Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 1.50 |
Borrower/Recipient | 0.30 |
P114409
Closed
Ani Balabanyan
N/A
December 18, 2008
(as of board presentation)
February 24, 2009
April 28, 2009
US$ 1.80 million
N/A
2009
US$ 1.50 million
C
January 15, 2013
September 30, 2012
BANK APPROVED
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 1.50 |
Borrower/Recipient | 0.30 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 1.50 |
Total Project Cost** | 1.80 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2012-09-24 |
Summary Global Objective Rating | Satisfactory | 2012-09-24 |
Project Management | Satisfactory | 2012-09-24 |
Financial Management | Satisfactory | 2012-09-24 |
Monitoring and Evaluation | Satisfactory | 2012-09-24 |
Overall Implementation Progress (IP) | Satisfactory | 2012-09-24 |
Procurement | Satisfactory | 2012-09-24 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 03-05-2013 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 10-31-2013 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Surface geological map is produced containing fault structures, potential recharging zones, and surface geothermal manifestations | Value | Surface geological map is produced with proposed a | ||
Date | September 10, 2012 | December 31, 2009 | ||
Comment | The target was achieved on November 15, 2009 |
Two cross sections with the visualization of the rock formation resistivity are produced; also the need for performing 3D seismic is assessed | Value | Two cross sections are produced and the justificat | ||
Date | September 10, 2012 | December 31, 2009 | ||
Comment | The target was achieved on November 15, 2009 |
3D images of the site subsurface structure with main fault zones and the depth, extent and thickness of permeable zones are produced; and at least 3 cross sections | Value | 3D images of the site subsurface structure are pro | ||
Date | September 10, 2012 | July 31, 2012 | ||
Comment | The target was achieved on May 15, 2012. |
The economic and financial rates of return are assessed and sensitivity analysis conducted | Value | The economic and financial analysis is completed | ||
Date | September 10, 2012 | September 28, 2012 | ||
Comment | Planned to be completed by September 24, 2012. |
Decision whether to drill or not to drill exploratory wells for the geothermal sites, based on the results of site investigation works | Value | drill or not drill decision made | ||
Date | September 10, 2012 | September 30, 2012 | ||
Comment | Early to measure. 3D MT sounding study and independent interpretation of results of 3D MT sounding were completed. Assessment ofeconomic and financial viability is underway; the preliminary results indicate that the plant viability critically depends on theresource temperature, which can be confirmed through exploratory drilling. The outcome indicator will be achieved by the projectclosingdate when the economic and financial assessment is completed. |