Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 710.00 |
Borrower/Recipient | 30.00 |
P114107
Closed
Paul Procee
International Economic and Financial Cooperation Department, Ministry of Finance
November 2, 2008
(as of board presentation)
February 12, 2009
June 17, 2009
US$ 740.00 million
Gansu Longnan Municipal Government, Gansu Provincial Government,Sichuan Provincial Health Bureau,Sichuan Provincial Construction Commission
2009
US$ 710.00 million
A
July 12, 2023
May 31, 2016
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 710.00 |
Borrower/Recipient | 30.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 710.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 710.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 740.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 26, 2013 | IBRD-76160 | Loan Disb | 15,848,789.00 |
Feb 24, 2014 | IBRD-76160 | Loan Disb | 14,995,144.00 |
Feb 19, 2014 | IBRD-76160 | Loan Disb | 16,284,636.00 |
Dec 23, 2013 | IBRD-76160 | Loan Disb | 17,750,492.00 |
Apr 15, 2014 | IBRD-76160 | Loan Repay | 10,640,257.00 |
Apr 15, 2014 | IBRD-76160 | Int Charges | 14,263.64 |
Apr 15, 2014 | IBRD-76160 | Int Charges | 1,139,306.50 |
Dec 18, 2014 | IBRD-76160 | Loan Disb | 10,267,028.00 |
Jul 7, 2014 | IBRD-76160 | Loan Disb | 19,248,182.00 |
Jul 7, 2014 | IBRD-76160 | Loan Disb | 15,966,630.00 |
Oct 15, 2022 | IBRD-76160 | Int Charges | 5,450,928.00 |
Oct 15, 2022 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Apr 15, 2023 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Apr 15, 2023 | IBRD-76160 | Int Charges | 475,471.80 |
Apr 15, 2023 | IBRD-76160 | Int Charges | 10,224,893.00 |
Oct 15, 2023 | IBRD-76160 | Int Charges | 237,936.42 |
Oct 15, 2023 | IBRD-76160 | Int Charges | 12,382,748.00 |
Oct 15, 2023 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Apr 15, 2024 | IBRD-76160 | Int Charges | 151,478.31 |
Apr 15, 2024 | IBRD-76160 | Int Charges | 13,094,433.00 |
Apr 15, 2024 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Feb 12, 2009 | IBRD-76160 | Loan Commitment | 710,000,000.00 |
Oct 15, 2019 | IBRD-76160 | Int Charges | 8,182,920.00 |
Oct 15, 2019 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Apr 15, 2019 | IBRD-76160 | Int Charges | 8,346,845.50 |
Apr 15, 2019 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Apr 15, 2020 | IBRD-76160 | Int Charges | 6,177,137.00 |
Apr 15, 2020 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Oct 15, 2020 | IBRD-76160 | Int Charges | 4,027,401.00 |
Oct 15, 2020 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Apr 15, 2021 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Apr 15, 2021 | IBRD-76160 | Int Charges | 1,410,155.40 |
Oct 15, 2021 | IBRD-76160 | Int Charges | 1,378,523.50 |
Oct 15, 2021 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Apr 15, 2022 | IBRD-76160 | Int Charges | 1,186,535.90 |
Apr 15, 2022 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Nov 28, 2016 | IBRD-76160 | Loan Disb | -10,999.27 |
Aug 19, 2016 | IBRD-76160 | Loan Disb | 3,000,000.00 |
Sep 22, 2016 | IBRD-76160 | Loan Disb | 5,500,000.00 |
Apr 15, 2017 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Apr 15, 2017 | IBRD-76160 | Int Charges | 4,615,211.00 |
Apr 15, 2017 | IBRD-76160 | Int Charges | 8,842.37 |
Oct 15, 2017 | IBRD-76160 | Int Charges | 5,080,687.50 |
Oct 15, 2017 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Apr 15, 2018 | IBRD-76160 | Int Charges | 30,792.04 |
Apr 15, 2018 | IBRD-76160 | Int Charges | 5,354,194.00 |
Apr 15, 2018 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Oct 15, 2018 | IBRD-76160 | Int Charges | 8,074,014.00 |
Oct 15, 2018 | IBRD-76160 | Loan Repay | 14,085,199.00 |
Sep 10, 2014 | IBRD-76160 | Loan Disb | 13,952,278.00 |
Jun 11, 2015 | IBRD-76160 | Loan Disb | 17,558,536.00 |
Jun 15, 2015 | IBRD-76160 | Loan Disb | 17,947,746.00 |
Apr 15, 2015 | IBRD-76160 | Int Charges | 5,290.23 |
Apr 15, 2015 | IBRD-76160 | Int Charges | 1,266,524.50 |
Apr 15, 2015 | IBRD-76160 | Loan Repay | 12,500,508.00 |
Dec 30, 2015 | IBRD-76160 | Loan Disb | 14,687,360.00 |
Oct 15, 2015 | IBRD-76160 | Loan Repay | 13,256,792.00 |
Oct 15, 2015 | IBRD-76160 | Int Charges | 1,678,962.50 |
Apr 1, 2016 | IBRD-76160 | Loan Disb | 17,380,926.00 |
Apr 15, 2016 | IBRD-76160 | Int Charges | 2,106,257.20 |
Apr 15, 2016 | IBRD-76160 | Loan Repay | 13,575,508.00 |
May 31, 2016 | IBRD-76160 | Loan Disb | 1,922,120.60 |
Oct 15, 2016 | IBRD-76160 | Int Charges | 4,528.70 |
Oct 15, 2016 | IBRD-76160 | Int Charges | 3,425,426.50 |
Oct 15, 2016 | IBRD-76160 | Loan Repay | 14,004,035.00 |
Nov 28, 2016 | IBRD-76160 | Loan Cancel | 14,195,792.00 |
Nov 28, 2016 | IBRD-76160 | Loan Disb | -4,908,232.50 |
Oct 15, 2014 | IBRD-76160 | Int Charges | 19,653.53 |
Oct 15, 2014 | IBRD-76160 | Int Charges | 1,133,782.80 |
Oct 15, 2014 | IBRD-76160 | Loan Repay | 11,996,747.00 |
Oct 28, 2013 | IBRD-76160 | Loan Disb | 16,750,683.00 |
Oct 15, 2013 | IBRD-76160 | Int Charges | 31,552.80 |
Oct 15, 2013 | IBRD-76160 | Int Charges | 1,142,865.00 |
Sep 11, 2013 | IBRD-76160 | Loan Disb | 21,348,664.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2016-05-29 |
Procurement | Moderately Satisfactory | 2016-05-29 |
Project Management | Moderately Satisfactory | 2016-05-29 |
Financial Management | Moderately Satisfactory | 2016-05-29 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2016-05-29 |
Counterpart Funding | Moderately Satisfactory | 2016-05-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2016-05-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 02-27-2017 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Substantial |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 05-15-2017 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Substantial | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Satisfactory | N/a |
Government Performance | Moderately Satisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Sichuan - Percentage of project roads with traffic restored to pre-earthquake levels | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | May 31, 2016 | |
Comment |
Sichuan - Percentage of county towns with water supply services that are at a minimum restored to pre-earthquake levels | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | June 30, 2014 | |
Comment |
Sichuan - Percentage of reconstructed (a) county health facilities and (b) township health facilities that reach bed occupancy rates not below 2007 levels | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | June 30, 2014 | |
Comment |
Gansu - Percentage of project roads with traffic restored to pre-earthquake levels | Value | 0.00 | 95.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | May 31, 2016 | |
Comment |
Gansu - Percentage of county towns with water supply services that are at a minimum restored to pre-earthquake levels | Value | 0.00 | 85.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | May 31, 2016 | |
Comment |
Gansu - Percentage of reconstructed (a) county health facilities and (b) township health facilities that reach bed occupancy rates not below 2007 levels | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | May 31, 2016 | |
Comment |
Gansu - Percentage of reconstruction (a) primary and (b) secondary schools that reach enrollment rates of (a) 99% and (b) 80% respectively | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | May 31, 2016 | |
Comment |
Roads rehabilitated, Non-rural | Value | 0.00 | 240.00 | 218.00 |
Date | January 1, 2010 | May 20, 2016 | May 31, 2016 | |
Comment |
Health facilities constructed, renovated, and/or equipped (number) | Value | 0.00 | 68.00 | 68.00 |
Date | January 1, 2010 | May 20, 2016 | May 31, 2016 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Infrastructure Sichuan - Percentage of total project assets (measured by sector with appropriate indicators) built to applicable governmentstandards that | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | May 31, 2016 | |
Comment |
Health Sichuan - Percentage of total number of project health facilities built to applicable government standards that address flood and seismic hazards | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | June 30, 2014 | |
Comment |
Health Sichuan - Perentage of restored project facilities that are fully equipped according to government standards | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2009 | May 20, 2016 | June 30, 2014 | |
Comment |
Capacity Building Sichuan - Percentage of PMO/PIU staff trained in project management processes for earthquake reconstruction. | Value | 0.00 | 100.00 | 100.00 |
Date | December 5, 2008 | May 20, 2016 | June 30, 2014 | |
Comment |
Infrastructure Gansu - Percentage of total project infrastructure assets (measured by sector with appropriate indicators) built to applicable government standards that address flood and seismic hazard | Value | 0.00 | 95.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | May 31, 2016 | |
Comment |
Health Gansu - Percentage of total number of project health facilities built to applicable government standards that address flood and seismic hazards. | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | June 30, 2014 | |
Comment |
Health Gansu - Percentage of restored project facilities that are fully equipped according to government standards. | Value | 0.00 | 90.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | May 31, 2016 | |
Comment |
Education Gansu - Percentage of total number of project schools built to applicable government standards that address flood and seismic hazards. | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | June 30, 2014 | |
Comment |
Education Gansu - Percentage of restored project schools that are fully equipped according to government standards. | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | May 31, 2016 | |
Comment |
Capacity Building Gansu - Percentage of PMO/PIU staff trained in project management processes for earthquake reconstruction efforts. | Value | 0.00 | 100.00 | 100.00 |
Date | May 12, 2008 | May 20, 2016 | June 30, 2014 | |
Comment |
Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions. | Value | 0.00 | 186.00 | 186.00 |
Date | May 12, 2008 | May 20, 2016 | May 31, 2016 | |
Comment |
Number of water utilities that the project is supporting | Value | 0.00 | 21.00 | 21.00 |
Date | May 12, 2008 | May 20, 2016 | May 31, 2016 | |
Comment |