Togo Efficient Lighting Program

Development Objective

This subcomponent aims to rehabilitate the power distribution network in Lomé and engage in energy demand-side management by replacing existing incandescent light bulbs with compact fluorescent light bulbs (CFL) to reduce electricity use, increase access to electricity, and improve overall lighting services in beneficiary neighborhoods.

Key Details

Project Details

  • P115066

  • Closed

  • Kwabena Amankwah-Ayeh

  • Government of Togo

  • Togo

  • June 2, 2009

  • (as of board presentation)

    June 2, 2009

  • September 1, 2009

  • US$ 7.11 million

  • Ministry of Urban Development and Housing,AGETUR

  • Western and Central Africa

  • 2009

  • US$ 1.82 million

  • C

  • August 5, 2024

  • June 30, 2016

  • BANK APPROVED

  • P113415

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
GLOBAL ENVIRONMENT - Associated IDA Fund 3.00
Global Environment Facility (GEF) 1.82
Local Sources of Borrowing Country 0.97
Borrower/Recipient 1.32

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 1.82
Total Project Cost** 7.11

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Financial Management Satisfactory 2016-06-27
Monitoring and Evaluation Satisfactory 2016-06-27
Overall Safeguards Rating Satisfactory 2016-06-27
Project Management Satisfactory 2016-06-27
Overall Implementation Progress (IP) Satisfactory 2016-06-27
Procurement Satisfactory 2016-06-27

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-29-2016
Outcomes
Risk to Development OutcomeSubstantial
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.