Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 50.00 |
P116152
Closed
Ernesto Sanchez-Triana
N/A
October 13, 2009
(as of board presentation)
December 8, 2009
December 22, 2009
US$ 50.00 million
Ministry of Economy and Finance
2010
US$ 50.00 million
N/A
Not Applicable
December 31, 2012
BANK APPROVED
April 7, 2018
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 50.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 50.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 8, 2009 | IBRD-78100 | Loan Commitment | 50,000,000.00 |
Sep 15, 2013 | IBRD-78100 | Int Charges | 178,888.90 |
Mar 15, 2023 | IBRD-78100 | Int Charges | 1,211,215.50 |
Sep 15, 2023 | IBRD-78100 | Int Charges | 19,096.88 |
Sep 15, 2023 | IBRD-78100 | Int Charges | 1,408,196.90 |
Mar 15, 2024 | IBRD-78100 | Int Charges | 1,570,014.50 |
Mar 15, 2024 | IBRD-78100 | Int Charges | 25,653.75 |
Sep 15, 2021 | IBRD-78100 | Int Charges | 181,444.44 |
Mar 15, 2022 | IBRD-78100 | Int Charges | 170,944.44 |
Sep 15, 2022 | IBRD-78100 | Int Charges | 418,142.84 |
Mar 15, 2019 | IBRD-78100 | Int Charges | 766,736.10 |
Mar 15, 2020 | IBRD-78100 | Int Charges | 642,055.56 |
Sep 15, 2019 | IBRD-78100 | Int Charges | 812,666.70 |
Sep 15, 2020 | IBRD-78100 | Int Charges | 311,777.78 |
Mar 15, 2021 | IBRD-78100 | Int Charges | 196,083.33 |
Sep 15, 2017 | IBRD-78100 | Int Charges | 477,888.90 |
Mar 15, 2018 | IBRD-78100 | Int Charges | 480,152.78 |
Sep 15, 2018 | IBRD-78100 | Int Charges | 705,333.30 |
Mar 15, 2017 | IBRD-78100 | Int Charges | 417,305.56 |
Mar 15, 2016 | IBRD-78100 | Int Charges | 224,972.22 |
Sep 15, 2016 | IBRD-78100 | Int Charges | 327,111.10 |
Sep 15, 2015 | IBRD-78100 | Int Charges | 186,555.56 |
Mar 15, 2015 | IBRD-78100 | Int Charges | 158,375.00 |
Sep 15, 2014 | IBRD-78100 | Int Charges | 153,333.34 |
Mar 15, 2014 | IBRD-78100 | Int Charges | 163,402.77 |
Mar 15, 2023 | IBRD-78100 | Int Charges | 57,029.80 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2012-07-09 |
Monitoring and Evaluation | Satisfactory | 2012-07-09 |
Program Management | Satisfactory | 2012-07-09 |
Overall Implementation Progress (IP) | Satisfactory | 2012-07-09 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 09-30-2016 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Negligible |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 05-22-2017 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Negligible | N/a |
Bank Performance | Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | High | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
MINAM has the capacity to review at least 5 Environmental Impact Assessments (EIAs) of large infrastructure/investment projects with potentially significant impacts. | Value | zero | MINAM has reviewed 150 EIAs. | At least 10 projects reviewed per year. |
Date | September 30, 2008 | June 21, 2012 | December 31, 2012 | |
Comment |
National Service of Natural Protected Areas applies financial strategy to increase national protected areas funding from various sources (including private sector) by at least US$2 million/yr | Value | $14.2 million | The budget for 2012 was set at approximately $16.5 | $24 million |
Date | September 30, 2008 | June 21, 2012 | December 31, 2012 | |
Comment |
Air quality data Lima-Callao metropolitan region is widely published and disseminated (in real time) through harmonized monitoring network. | Value | No pollution contigency plans exist in Peru except | Air quality data for Lima-Callao region is publish | Harmonized monitoring network publishes air qualit |
Date | September 30, 2008 | June 21, 2012 | December 31, 2012 | |
Comment |
Priority Mining Environmental LEgacies identified following the priority-setting update | Value | No mining environmental legacies have been identif | 119 priority mining environmental legacies have be | At least 10 priority mining environmental legacies |
Date | September 30, 2008 | June 21, 2012 | December 31, 2012 | |
Comment |
Environmental participatory monitoring | Value | 35 community-based monitoring pilots | To date, 43 community participatory monitoring com | Environmental participatory monitoring undertaken |
Date | September 30, 2008 | June 21, 2012 | December 31, 2012 | |
Comment |
Gas stations supplying clean diesel (with less than 50ppm of sulfur content) | Value | zero gas stations | All stations in Lima-Callao are now supplying clea | At least 30 percent of gas stations in main cities |
Date | September 30, 2008 | June 21, 2012 | December 31, 2012 | |
Comment |
Conversion of gasoline vehicles to natural gas and natural gas service stations installed and operating. | Value | 35,000 vehicles converted to natural gas in Lima | By February 2012, approximately 130,000 vehicles h | At least 80,000 vehicles converted to natural as a |
Date | September 30, 2008 | June 21, 2012 | December 31, 2012 | |
Comment |
Vehicle inspection and maintenance system operating in Lima | Value | 6 inspection lanes operational in Lima for heavy-d | 556,626 vehicles inspected in Lima-Callao; 47,688 | At least 20 lanes for vehicle inspection and maint |
Date | September 30, 2008 | June 21, 2012 | December 31, 2012 | |
Comment |
Anchoveta fishing fleet under quota system | Value | zero percent regulated by quotas | 100 percent now regulated | 100 percent of anchoveta fleet under the quota sys |
Date | September 30, 2008 | June 21, 2012 | December 31, 2012 | |
Comment |
Promote sustainable fisheries | Value | Zero workers benefit from economic incentives for | By April 2012, 2,125 fishermen have taken advantag | At least 3000 workers benefit from economic incent |
Date | September 30, 2008 | June 21, 2012 | December 31, 2012 | |
Comment |
Report on the economic, environmental and social consequences of anchoveta quota system is issued by an independent observatory | Value | None | 1.Estudio De Línea De Base Sobre La Repercusión So | Report on the economic, environmental and social c |
Date | September 30, 2008 | June 21, 2010 | December 31, 2012 | |
Comment |