Financier | Commitments |
---|---|
EFA-FTI Education Program Development Fund | 28.00 |
P115427
Closed
Ryoko Tomita
N/A
April 29, 2009
(as of board presentation)
August 6, 2009
August 6, 2009
US$ 28.00 million
N/A
2010
US$ 28.00 million
B
Not Applicable
September 30, 2013
BANK APPROVED
July 17, 2024
Financier | Commitments |
---|---|
EFA-FTI Education Program Development Fund | 28.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 28.00 |
Total Project Cost** | 28.00 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Moderately Satisfactory | 2013-09-26 |
Procurement | Moderately Satisfactory | 2013-09-26 |
Overall Safeguards Rating | Satisfactory | 2013-09-26 |
Progress towards achievement of PDO | Satisfactory | 2013-09-26 |
Financial Management | Satisfactory | 2013-09-26 |
Overall Implementation Progress (IP) | Satisfactory | 2013-09-26 |
Counterpart Funding | Satisfactory | 2013-09-26 |
Project Management | Satisfactory | 2013-09-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 04-09-2014 |
---|---|
Outcomes | |
Risk to Development Outcome | Substantial |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 09-15-2014 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Moderate | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 332377.00 | 326074.00 |
Date | August 31, 2013 | September 30, 2013 | ||
Comment | All LBS and UBS teachers have been trained (7,602 teachers). Also, all of students are beneficiaries (324,775). |
Gross enrolment at lower basic school | Value | 89.60 | 90.00 | 89.00 |
Date | December 30, 2008 | August 31, 2013 | September 30, 2013 | |
Comment | The population data was updated, therefore the 2008 baseline has been adjusted. | Reaching the last 10% is extremely complex and will be one of the priorities under the new project.89% for boys and 91% for girls |
% of qualified teachers (LBS) | Value | 70.00 | 79.43 | 85.60 |
Date | December 30, 2008 | August 31, 2013 | September 30, 2013 | |
Comment | Excluding teacher trainees. Data are for Government and Grant aided schools. |
GER Gender Parity LBS | Value | 1.03 | 1.03 | 1.03 |
Date | December 31, 2008 | August 31, 2013 | September 30, 2013 | |
Comment |
Average correct words per minutes (EGRA), Grade 2 | Value | 3.98 | 12.40 | 0.00 |
Date | September 30, 2007 | September 12, 2013 | ||
Comment | This is an actual result of the 2013 EGRA. |
Female beneficiaries | Value | 0.00 | 50.50 | 50.50 |
Date | August 31, 2013 | September 30, 2013 | ||
Comment |
Average correct words per minutes (EGRA) Grade 3 | Value | 9.28 | 21.40 | 0.00 |
Date | September 30, 2007 | September 12, 2013 | ||
Comment | This is an actual result of the 2013 EGRA. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Teacher-Pupil Ratio at lower basic school | Value | 1:41 | 1:32 | 1:39 |
Date | September 30, 2009 | August 31, 2013 | September 30, 2013 | |
Comment | The EMIS data structure changed in 2010, so data before that do not align with the current data. Therefore, this baseline comesfrom CSR. It includes teacher trainees. | The data includes teacher trainees. The data does not include basic cycle schools. The latest data show that including TTs, it is1:40 in 2010 and 1:38 in 2011. |
Teacher-Pupil Ratio at upper basic school | Value | 1:38 | 1:27 | 1:39 |
Date | September 30, 2009 | August 31, 2013 | September 30, 2013 | |
Comment | The EMIS data structure changed in 2010, so data before that do not align with the current data. Therefore, this baseline comesfrom CSR. It includes teacher trainees. | The data include teacher trainees. |
Pupil: Textbooks ratio at lower basic school | Value | 1:1 | 2:1 | 1:1 |
Date | December 30, 2008 | August 31, 2013 | September 30, 2013 | |
Comment | All core subjects for grades 5-6 will be delivered before project closing date. Once they are delivered to schools, the ratio willbe 1:1. |
Pupil: Textbooks ratio at upper basic school | Value | 3:1 | 2:1 | 1:1 |
Date | December 30, 2008 | August 31, 2013 | September 30, 2013 | |
Comment | Textbooks and teachers' guides of Two subjects (Science and Social & Environmental Studies) for grades 7-9 will be deliveredbeforeproject closing date. Once they are delivered to schools, the ratio will be 1:1. |
% of schools with approved school development plans | Value | 90 | 100% | 100% |
Date | December 30, 2009 | August 31, 2013 | September 30, 2013 | |
Comment |
Frequency and duration of support visits to schools by cluster monitors | Value | 2h | 4-hour visit to each school, 3 times per month | 4-hour visit to each school, 3 times per month |
Date | December 30, 2008 | August 31, 2013 | September 30, 2013 | |
Comment |
Education share of budget | Value | 14.00 | 20.07 | 20.00 |
Date | December 30, 2008 | August 31, 2013 | September 30, 2013 | |
Comment |
Availability of sector statistics by February of each year | Value | 2007 data available | 2012/13 available | 2012/13 available |
Date | December 30, 2009 | August 31, 2013 | September 30, 2013 | |
Comment |
Performance management system is functional and helps informs key personnel decisions | Value | Yes | Yes | Yes |
Date | December 31, 2008 | August 31, 2013 | September 30, 2013 | |
Comment | All job profiles completed in all directorates |
Mean score of Grade 3 level English on NAT | Value | 37.70 | 45.57 | 0.00 |
Date | January 31, 2012 | August 31, 2013 | ||
Comment | This is an actual result of the 2013 NAT. |
Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions. | Value | 0.00 | 396.00 | 396.00 |
Date | December 31, 2008 | August 31, 2013 | September 30, 2013 | |
Comment | Construction of 252 classrooms and rehabilitation of 144 classrooms | Construction of 252 classrooms and rehabilitation of 144 classrooms |
Mean score of Grade 3 Level Math on NAT | Value | 36.50 | 47.20 | 0.00 |
Date | January 31, 2012 | August 31, 2013 | ||
Comment |