WAPP (Phase 3) Adjarala Hydroelectric Project

Development Objective

The development objective of the WAPP Adjarala Hydropower Project (Phase 3) is to increase power supply and reduce the cost of supply in Togo and Benin.

Key Details

Project Details

  • P115063

  • Dropped

  • Franklin Koffi S.W. Gbedey

  • Ministry of Energy,Government of Togo

  • Africa

  • May 29, 2013

  • (as of board presentation)

    March 31, 2016

  • N/A

  • US$ 450.00 million

  • Communauté Electrique du Bénin (CEB)

  • Africa

  • 2016

  • US$ 390.00 million

  • A

  • December 19, 2024

  • N/A

  • Yes

  • DECISION MEETING

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
West African Development Bank 40.00
African Development Bank 100.00
FRANCE: French Agency for Development 78.00
IDA Credit 120.00
West African Economic and Monetary Union 52.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 120.00
IBRD + IDA Commitment 120.00
Lending Instrument
Grant Amount 270.00
Total Project Cost** 450.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

No data available.

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.000.003100000.00
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Female beneficiariesValue50.000.0050.00
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Energy generated under projectValue0.000.00461.00
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Average generation cost of CEBValue0.100.000.80
    DateFebruary 24, 2014December 31, 2021
    CommentUSD/kWh

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Commissioning of the Adjarala dam and power plant completedValueNoYes
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Commissioning of the power plant compleredValueNoYes
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Expert Panel’s environmental and social monitoring report made publically availableValueYesYes
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Operational manual for the dam and reservoir is completedValueNoYes
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Transmission lines constructed or rehabilitated under the projectValue0.000.00130.00
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Transmission lines constructed under the projectValue0.000.00130.00
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Generation Capacity of Hydropower constructed or rehabilitated under the projectValue0.000.00147.00
    DateFebruary 24, 2014December 31, 2021
    Comment
  • CEB staff are trained on the use of the operational manual for the dam and reservoirValueNoYes
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Potential irrigation development study completed and reviewedValueNoYes
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Flood and Mono basin management study completed and reviewedValueNoYes
    DateFebruary 24, 2014December 31, 2021
    Comment
  • Generation Capacity of Hydropower constructed under the projectValue0.000.00147.00
    DateFebruary 24, 2014December 31, 2021
    Comment