Lagos Urban Transport Project 2

Development Objective

The objectives are to improve the capacity to manage the transport sector in the Lagos Metropolitan area and enhance efficiency and effectiveness of the public transport network.

Key Details

Project Details

  • P114762

  • Closed

  • Roger Gorham

  • N/A

  • Nigeria

  • July 16, 2009

  • (as of board presentation)

    June 29, 2010

  • November 25, 2010

  • US$ 4.50 million

  • A

  • September 23, 2022

  • May 31, 2017

  • BANK APPROVED

  • P112956

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
GLOBAL ENVIRONMENT - Associated IDA Fund 190.00
Global Environment Facility (GEF) 4.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 4.50
Total Project Cost** 194.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Summary Global Objective Rating Satisfactory 2017-05-31
Project Management Satisfactory 2017-05-31
Financial Management Highly Satisfactory 2017-05-31
Monitoring and Evaluation Highly Satisfactory 2017-05-31
Overall Implementation Progress (IP) Moderately Satisfactory 2017-05-31
Procurement Satisfactory 2017-05-31
Overall Safeguards Rating Moderately Satisfactory 2017-05-31
Counterpart Funding Satisfactory 2017-05-31

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-05-2017
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencyHighly Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-08-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualityModestN/a
M&e QualityModestN/a

Results Framework