Haiti Education for All Fast-Track Initiative Catalytic Fund

Development Objective

The objective of the Project is to assist the Recipient in implementing its National Education for All Strategy (SNA/EPT) through the improvement of: (a) access to primary education for poor children aged 6-12; and (b) equity, quality and governance in the Recipient’s education sector.

Key Details

Project Details

  • P114174

  • Closed

  • Axelle Latortue , Juan Baron

  • Ministère de l'Economieet des Finances (MEF)

  • Haiti

  • December 11, 2009

  • (as of board presentation)

    December 11, 2009

  • July 15, 2010

  • US$ 22.00 million

  • Ministry of National Education and Vocational Training

  • Latin America and Caribbean

  • 2010

  • US$ 22.00 million

  • C

  • Not Applicable

  • October 31, 2015

  • BANK APPROVED

  • September 28, 2021

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Education for All - Fast Track Initiative 22.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 22.00
Total Project Cost** 22.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2015-08-18
Monitoring and Evaluation Moderately Satisfactory 2015-08-18
Progress towards achievement of PDO Moderately Unsatisfactory 2015-08-18
Procurement Moderately Satisfactory 2015-08-18
Financial Management Moderately Unsatisfactory 2015-08-18
Overall Implementation Progress (IP) Moderately Satisfactory 2015-08-18

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 05-31-2016
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Unsatisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Unsatisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-29-2016PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Schools participating in the teacher compensation programValue0.002824.003000.00
    DateMarch 11, 2010June 22, 2015October 31, 2015
    Comment
  • Number of children participating in school health and nutrition programValue0.0062000.0050000.00
    DateMarch 11, 2010June 22, 2015October 31, 2015
    Comment
  • Children benefiting from primary education enrollment subsidiesValue0.0083000.0083000.00
    DateOctober 24, 2011June 22, 2015October 31, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Contract signed with UNESCO for curricular and pedagogical support to the MENFPValueNoYesYes
    DateMarch 11, 2010June 22, 2015October 31, 2015
    Comment
  • Implementation of ECD action planValue0.0040.00100.00
    DateMarch 11, 2010June 22, 2015October 31, 2015
    Comment
  • Implementation of institutional strengthening action planValue0.0080.00100.00
    DateMarch 11, 2010June 22, 2015October 31, 2015
    Comment