Financier | Commitments |
---|---|
Special Financing | 8.00 |
Islamic Development Bank | 8.00 |
P116199
Closed
Monali Ranade
Palestine Liberation Organization (for the Benefit of the Palestinian Authority)
December 29, 2011
(as of board presentation)
March 6, 2012
June 18, 2012
US$ 16.00 million
Palestinian Energy and National Resources Authority
2012
US$ 16.00 million
B
Not Applicable
June 30, 2020
Yes
BANK APPROVED
October 18, 2022
Financier | Commitments |
---|---|
Special Financing | 8.00 |
Islamic Development Bank | 8.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 16.00 |
Total Project Cost** | 16.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2020-06-29 |
Monitoring and Evaluation | Moderately Satisfactory | 2020-06-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2020-06-29 |
Procurement | Moderately Satisfactory | 2020-06-29 |
Project Management | Moderately Satisfactory | 2020-06-29 |
Financial Management | Moderately Satisfactory | 2020-06-29 |
Overall Safeguards Rating | Satisfactory | 2020-06-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-29-2021 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Highly Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-22-2021 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 190000.00 | 0.00 |
Date | September 19, 2014 | June 22, 2020 | ||
Comment |
Female beneficiaries | Value | 0.00 | 46.00 | 0.00 |
Date | September 19, 2014 | February 26, 2018 | ||
Comment |
People provided with access to electricity by household connections | Value | 0.00 | 190000.00 | 0.00 |
Date | September 19, 2014 | June 22, 2020 | ||
Comment |
People provided with access to electricity by hhold connections-Grid | Value | 0.00 | 190000.00 | 0.00 |
Date | September 19, 2014 | June 22, 2020 | ||
Comment |
Community electricity reconnections to the grid | Value | 0.00 | 650.00 | 0.00 |
Date | September 19, 2014 | June 24, 2020 | ||
Comment |
Water pumping stations reconnected to the grid | Value | 0.00 | 90.00 | 0.00 |
Date | September 19, 2014 | June 24, 2020 | ||
Comment |
Commercial consumers reconnected to the grid | Value | 0.00 | 600.00 | 0.00 |
Date | September 19, 2014 | June 24, 2020 | ||
Comment |
Hospitals and clinics reconnected to the grid | Value | 0.00 | 9.00 | 0.00 |
Date | September 19, 2014 | June 24, 2020 | ||
Comment |
System Loss Reduction | Value | 30.00 | 28.00 | 0.00 |
Date | September 19, 2014 | June 24, 2020 | December 31, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Replenishment of materials for emergency repairs | Value | 0.00 | 100.00 | 0.00 |
Date | September 19, 2014 | June 24, 2020 | ||
Comment |
Electricity Master Plan for Gaza | Value | No masterplan | Completed | Final master plan complete |
Date | June 1, 2012 | June 22, 2020 | June 1, 2013 | |
Comment |
Distribution lines constructed or rehabilitated under the project | Value | 0.00 | 460.00 | 0.00 |
Date | June 1, 2012 | June 24, 2020 | ||
Comment |
Distribution lines constructed under the project | Value | 0.00 | 460.00 | 0.00 |
Date | June 1, 2012 | June 24, 2020 | ||
Comment |
Transmission lines constructed or rehabilitated under the project | Value | 0.00 | 125.00 | 0.00 |
Date | June 1, 2012 | June 24, 2020 | ||
Comment |
Transmission lines constructed under the project | Value | 0.00 | 125.00 | 0.00 |
Date | June 1, 2012 | June 24, 2020 | ||
Comment |
Incremental increase in MVA capacity of MV Feeders | Value | 0.00 | 40.00 | 40.00 |
Date | June 1, 2012 | June 24, 2020 | June 1, 2015 | |
Comment |
Grievances registered related to delivery of project benefits addressed (%) | Value | 0.00 | 0.00 | 0.00 |
Date | September 19, 2014 | June 24, 2020 | ||
Comment |
Grievances related to delivery of project benefits that are addressed-(number) | Value | 0.00 | 0.00 | 0.00 |
Date | September 19, 2014 | February 18, 2018 | ||
Comment |