,925.06
May 15, 2022 IDA-48730 Int Charges 317,883.44
May 15, 2022 IDA-48730 Int Charges 317,883.44
May 15, 2022 IDA-48730 Loan Repay 18,913.56
May 15, 2022 IDA-48730 Loan Repay 846,075.50
Nov 15, 2022 IDA-48730 Loan Repay 43,163.18
Nov 15, 2022 IDA-48730 Int Charges 292,472.40
Nov 15, 2022 IDA-48730 Int Charges 292,472.40
Nov 15, 2022 IDA-48730 Loan Repay 812,206.00
Nov 15, 2023 IDA-48730 Int Charges 10,132.56
Nov 15, 2023 IDA-48730 Int Charges 10,132.56
Nov 15, 2023 IDA-48730 Loan Repay 862,116.06
Nov 15, 2023 IDA-48730 Int Charges 300,344.34
Nov 15, 2023 IDA-48730 Int Charges 300,344.34
May 15, 2023 IDA-48730 Int Charges 19,046.76
May 15, 2023 IDA-48730 Int Charges 19,046.76
May 15, 2023 IDA-48730 Loan Repay 872,717.44
May 15, 2023 IDA-48730 Int Charges 303,921.10
May 15, 2023 IDA-48730 Int Charges 303,921.10
May 15, 2024 IDA-48730 Int Charges 6,769.02
May 15, 2024 IDA-48730 Int Charges 6,769.02
May 15, 2024 IDA-48730 Int Charges 303,201.66
May 15, 2024 IDA-48730 Int Charges 303,201.66
May 15, 2024 IDA-48730 Loan Repay 860,146.56
May 17, 2016 IDA-48730 Int Charges 456.60
May 17, 2016 IDA-48730 Int Charges 456.60
May 25, 2016 IDA-48730 Loan Disb 420,964.16
May 17, 2016 IDA-48730 Int Charges 237,282.22
May 17, 2016 IDA-48730 Int Charges 237,282.22
Oct 17, 2016 IDA-48730 Loan Disb 5,631,913.00
Nov 15, 2016 IDA-48730 Int Charges 2,687.09
Nov 15, 2016 IDA-48730 Int Charges 2,687.09
Nov 15, 2016 IDA-48730 Int Charges 251,040.69
Nov 15, 2016 IDA-48730 Int Charges 251,040.69
Jun 6, 2016 IDA-48730 Loan Disb 3,088,029.00
May 15, 2017 IDA-48730 Int Charges 3,499.56
May 15, 2017 IDA-48730 Int Charges 3,499.56
Jun 29, 2017 IDA-48730 Loan Disb 5,561,544.50
Mar 8, 2017 IDA-48730 Loan Disb 845,925.90
May 15, 2017 IDA-48730 Int Charges 265,010.25
May 15, 2017 IDA-48730 Int Charges 265,010.25
Dec 1, 2017 IDA-48730 Int Charges 301,528.97
Dec 1, 2017 IDA-48730 Int Charges 4,275.78
Dec 1, 2017 IDA-48730 Int Charges 4,275.78
Dec 1, 2017 IDA-48730 Int Charges 301,528.97
Dec 26, 2017 IDA-48730 Loan Disb 7,521,955.50
Jan 29, 2018 IDA-48730 Loan Disb -2,477,295.20
Sep 15, 2017 IDA-48730 Loan Disb 3,121,256.00
Apr 24, 2018 IDA-48730 Loan Disb 2,530,473.50
Feb 2, 2018 IDA-48730 Loan Disb -124,728.50
May 17, 2018 IDA-48730 Int Charges 2,779.51
May 17, 2018 IDA-48730 Int Charges 2,779.51
May 17, 2018 IDA-48730 Int Charges 335,415.75
May 17, 2018 IDA-48730 Int Charges 335,415.75
Jul 3, 2018 IDA-48730 Loan Disb -5,008.03
Aug 15, 2018 IDA-48730 Loan Disb 123,055.66
Nov 15, 2018 IDA-48730 Int Charges 6,296.84
Nov 15, 2018 IDA-48730 Int Charges 6,296.84
Nov 16, 2018 IDA-48730 Int Charges 330,410.60
Nov 16, 2018 IDA-48730 Int Charges 330,410.60
May 15, 2019 IDA-48730 Int Charges 4,967.20
May 15, 2019 IDA-48730 Int Charges 4,967.20
May 24, 2019 IDA-48730 Int Charges 331,368.47
May 24, 2019 IDA-48730 Int Charges 331,368.47
Nov 15, 2019 IDA-48730 Int Charges 3,047.56

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2019-12-19
Procurement Moderately Satisfactory 2019-12-19
Project Management Satisfactory 2019-12-19
Progress towards achievement of PDO Moderately Satisfactory 2019-12-19
Counterpart Funding Moderately Satisfactory 2019-12-19
Monitoring and Evaluation Moderately Satisfactory 2019-12-19
Overall Implementation Progress (IP) Moderately Satisfactory 2019-12-19

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 08-14-2020
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-10-2020PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People benefiting from improved tenure security under component 2 of the KISIP.Value0.00125525.00100000.00
    DateOctober 25, 2010November 15, 2019July 31, 2018
    Comment
  • Direct project beneficiariesValue0.001389980.001070000.00
    DateOctober 25, 2010November 15, 2019May 7, 2015
    Comment
  • Female beneficiariesValue0.00395750.000.00
    DateOctober 25, 2010February 19, 2018
    Comment
  • People in informal settlements provided with access to improved drainage infrastructure under KISIPValue0.001000000.001100000.00
    DateOctober 25, 2010November 15, 2019May 31, 2018
    Comment
  • Number of people in urban areas provided with access to all-season roads within a 500 meter range under the projectValue0.001000000.001100000.00
    DateOctober 25, 2010November 15, 2019May 31, 2018
    Comment
  • Number of people in urban areas provided with access to Improved Water Sources under the projectValue0.00262780.00162000.00
    DateOctober 25, 2010November 15, 2019April 6, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Policies, frameworks, and guidelines for slum upgrading developed and adopted by the MLHUDValue0.001.000.00
    DateOctober 25, 2010November 15, 2019
    Comment
  • Informal settlements benefiting from enhanced tenure security under KISIP.Value0.0080.000.00
    DateOctober 25, 2010November 15, 2019
    Comment
  • People in settlements provided with access to improved shared sanitation facilities under the KISIP.Value0.0035000.003050.00
    DateOctober 25, 2010November 15, 2019September 30, 2018
    Comment
  • Situational AnalysisValueNoYes
    DateJanuary 4, 2016November 15, 2019
    Comment
  • Database with slum inventory operational and accessible to the public.ValueNoYes
    DateOctober 25, 2010November 15, 2019
    Comment
  • GIS lab at the ministry upgraded and operational.ValueNoYes
    DateOctober 25, 2010November 15, 2019
    Comment
  • New piped household water connections that are resulting from the project interventionValue0.008739.007306.00
    DateOctober 25, 2010November 15, 2019September 30, 2018
    Comment
  • Housing SurveyValueNoYes
    DateJanuary 4, 2016November 15, 2019
    Comment
  • Roads rehabilitated, Non-ruralValue0.0098.2890.20
    DateOctober 25, 2010November 15, 2019September 30, 2018
    Comment
  • New street or security lights put into place under the KISIP.Value0.00134.00134.00
    DateOctober 25, 2010November 15, 2019September 30, 2018
    Comment
  • New Sewer connections constructed under the projectValue0.004788.004730.00
    DateOctober 25, 2010November 15, 2019September 30, 2018
    Comment
  • Drainage System RehabiliatedValue0.00109.210.00
    DateJanuary 4, 2016November 15, 2019September 30, 2018
    Comment
  • Footpaths RehabilitatedValue0.00120.070.00
    DateJanuary 4, 2016November 15, 2019
    Comment