Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IDA Fund | 3.00 |
Global Environment Facility (GEF) | 1.82 |
Local Sources of Borrowing Country | 0.97 |
Borrower/Recipient | 1.32 |
P115066
Closed
Kwabena Amankwah-Ayeh
Government of Togo
June 2, 2009
(as of board presentation)
June 2, 2009
September 1, 2009
US$ 7.11 million
Ministry of Urban Development and Housing,AGETUR
2009
US$ 1.82 million
C
August 5, 2024
June 30, 2016
BANK APPROVED
Financier | Commitments |
---|---|
GLOBAL ENVIRONMENT - Associated IDA Fund | 3.00 |
Global Environment Facility (GEF) | 1.82 |
Local Sources of Borrowing Country | 0.97 |
Borrower/Recipient | 1.32 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 1.82 |
Total Project Cost** | 7.11 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2016-06-27 |
Monitoring and Evaluation | Satisfactory | 2016-06-27 |
Overall Safeguards Rating | Satisfactory | 2016-06-27 |
Project Management | Satisfactory | 2016-06-27 |
Overall Implementation Progress (IP) | Satisfactory | 2016-06-27 |
Procurement | Satisfactory | 2016-06-27 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-29-2016 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |