Financier | Commitments |
---|---|
Borrower/Recipient | 46.60 |
IDA Credit | 160.00 |
P113949
Closed
Cuong Hung Pham
Ministry of Agriculture and Rural Development
June 1, 2011
(as of board presentation)
June 7, 2011
October 7, 2011
US$ 206.60 million
Central Project Office
2011
US$ 160.00 million
B
Not Applicable
September 15, 2017
BANK APPROVED
April 22, 2024
Financier | Commitments |
---|---|
Borrower/Recipient | 46.60 |
IDA Credit | 160.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 160.00 |
IBRD + IDA Commitment | 160.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 206.60 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 15, 2016 | IDA-49510 | Int Charges | 316,703.75 |
Nov 15, 2016 | IDA-49510 | Int Charges | 316,703.75 |
Sep 6, 2016 | IDA-49510 | Loan Disb | 2,264,035.00 |
Apr 4, 2017 | IDA-49510 | Loan Disb | 1,577,376.00 |
Jun 30, 2017 | IDA-49510 | Loan Disb | 1,077,541.60 |
Jun 20, 2017 | IDA-49510 | Loan Disb | 3,944,120.20 |
May 5, 2017 | IDA-49510 | Loan Disb | 1,815,149.00 |
May 15, 2017 | IDA-49510 | Int Charges | 7,637.58 |
May 15, 2017 | IDA-49510 | Int Charges | 7,637.58 |
May 15, 2017 | IDA-49510 | Int Charges | 346,129.20 |
May 15, 2017 | IDA-49510 | Int Charges | 346,129.20 |
Oct 9, 2015 | IDA-49510 | Loan Disb | 2,968,088.50 |
Dec 22, 2015 | IDA-49510 | Loan Disb | 1,851,357.00 |
Apr 27, 2016 | IDA-49510 | Loan Disb | 2,500,763.20 |
Mar 9, 2016 | IDA-49510 | Loan Disb | 3,962,036.50 |
Jun 30, 2016 | IDA-49510 | Loan Disb | 2,816,908.80 |
Dec 30, 2016 | IDA-49510 | Loan Disb | 2,549,912.80 |
May 15, 2016 | IDA-49510 | Int Charges | 2,735.67 |
May 15, 2016 | IDA-49510 | Int Charges | 2,735.67 |
Jun 27, 2014 | IDA-49510 | Loan Disb | 1,498,880.00 |
Jun 19, 2014 | IDA-49510 | Loan Disb | 2,013,960.80 |
Aug 19, 2014 | IDA-49510 | Loan Disb | 2,269,312.20 |
Dec 22, 2014 | IDA-49510 | Loan Disb | 2,026,218.00 |
Jan 27, 2015 | IDA-49510 | Loan Disb | 2,200,671.00 |
Mar 17, 2015 | IDA-49510 | Loan Disb | 1,493,131.00 |
Apr 10, 2015 | IDA-49510 | Loan Disb | 1,856,928.50 |
May 15, 2015 | IDA-49510 | Int Charges | 1,093.62 |
May 15, 2015 | IDA-49510 | Int Charges | 1,093.62 |
May 15, 2015 | IDA-49510 | Int Charges | 209,327.52 |
May 15, 2015 | IDA-49510 | Int Charges | 209,327.52 |
Jun 22, 2015 | IDA-49510 | Loan Disb | 1,201,665.60 |
Jul 7, 2015 | IDA-49510 | Loan Disb | 2,068,494.90 |
Nov 15, 2015 | IDA-49510 | Int Charges | 9,948.66 |
Nov 15, 2015 | IDA-49510 | Int Charges | 9,948.66 |
Nov 15, 2015 | IDA-49510 | Int Charges | 249,905.22 |
Nov 15, 2015 | IDA-49510 | Int Charges | 249,905.22 |
Aug 7, 2015 | IDA-49510 | Loan Disb | 2,153,541.00 |
Jan 23, 2015 | IDA-49510 | Loan Disb | 2,115,527.20 |
Dec 11, 2014 | IDA-49510 | Loan Disb | 1,999,955.90 |
Feb 13, 2014 | IDA-49510 | Loan Disb | 3,635,658.20 |
Oct 1, 2013 | IDA-49510 | Loan Disb | 1,867,726.20 |
Dec 16, 2013 | IDA-49510 | Loan Disb | 5,000,000.00 |
Dec 16, 2013 | IDA-49510 | Loan Disb | 3,526,101.80 |
Nov 15, 2013 | IDA-49510 | Int Charges | 56,693.00 |
Nov 15, 2013 | IDA-49510 | Int Charges | 56,693.00 |
Nov 15, 2013 | IDA-49510 | Int Charges | 2,251.61 |
Nov 15, 2013 | IDA-49510 | Int Charges | 2,251.61 |
Oct 30, 2013 | IDA-49510 | Loan Disb | 4,134,603.20 |
Mar 18, 2014 | IDA-49510 | Loan Disb | 2,098,030.00 |
Mar 18, 2014 | IDA-49510 | Loan Disb | 2,446,710.80 |
May 15, 2014 | IDA-49510 | Int Charges | 6,765.30 |
May 15, 2014 | IDA-49510 | Int Charges | 6,765.30 |
May 15, 2014 | IDA-49510 | Int Charges | 127,330.49 |
May 15, 2014 | IDA-49510 | Int Charges | 127,330.49 |
May 9, 2014 | IDA-49510 | Loan Disb | 1,924,552.60 |
Nov 29, 2017 | IDA-49510 | Loan Disb | 1,801,997.00 |
Feb 13, 2018 | IDA-49510 | Loan Cancel | 12,654,895.00 |
Feb 13, 2018 | IDA-49510 | Loan Disb | -816,964.60 |
Dec 4, 2017 | IDA-49510 | Loan Disb | 2,197,119.20 |
Nov 15, 2017 | IDA-49510 | Int Charges | 439,805.88 |
Nov 15, 2017 | IDA-49510 | Int Charges | 439,805.88 |
Dec 8, 2017 | IDA-49510 | Loan Disb | 2,000,000.00 |
Feb 13, 2018 | IDA-49510 | Loan Disb | -118,670.75 |
May 26, 2016 | IDA-49510 | Loan Disb | 2,418,569.20 |
Jan 23, 2017 | IDA-49510 | Loan Disb | 1,259,737.90 |
Aug 31, 2016 | IDA-49510 | Loan Disb | 3,017,034.50 |
May 18, 2016 | IDA-49510 | Int Charges | 275,546.25 |
May 18, 2016 | IDA-49510 | Int Charges | 275,546.25 |
Nov 1, 2016 | IDA-49510 | Loan Disb | 3,373,940.80 |
Nov 15, 2016 | IDA-49510 | Int Charges | 3,700.61 |
Nov 15, 2016 | IDA-49510 | Int Charges | 3,700.61 |
Sep 26, 2014 | IDA-49510 | Loan Disb | 2,533,654.00 |
Dec 1, 2014 | IDA-49510 | Loan Disb | 1,679,113.00 |
Nov 15, 2014 | IDA-49510 | Int Charges | 171,530.12 |
Nov 15, 2014 | IDA-49510 | Int Charges | 171,530.12 |
Nov 6, 2014 | IDA-49510 | Loan Disb | 3,103,734.00 |
Nov 15, 2014 | IDA-49510 | Int Charges | 4,618.25 |
Nov 15, 2014 | IDA-49510 | Int Charges | 4,618.25 |
Sep 17, 2013 | IDA-49510 | Loan Disb | 2,786,484.80 |
Jul 2, 2013 | IDA-49510 | Loan Disb | 757,709.25 |
Nov 15, 2023 | IDA-49510 | Int Charges | 392,521.25 |
Nov 15, 2023 | IDA-49510 | Int Charges | 392,521.25 |
Nov 15, 2023 | IDA-49510 | Int Charges | 30,081.29 |
Nov 15, 2023 | IDA-49510 | Int Charges | 30,081.29 |
Nov 15, 2023 | IDA-49510 | Loan Repay | 3,056,682.00 |
May 15, 2023 | IDA-49510 | Int Charges | 56,575.29 |
May 15, 2023 | IDA-49510 | Int Charges | 56,575.29 |
May 15, 2023 | IDA-49510 | Loan Repay | 3,094,269.80 |
May 15, 2023 | IDA-49510 | Int Charges | 398,878.72 |
May 15, 2023 | IDA-49510 | Int Charges | 398,878.72 |
May 15, 2024 | IDA-49510 | Int Charges | 20,084.85 |
May 15, 2024 | IDA-49510 | Int Charges | 20,084.85 |
May 15, 2024 | IDA-49510 | Int Charges | 400,273.00 |
May 15, 2024 | IDA-49510 | Int Charges | 400,273.00 |
May 15, 2024 | IDA-49510 | Loan Repay | 3,049,699.00 |
Jun 7, 2011 | IDA-49510 | Loan Commitment | 160,000,000.00 |
May 15, 2021 | IDA-49510 | Int Charges | 1,113.90 |
May 15, 2021 | IDA-49510 | Int Charges | 1,113.90 |
May 15, 2021 | IDA-49510 | Int Charges | 493,799.40 |
May 15, 2021 | IDA-49510 | Int Charges | 493,799.40 |
Nov 15, 2020 | IDA-49510 | Int Charges | 483,219.53 |
Nov 15, 2020 | IDA-49510 | Int Charges | 483,219.53 |
Nov 15, 2020 | IDA-49510 | Int Charges | 6,494.88 |
Nov 15, 2020 | IDA-49510 | Int Charges | 6,494.88 |
Nov 15, 2021 | IDA-49510 | Int Charges | 3,457.73 |
Nov 15, 2021 | IDA-49510 | Int Charges | 3,457.73 |
Nov 15, 2021 | IDA-49510 | Loan Repay | 3,237,776.00 |
Nov 15, 2021 | IDA-49510 | Int Charges | 485,666.40 |
Nov 15, 2021 | IDA-49510 | Int Charges | 485,666.40 |
May 15, 2022 | IDA-49510 | Loan Repay | 55,893.02 |
May 15, 2022 | IDA-49510 | Loan Repay | 3,010,975.20 |
May 15, 2022 | IDA-49510 | Int Charges | 448,529.47 |
May 15, 2022 | IDA-49510 | Int Charges | 448,529.47 |
Nov 15, 2022 | IDA-49510 | Loan Repay | 128,277.40 |
Nov 15, 2022 | IDA-49510 | Loan Repay | 2,904,483.00 |
Nov 15, 2022 | IDA-49510 | Int Charges | 376,717.72 |
Nov 15, 2022 | IDA-49510 | Int Charges | 376,717.72 |
Nov 15, 2019 | IDA-49510 | Int Charges | 471,220.12 |
Nov 15, 2019 | IDA-49510 | Int Charges | 471,220.12 |
Nov 15, 2019 | IDA-49510 | Int Charges | 3,467.26 |
Nov 15, 2019 | IDA-49510 | Int Charges | 3,467.26 |
May 15, 2020 | IDA-49510 | Int Charges | 458.13 |
May 15, 2020 | IDA-49510 | Int Charges | 458.13 |
May 15, 2020 | IDA-49510 | Int Charges | 469,923.80 |
May 15, 2020 | IDA-49510 | Int Charges | 469,923.80 |
May 15, 2018 | IDA-49510 | Int Charges | 1,665.88 |
May 15, 2018 | IDA-49510 | Int Charges | 1,665.88 |
May 15, 2018 | IDA-49510 | Int Charges | 491,363.62 |
May 15, 2018 | IDA-49510 | Int Charges | 491,363.62 |
Nov 15, 2018 | IDA-49510 | Int Charges | 10,451.53 |
Nov 15, 2018 | IDA-49510 | Int Charges | 10,451.53 |
Nov 15, 2018 | IDA-49510 | Int Charges | 467,174.20 |
Nov 15, 2018 | IDA-49510 | Int Charges | 467,174.20 |
May 15, 2019 | IDA-49510 | Int Charges | 470,584.06 |
May 15, 2019 | IDA-49510 | Int Charges | 470,584.06 |
May 15, 2019 | IDA-49510 | Int Charges | 7,269.81 |
May 15, 2019 | IDA-49510 | Int Charges | 7,269.81 |
Feb 22, 2017 | IDA-49510 | Loan Disb | 2,443,866.50 |
May 19, 2017 | IDA-49510 | Loan Disb | 6,000,000.00 |
Nov 15, 2017 | IDA-49510 | Int Charges | 7,403.86 |
Nov 15, 2017 | IDA-49510 | Int Charges | 7,403.86 |
Nov 7, 2017 | IDA-49510 | Loan Disb | 3,376,843.80 |
Oct 18, 2017 | IDA-49510 | Loan Disb | 2,115,714.80 |
Aug 8, 2017 | IDA-49510 | Loan Disb | 3,532,933.50 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2017-05-10 |
Project Management | Moderately Satisfactory | 2017-05-10 |
Counterpart Funding | Moderately Satisfactory | 2017-05-10 |
Progress towards achievement of PDO | Satisfactory | 2017-05-10 |
Financial Management | Moderately Satisfactory | 2017-05-10 |
Monitoring and Evaluation | Satisfactory | 2017-05-10 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2017-05-10 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-15-2018 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 08-08-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of areas where agricultural production has increased | Value | 0.00 | 50000.00 | 93358.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Number of areas where agricultural production has been maintained through prevention of future salinity intrusion and flood risks. | Value | 0.00 | 50000.00 | 11479.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Provision of sustainable and safe potable water supply to rural population | Value | 0.00 | 60000.00 | 66615.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Increased water productivity in the pilot areas. | Value | 0.00 | 20.00 | 16.80 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Area transferred to WUOs for managing tertiary and quaternary irrigation facilities | Value | 0.00 | 40000.00 | 42825.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Number of rural households served by improved sanitation | Value | 0.00 | 10000.00 | 18607.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Area provided with irrigation and drainage services (ha) | Value | 0.00 | 0.00 | 134162.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Operational water user associations created and/or strengthened (number) | Value | 0.00 | 0.00 | 145.00 |
Date | October 1, 2013 | June 7, 2011 | September 15, 2017 | |
Comment |
Area provided with irrigation and drainage services - Improved (ha) | Value | 0.00 | 0.00 | 54033.00 |
Date | September 30, 2012 | June 7, 2011 | September 15, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of provinces having water resources management plans considering the impacts on the upstream development and climate change and improve the current operations and maintenance practices | Value | 0.00 | 7.00 | 0.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Number of pilot programs on improved irrigation and advanced high productivity agriculture practices implemented | Value | 0.00 | 6.00 | 6.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Number of provinces implementing programs which would bring improvement in water resources operations and maintenance | Value | 0.00 | 7.00 | 0.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Number of subprojects successfully prepared with satisfactory safeguard plans | Value | 5.00 | 9.00 | 13.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Number of the subprojects constructed | Value | 0.00 | 9.00 | 13.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Number of the subprojects environmental and social safeguard implemented | Value | 0.00 | 9.00 | 13.00 |
Date | September 1, 2011 | June 7, 2011 | September 15, 2017 | |
Comment |
Number of the rural water supply systems constructed/expanded | Value | 0.00 | 0.00 | 89.00 |
Date | September 1, 2011 | March 31, 2017 | September 15, 2017 | |
Comment |