Financier | Commitments |
---|---|
Borrower/Recipient | 122.90 |
International Bank for Reconstruction and Development | 78.00 |
P116919
Closed
Mirlan Aldayarov
Kazakhstan Electricity Grid Operating Company (KEGOC)
September 3, 2009
(as of board presentation)
November 16, 2010
March 2, 2011
US$ 200.90 million
Kazakhstan Electricity Transmission Grid Operating Company (KEGOC)
2011
US$ 78.00 million
B
N/A
April 30, 2015
BANK APPROVED
October 2, 2023
Financier | Commitments |
---|---|
Borrower/Recipient | 122.90 |
International Bank for Reconstruction and Development | 78.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 78.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 78.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 200.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 16, 2010 | IBRD-79650 | Loan Commitment | 78,000,000.00 |
Jan 15, 2014 | IBRD-79650 | Int Charges | 162.82 |
Jan 15, 2014 | IBRD-79650 | Int Charges | 345,339.40 |
Jan 3, 2014 | IBRD-79650 | Loan Disb | 5,319,965.00 |
Feb 28, 2014 | IBRD-79650 | Loan Disb | 5,511,812.50 |
May 2, 2014 | IBRD-79650 | Loan Disb | 200,000.00 |
Jul 15, 2014 | IBRD-79650 | Int Charges | 15,628.35 |
Jul 15, 2014 | IBRD-79650 | Int Charges | 520,225.25 |
Jul 8, 2014 | IBRD-79650 | Loan Disb | 455,141.16 |
Jan 15, 2015 | IBRD-79650 | Int Charges | 131.86 |
Jul 15, 2022 | IBRD-79650 | Int Charges | 375,356.75 |
Jan 15, 2015 | IBRD-79650 | Int Charges | 539,771.25 |
Jul 15, 2022 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jan 15, 2022 | IBRD-79650 | Int Charges | 331,886.38 |
Jan 15, 2022 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Sep 1, 2022 | IBRD-79650 | Int Charges | 959,700.70 |
Sep 1, 2022 | IBRD-79650 | Int Charges | 260,355.58 |
Sep 1, 2022 | IBRD-79650 | Loan Repay | 46,381,636.00 |
Jul 15, 2020 | IBRD-79650 | Int Charges | 844,326.10 |
Jul 15, 2020 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jan 15, 2021 | IBRD-79650 | Int Charges | 407,563.75 |
Jan 15, 2021 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jul 15, 2021 | IBRD-79650 | Int Charges | 364,145.38 |
Jul 15, 2021 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jul 15, 2019 | IBRD-79650 | Int Charges | 1,186,880.80 |
Jul 15, 2019 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jan 15, 2020 | IBRD-79650 | Int Charges | 980,341.25 |
Jan 15, 2020 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jul 15, 2017 | IBRD-79650 | Int Charges | 823,004.44 |
Jul 15, 2017 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jan 15, 2018 | IBRD-79650 | Int Charges | 856,704.50 |
Jan 15, 2018 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jul 15, 2018 | IBRD-79650 | Int Charges | 951,172.90 |
Jul 15, 2018 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jan 15, 2019 | IBRD-79650 | Int Charges | 1,137,713.80 |
Jan 15, 2019 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jul 15, 2015 | IBRD-79650 | Int Charges | 541,733.50 |
Jan 15, 2016 | IBRD-79650 | Int Charges | 587,183.56 |
Jan 15, 2016 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jul 15, 2016 | IBRD-79650 | Int Charges | 706,972.06 |
Jul 15, 2016 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jan 15, 2017 | IBRD-79650 | Int Charges | 737,991.25 |
Jan 15, 2017 | IBRD-79650 | Loan Repay | 1,783,909.00 |
Jul 30, 2014 | IBRD-79650 | Loan Cancel | 6,643,638.50 |
Jul 15, 2013 | IBRD-79650 | Int Charges | 438.67 |
Aug 28, 2013 | IBRD-79650 | Loan Disb | 18,786,940.00 |
Jul 15, 2013 | IBRD-79650 | Int Charges | 220,871.33 |
Nov 13, 2013 | IBRD-79650 | Loan Disb | 7,228,834.50 |
Nov 15, 2013 | IBRD-79650 | Loan Disb | 200,000.00 |
Dec 4, 2013 | IBRD-79650 | Loan Disb | 6,831,942.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2015-04-10 |
Financial Management | Highly Satisfactory | 2015-04-10 |
Monitoring and Evaluation | Satisfactory | 2015-04-10 |
Procurement | Satisfactory | 2015-04-10 |
Project Management | Satisfactory | 2015-04-10 |
Counterpart Funding | Satisfactory | 2015-04-10 |
Overall Implementation Progress (IP) | Satisfactory | 2015-04-10 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 10-30-2015 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 08-12-2016 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Modest | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increased Reliability of Supply measured by reduced outages in Almaty Branch of KEGOC | Value | |||
Date | December 30, 2009 | April 7, 2015 | April 30, 2015 | |
Comment |
Increased capacity to supply Almaty Oblast measured by capacity of 500 kV transformers connected to HV network | Value | 1000MVA | 2000MVA | 2000MVA |
Date | December 30, 2009 | April 30, 2015 | April 30, 2015 | |
Comment |
Increased capacity to supply Almaty Oblast measured by reduced overloading of transformers in Almaty SS relative to design capacity | Value | 109.00 | 60.00 | 70.00 |
Date | December 30, 2009 | April 30, 2015 | April 30, 2015 | |
Comment |
Increased Transmission Line Capacity for Almaty Oblast | Value | 650MW in 1 line from YuKGRES SS | 1,500 MW in 2 lines from YuKGRES SS | 1,300 MW in 2 lines from YuKGRES SS |
Date | December 30, 2009 | April 30, 2015 | April 30, 2015 | |
Comment |
Transmission lines constructed or rehabilitated under the project | Value | 0.00 | 321.70 | 319.00 |
Date | December 30, 2009 | April 30, 2015 | April 30, 2015 | |
Comment |
Frequency of outages per year | Value | 29 outages | 2 outages | 10 outages |
Date | December 30, 2009 | April 30, 2015 | April 30, 2015 | |
Comment |
total duration of outages per year, in hours | Value | 111.1 | 1.25 | 40 |
Date | December 30, 2009 | April 30, 2015 | April 30, 2015 | |
Comment |
Total amount of unserved energy from outages | Value | 0.169 GWh | 0.092 GWh | 0.140 GWh |
Date | December 30, 2009 | April 30, 2015 | April 30, 2015 | |
Comment |
Transmission lines constructed under the project | Value | 0.00 | 321.70 | 319.00 |
Date | December 30, 2009 | April 30, 2015 | April 30, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Construction and commissioning of lines | Value | No lines. | 321.7 kms of new lines were constructed and operat | New lines operational |
Date | April 30, 2015 | April 30, 2015 | ||
Comment |
Construction of Alma SS | Value | No substation | Construction of Alma SS is completed and it is ope | Alma SS operational |
Date | April 30, 2015 | April 30, 2015 | ||
Comment |
Modernization of Almaty and YuKGRES SSs | Value | Substations exist but are in poor operating condit | Complete and commissioned | Substations are operational. |
Date | December 30, 2009 | July 30, 2014 | April 30, 2015 | |
Comment |