Financier | Commitments |
---|---|
Borrower/Recipient | 21.00 |
International Bank for Reconstruction and Development | 48.00 |
P114766
Closed
Mirlan Aldayarov
N/A
October 27, 2008
(as of board presentation)
September 15, 2009
January 27, 2010
US$ 69.00 million
N/A
2010
US$ 48.00 million
B
N/A
April 30, 2013
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Borrower/Recipient | 21.00 |
International Bank for Reconstruction and Development | 48.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 48.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 48.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 69.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 15, 2013 | IBRD-77380 | Int Charges | 292,286.70 |
Sep 15, 2009 | IBRD-77380 | Loan Commitment | 48,000,000.00 |
Sep 15, 2014 | IBRD-77380 | Int Charges | 269,748.10 |
Mar 15, 2015 | IBRD-77380 | Int Charges | 265,350.03 |
Mar 15, 2015 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Sep 15, 2015 | IBRD-77380 | Int Charges | 278,606.38 |
Sep 15, 2015 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Mar 15, 2016 | IBRD-77380 | Int Charges | 298,585.25 |
Mar 15, 2016 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Sep 15, 2016 | IBRD-77380 | Int Charges | 372,160.97 |
Sep 15, 2016 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Sep 15, 2017 | IBRD-77380 | Int Charges | 456,057.20 |
Sep 15, 2017 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Mar 15, 2017 | IBRD-77380 | Int Charges | 425,009.84 |
Mar 15, 2017 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Mar 15, 2018 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Mar 15, 2018 | IBRD-77380 | Int Charges | 441,538.00 |
Sep 15, 2018 | IBRD-77380 | Int Charges | 594,074.50 |
Sep 15, 2018 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Mar 15, 2019 | IBRD-77380 | Int Charges | 615,252.30 |
Mar 15, 2019 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Mar 15, 2020 | IBRD-77380 | Int Charges | 491,800.80 |
Mar 15, 2020 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Sep 15, 2019 | IBRD-77380 | Int Charges | 625,392.75 |
Sep 15, 2019 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Sep 15, 2020 | IBRD-77380 | Int Charges | 263,518.75 |
Sep 15, 2020 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Mar 15, 2021 | IBRD-77380 | Int Charges | 177,874.48 |
Mar 15, 2021 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Sep 15, 2021 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Sep 15, 2021 | IBRD-77380 | Int Charges | 160,477.27 |
Mar 15, 2022 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Mar 15, 2022 | IBRD-77380 | Int Charges | 146,167.42 |
Sep 15, 2022 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Sep 15, 2022 | IBRD-77380 | Int Charges | 282,892.62 |
Mar 15, 2023 | IBRD-77380 | Int Charges | 632,792.44 |
Mar 15, 2023 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Sep 15, 2023 | IBRD-77380 | Int Charges | 775,525.80 |
Sep 15, 2023 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Sep 15, 2023 | IBRD-77380 | Loan Repay | 10,000,000.00 |
Mar 15, 2024 | IBRD-77380 | Loan Repay | 1,118,152.80 |
Mar 15, 2024 | IBRD-77380 | Int Charges | 490,033.03 |
Mar 15, 2014 | IBRD-77380 | Int Charges | 276,593.70 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2013-04-28 |
Progress towards achievement of PDO | Satisfactory | 2013-04-28 |
Financial Management | Satisfactory | 2013-04-28 |
Monitoring and Evaluation | Satisfactory | 2013-04-28 |
Overall Implementation Progress (IP) | Satisfactory | 2013-04-28 |
Procurement | Satisfactory | 2013-04-28 |
Project Management | Satisfactory | 2013-04-28 |
Overall Safeguards Rating | Satisfactory | 2013-04-28 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-30-2013 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 06-27-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Negligible To Low | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Exemplary | N/a |
M&e Quality | High | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Partial reduction of power deficit in the southern region of Kazakhstan | Value | 865.00 | 565.00 | 615.00 |
Date | December 31, 2007 | April 12, 2013 | April 30, 2013 | |
Comment | Winter power deficit | Target achieved. Winter power deficit reduced by 300 MW. The value has been adjusted to reflect increase of the peak demand andreduction of thermal generation throughout the project implementation period. | Winter power deficit reduced by 250 MW. |
Reduction in load shedding in the Almaty power region during peak demand periods | Value | 80.00 | 0.00 | 0.00 |
Date | December 31, 2007 | April 12, 2013 | April 30, 2013 | |
Comment | Target achieved. No load shedding in Almaty region in 2012. | No load shedding. |
Reduction in CO2 emissions (in mln.metric tons) | Value | 0.00 | 1.20 | 1.20 |
Date | December 31, 2007 | April 12, 2013 | April 30, 2013 | |
Comment | Baseline scenario estimates emission of 1.20 m tons of CO2 with no project. | Target is expected to be achieved upon completion of a full year operation of the Moinak HPP. Moinak Hydroelectric Power Plant inQ4 of 2012 and Q1 of 2013 generated 0.42 TWh electricity, which equates to annual generation of about 0.84 TWh and about 1.0 mlntons of CO2 emission reductions. | Estimated 1.2 m tons of CO2 emissions avoided. |
Transmission lines constructed or rehabilitated under the project | Value | 0.00 | 325.18 | 325.00 |
Date | December 31, 2007 | April 12, 2013 | April 30, 2013 | |
Comment | No line constructed. | Target achieved. | 325 km of lines constructed. |
Additional installed peak capacity in the southern region of Kazakhstan | Value | 0.00 | 300.00 | 300.00 |
Date | December 31, 2007 | April 12, 2013 | April 30, 2013 | |
Comment | No plant commissioned | Target achieved. Both units are fully commissioned, Unit 1 was commissioned in January 2012, Unit 2 in May 2012. | Moinak HPP is commissioned with two 150MW units. |
Transmission lines rehabilitated under the project | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment | n/a | n/a |
Transmission lines constructed under the project | Value | 0.00 | 325.18 | 325.00 |
Date | December 31, 2007 | April 12, 2013 | April 30, 2013 | |
Comment | No line constructed. | Target achieved. | 325 km of lines constructed. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Turn key contracts for transmission lines and substations awarded in accordance with procurement plan | Value | 0.00 | 2.00 | 2.00 |
Date | January 31, 2010 | April 12, 2013 | December 31, 2012 | |
Comment | number of contracts awarded | Target achieved. All contracts have been concluded and fully implemented. | Contracts implemented. |
Technical assistance | Value | 0.00 | 1.00 | 1.00 |
Date | January 31, 2010 | April 12, 2013 | December 31, 2012 | |
Comment | Target achieved. The Procurement and Project Management consultant is fully engaged. |