Energy Efficiency Project

Abstract*

The development objective of the Energy Efficiency Project for Armenia is to reduce energy consumption of social and other public facilities. The global environmental objective is to decrease greenhouse gas emissions through the removal of barriers to the implementation of energy efficiency investments in the public sector. There are two components to the project. The first component of the project is Energy efficiency investments in public facilities...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to reduce energy consumption of social and other public facilities. The global environmental objective is to decrease greenhouse gas emissions through the removal of barriers to the implementation of energy efficiency investments in the public sector.

Key Details

Project Details

  • P116680

  • Closed

  • Ani Balabanyan , Jasneet Singh

  • Republic of Armenia

  • Armenia

  • April 28, 2010

  • (as of board presentation)

    March 27, 2012

  • August 10, 2012

  • US$ 10.66 million

  • Armenia Renewable Resources and Energy Efficiency Fund

  • Europe and Central Asia

  • 2012

  • US$ 1.82 million

  • B

  • October 2, 2023

  • June 30, 2016

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 8.84
Global Environment Facility (GEF) 1.82

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 1.82
Total Project Cost** 10.66

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2016-06-09
Project Management Satisfactory 2016-06-09
Monitoring and Evaluation Satisfactory 2016-06-09
Overall Implementation Progress (IP) Highly Satisfactory 2016-06-09
Summary Global Objective Rating Highly Satisfactory 2016-06-09
Procurement Satisfactory 2016-06-09
Financial Management Satisfactory 2016-06-09

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-22-2016
OutcomesHighly Satisfactory
Risk to Development OutcomeNegligible
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencyHighly Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-06-2017PROJECT PERFORMANCE ASSESSMENT REPORT: 03-28-2019
Outcome RatingHighly Satisfactory Moderately Satisfactory
Risk To Development OutcomeModestSubstantial
Bank PerformanceSatisfactoryModerately Satisfactory
Borrower PerformanceSatisfactoryModerately Satisfactory
Government PerformanceSatisfactoryNot Rated
Implementing AgencySatisfactorySatisfactory
Icr QualitySubstantialNot Rated
M&e QualityHighModest

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • CO2 emission reductions in retrofitted social and other public facilities through energy efficiency investmentsValue0.00137569.0050549.00
    DateJuly 3, 2012April 30, 2016June 30, 2016
    Comment
  • Energy savings in retrofitted social and other public facilitiesValue0.00540.24215.69
    DateJuly 3, 2012April 30, 2016June 30, 2016
    Comment
  • Regulations, legislative amendments, guidelines to further promote energy efficiencyValueNoYesYes
    DateJuly 3, 2012April 30, 2016June 30, 2016
    Comment
  • Number of public sector projects commissionedValue0.0098.0085.00
    DateJuly 3, 2012April 30, 2016June 30, 2016
    Comment
  • Cumulative investments in social and other public facilitiesValue0.009885955.006000000.00
    DateJuly 3, 2012April 30, 2016June 30, 2016
    Comment