Skip to Main Navigation

Alma Transmission Project

Abstract*

The objective of the Alma Electricity Transmission Project for Kazakhstan is to improve the reliability and quality of electricity supply to consumers in the Almaty region in an environmentally responsible and financially sustainable manner. There are three components to the project: (1) construction of transmission lines provision of goods and works for: (a) construction of a 500 kV overhead transmission line (OHTL) from Alma substation to Almaty...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective is to improve the reliability and quality of electricity supply to consumers in the Almaty region in an environmentally responsible and financially sustainable manner.

Key Details

Project Details

  • P116919

  • Closed

  • Mirlan Aldayarov

  • Kazakhstan Electricity Grid Operating Company (KEGOC)

  • Kazakhstan

  • September 3, 2009

  • (as of board presentation)

    November 16, 2010

  • March 2, 2011

  • US$ 200.90 million

  • Kazakhstan Electricity Transmission Grid Operating Company (KEGOC)

  • Europe and Central Asia

  • 2011

  • US$ 78.00 million

  • B

  • N/A

  • April 30, 2015

  • BANK APPROVED

  • October 2, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 122.90
International Bank for Reconstruction and Development 78.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 78.00
IDA Commitment N/A
IBRD + IDA Commitment 78.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 200.90

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 16, 2010 IBRD-79650 Loan Commitment 78,000,000.00
Jan 15, 2014 IBRD-79650 Int Charges 162.82
Jan 15, 2014 IBRD-79650 Int Charges 345,339.40
Jan 3, 2014 IBRD-79650 Loan Disb 5,319,965.00
Feb 28, 2014 IBRD-79650 Loan Disb 5,511,812.50
May 2, 2014 IBRD-79650 Loan Disb 200,000.00
Jul 15, 2014 IBRD-79650 Int Charges 15,628.35
Jul 15, 2014 IBRD-79650 Int Charges 520,225.25
Jul 8, 2014 IBRD-79650 Loan Disb 455,141.16
Jan 15, 2015 IBRD-79650 Int Charges 131.86
Jul 15, 2022 IBRD-79650 Int Charges 375,356.75
Jan 15, 2015 IBRD-79650 Int Charges 539,771.25
Jul 15, 2022 IBRD-79650 Loan Repay 1,783,909.00
Jan 15, 2022 IBRD-79650 Int Charges 331,886.38
Jan 15, 2022 IBRD-79650 Loan Repay 1,783,909.00
Sep 1, 2022 IBRD-79650 Int Charges 959,700.70
Sep 1, 2022 IBRD-79650 Int Charges 260,355.58
Sep 1, 2022 IBRD-79650 Loan Repay 46,381,636.00
Jul 15, 2020 IBRD-79650 Int Charges 844,326.10
Jul 15, 2020 IBRD-79650 Loan Repay 1,783,909.00
Jan 15, 2021 IBRD-79650 Int Charges 407,563.75
Jan 15, 2021 IBRD-79650 Loan Repay 1,783,909.00
Jul 15, 2021 IBRD-79650 Int Charges 364,145.38
Jul 15, 2021 IBRD-79650 Loan Repay 1,783,909.00
Jul 15, 2019 IBRD-79650 Int Charges 1,186,880.80
Jul 15, 2019 IBRD-79650 Loan Repay 1,783,909.00
Jan 15, 2020 IBRD-79650 Int Charges 980,341.25
Jan 15, 2020 IBRD-79650 Loan Repay 1,783,909.00
Jul 15, 2017 IBRD-79650 Int Charges 823,004.44
Jul 15, 2017 IBRD-79650 Loan Repay 1,783,909.00
Jan 15, 2018 IBRD-79650 Int Charges 856,704.50
Jan 15, 2018 IBRD-79650 Loan Repay 1,783,909.00
Jul 15, 2018 IBRD-79650 Int Charges 951,172.90
Jul 15, 2018 IBRD-79650 Loan Repay 1,783,909.00
Jan 15, 2019 IBRD-79650 Int Charges 1,137,713.80
Jan 15, 2019 IBRD-79650 Loan Repay 1,783,909.00
Jul 15, 2015 IBRD-79650 Int Charges 541,733.50
Jan 15, 2016 IBRD-79650 Int Charges 587,183.56
Jan 15, 2016 IBRD-79650 Loan Repay 1,783,909.00
Jul 15, 2016 IBRD-79650 Int Charges 706,972.06
Jul 15, 2016 IBRD-79650 Loan Repay 1,783,909.00
Jan 15, 2017 IBRD-79650 Int Charges 737,991.25
Jan 15, 2017 IBRD-79650 Loan Repay 1,783,909.00
Jul 30, 2014 IBRD-79650 Loan Cancel 6,643,638.50
Jul 15, 2013 IBRD-79650 Int Charges 438.67
Aug 28, 2013 IBRD-79650 Loan Disb 18,786,940.00
Jul 15, 2013 IBRD-79650 Int Charges 220,871.33
Nov 13, 2013 IBRD-79650 Loan Disb 7,228,834.50
Nov 15, 2013 IBRD-79650 Loan Disb 200,000.00
Dec 4, 2013 IBRD-79650 Loan Disb 6,831,942.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2015-04-10
Financial Management Highly Satisfactory 2015-04-10
Monitoring and Evaluation Satisfactory 2015-04-10
Procurement Satisfactory 2015-04-10
Project Management Satisfactory 2015-04-10
Counterpart Funding Satisfactory 2015-04-10
Overall Implementation Progress (IP) Satisfactory 2015-04-10

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 10-30-2015
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 08-12-2016PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeModestN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceSatisfactoryN/a
Government PerformanceSatisfactoryN/a
Implementing AgencySatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increased Reliability of Supply measured by reduced outages in Almaty Branch of KEGOCValue
    DateDecember 30, 2009April 7, 2015April 30, 2015
    Comment
  • Increased capacity to supply Almaty Oblast measured by capacity of 500 kV transformers connected to HV networkValue1000MVA2000MVA2000MVA
    DateDecember 30, 2009April 30, 2015April 30, 2015
    Comment
  • Increased capacity to supply Almaty Oblast measured by reduced overloading of transformers in Almaty SS relative to design capacityValue109.0060.0070.00
    DateDecember 30, 2009April 30, 2015April 30, 2015
    Comment
  • Increased Transmission Line Capacity for Almaty OblastValue650MW in 1 line from YuKGRES SS1,500 MW in 2 lines from YuKGRES SS1,300 MW in 2 lines from YuKGRES SS
    DateDecember 30, 2009April 30, 2015April 30, 2015
    Comment
  • Transmission lines constructed or rehabilitated under the projectValue0.00321.70319.00
    DateDecember 30, 2009April 30, 2015April 30, 2015
    Comment
  • Frequency of outages per yearValue29 outages2 outages10 outages
    DateDecember 30, 2009April 30, 2015April 30, 2015
    Comment
  • total duration of outages per year, in hoursValue111.11.2540
    DateDecember 30, 2009April 30, 2015April 30, 2015
    Comment
  • Total amount of unserved energy from outagesValue0.169 GWh0.092 GWh0.140 GWh
    DateDecember 30, 2009April 30, 2015April 30, 2015
    Comment
  • Transmission lines constructed under the projectValue0.00321.70319.00
    DateDecember 30, 2009April 30, 2015April 30, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Construction and commissioning of linesValueNo lines.321.7 kms of new lines were constructed and operatNew lines operational
    DateApril 30, 2015April 30, 2015
    Comment
  • Construction of Alma SSValueNo substationConstruction of Alma SS is completed and it is opeAlma SS operational
    DateApril 30, 2015April 30, 2015
    Comment
  • Modernization of Almaty and YuKGRES SSsValueSubstations exist but are in poor operating conditComplete and commissionedSubstations are operational.
    DateDecember 30, 2009July 30, 2014April 30, 2015
    Comment