DJ-Rural Community Development and Water Mobilization Project (PRODERMO)

Abstract*

The objective of the Rural Community Development and Water Mobilization (PRODERMO) Project for Djibouti is to increase access of rural communities to water and enhance their capacity to manage water and agro-pastoral resources in the project areas using a participatory approach to community-based development. There are three components to the project, the first component being priority community investment subprojects. This component will finance...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to increase access of rural communities to water and enhance their capacity to manage water and agro-pastoral resources in the project areas using a participatory approach to community-based development.

Key Details

Project Details

  • P117355

  • Closed

  • Mohamed Medouar

  • Ministry of Economy and Finance in charge of Industry

  • Djibouti

  • June 8, 2010

  • (as of board presentation)

    June 14, 2011

  • January 19, 2012

  • US$ 6.13 million

  • Ministry of Agriculture, Water, Fisheries, Livestock and Halieutic Resources (MAEPERH)

  • Middle East and North Africa

  • 2011

  • US$ 5.83 million

  • B

  • Not Applicable

  • December 31, 2019

  • BANK APPROVED

  • June 29, 2020

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 5.83
Borrower/Recipient 0.30

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 5.83
IBRD + IDA Commitment 5.83
Lending Instrument
Grant Amount N/A
Total Project Cost** 6.13

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 3, 2018 IDA-58260 Loan Disb 442,862.44
Jun 15, 2018 IDA-58260 Loan Disb 561,062.25
Oct 12, 2017 IDA-58260 Int Charges 3,516.79
Oct 12, 2017 IDA-58260 Int Charges 3,516.79
Oct 12, 2017 IDA-58260 Int Charges 783.33
Oct 12, 2017 IDA-58260 Int Charges 783.33
Oct 12, 2017 IDA-58260 Int Charges 1,305.55
Oct 12, 2017 IDA-58260 Int Charges 5,839.42
Jul 26, 2017 IDA-H7780 Loan Disb 268,022.03
Dec 26, 2017 IDA-H7780 Loan Disb 160,716.50
Feb 20, 2018 IDA-58260 Loan Disb 124,494.63
Feb 16, 2017 IDA-58260 Loan Disb 800,000.00
May 17, 2017 IDA-H7780 Loan Disb 62,696.05
Jul 24, 2017 IDA-H7780 Loan Disb 52,999.20
Jul 31, 2017 IDA-58260 Loan Disb 300,262.34
Nov 28, 2017 IDA-58260 Loan Disb 472,123.70
Nov 28, 2017 IDA-58260 Loan Disb 144,840.66
Jul 24, 2017 IDA-H7780 Loan Disb 38,786.47
Aug 17, 2016 IDA-H7060 Loan Disb 183,097.34
Aug 17, 2016 IDA-H7780 Loan Disb 141,435.55
Jan 30, 2017 IDA-H7060 Loan Disb 226,855.53
Dec 22, 2015 IDA-H7060 Loan Disb 180,370.73
Dec 24, 2015 IDA-H7060 Loan Disb -237,587.17
Feb 1, 2016 IDA-H7780 Loan Disb 127,415.03
Mar 2, 2016 IDA-H7060 Loan Disb 179,328.10
Dec 21, 2015 IDA-H7060 Loan Disb 237,587.16
Apr 7, 2016 IDA-H7780 Loan Disb 126,201.36
May 3, 2016 IDA-H7060 Loan Disb 190,299.81
May 3, 2016 IDA-H7780 Loan Disb 120,746.93
Mar 14, 2016 IDA-H7060 Loan Disb 300,939.47
Nov 30, 2016 IDA-H7060 Loan Disb 323,906.12
Nov 30, 2016 IDA-H7780 Loan Disb 76,455.61
Jun 1, 2015 IDA-H7060 Loan Disb 68,578.54
May 31, 2016 IDA-58260 Loan Commitment 7,000,000.00
Jun 14, 2011 IDA-H7060 Loan Commitment 5,830,000.00
Jun 12, 2012 IDA-H7780 Loan Commitment 3,000,000.00
Oct 23, 2023 IDA-58260 Loan Repay 107,964.92
Oct 23, 2023 IDA-58260 Int Charges 36.48
Oct 23, 2023 IDA-58260 Int Charges 36.48
Apr 9, 2024 IDA-58260 Int Charges 22,834.93
Apr 9, 2024 IDA-58260 Int Charges 22,834.93
Apr 9, 2024 IDA-58260 Int Charges 38,058.22
Apr 9, 2024 IDA-58260 Int Charges 83.40
Apr 9, 2024 IDA-58260 Loan Repay 105,989.05
Apr 1, 2024 IDA-58260 Loan Repay 3,509.19
Apr 9, 2024 IDA-58260 Int Charges 50.04
Apr 9, 2024 IDA-58260 Int Charges 50.04
Apr 18, 2023 IDA-58260 Int Charges 64.98
Apr 18, 2023 IDA-58260 Int Charges 64.98
Apr 18, 2023 IDA-58260 Int Charges 108.31
Apr 18, 2023 IDA-58260 Int Charges 24,045.08
Apr 18, 2023 IDA-58260 Int Charges 24,045.08
Apr 18, 2023 IDA-58260 Int Charges 40,075.15
Apr 18, 2023 IDA-58260 Loan Repay 105,855.80
Oct 23, 2023 IDA-58260 Int Charges 60.78
Oct 23, 2023 IDA-58260 Int Charges 22,986.21
Oct 23, 2023 IDA-58260 Int Charges 22,986.21
Oct 23, 2023 IDA-58260 Int Charges 38,310.32
Oct 1, 2023 IDA-58260 Loan Repay 321.87
Apr 1, 2022 IDA-58260 Loan Repay 2,132.38
Oct 31, 2022 IDA-58260 Loan Repay 102,314.30
Oct 31, 2022 IDA-58260 Int Charges 21.65
Oct 31, 2022 IDA-58260 Int Charges 21.65
Oct 31, 2022 IDA-58260 Int Charges 36.07
Oct 31, 2022 IDA-58260 Int Charges 23,267.61
Oct 31, 2022 IDA-58260 Int Charges 23,267.61
Oct 31, 2022 IDA-58260 Int Charges 38,779.43
Oct 1, 2022 IDA-58260 Loan Repay 3,547.67
Apr 1, 2023 IDA-58260 Loan Repay 5,436.37
Oct 5, 2021 IDA-58260 Loan Repay 115,905.94
Oct 5, 2021 IDA-58260 Int Charges 26,487.75
Oct 5, 2021 IDA-58260 Int Charges 26,487.75
Oct 5, 2021 IDA-58260 Int Charges 44,146.22
Apr 11, 2022 IDA-58260 Loan Repay 110,982.32
Apr 11, 2022 IDA-58260 Int Charges 9.38
Apr 11, 2022 IDA-58260 Int Charges 9.38
Apr 11, 2022 IDA-58260 Int Charges 15.63
Apr 11, 2022 IDA-58260 Int Charges 25,280.46
Apr 1, 2014 IDA-H7060 Loan Disb 76,805.61
Nov 10, 2014 IDA-H7060 Loan Disb 150,132.98
Nov 10, 2014 IDA-H7780 Loan Disb 82,463.27
Dec 11, 2014 IDA-H7780 Loan Disb 135,014.64
Dec 8, 2014 IDA-H7780 Loan Disb 71,295.03
Dec 1, 2014 IDA-H7060 Loan Disb 110,260.83
Jul 8, 2013 IDA-H7780 Loan Disb 300,000.00
Jan 5, 2015 IDA-H7060 Loan Disb 302,177.70
Oct 1, 2019 IDA-58260 Int Charges 22,073.07
Oct 1, 2019 IDA-58260 Int Charges 22,073.07
Oct 1, 2019 IDA-58260 Int Charges 36,647.91
Nov 21, 2019 IDA-58260 Loan Disb 71,162.84
Dec 6, 2018 IDA-58260 Loan Disb 328,750.84
Mar 28, 2019 IDA-58260 Loan Disb 342,237.47
Mar 28, 2019 IDA-58260 Loan Disb 180,309.23
Apr 11, 2019 IDA-58260 Int Charges 1,213.46
Apr 11, 2019 IDA-58260 Int Charges 18,588.77
Apr 11, 2019 IDA-58260 Int Charges 18,588.77
Apr 11, 2019 IDA-58260 Int Charges 30,981.27
Sep 12, 2019 IDA-58260 Loan Disb 215,410.66
Aug 21, 2019 IDA-58260 Loan Disb 241,818.55
Sep 26, 2019 IDA-58260 Loan Disb 306,936.97
Aug 10, 2018 IDA-58260 Loan Disb 494,448.53
Jul 20, 2018 IDA-58260 Loan Disb 190,044.20
Jan 31, 2019 IDA-58260 Loan Disb 296,878.78
Oct 1, 2018 IDA-58260 Int Charges 1,052.43
Oct 1, 2018 IDA-58260 Int Charges 13,494.97
Oct 1, 2018 IDA-58260 Int Charges 13,494.97
Oct 1, 2018 IDA-58260 Int Charges 21,272.97
Jan 3, 2019 IDA-58260 Loan Disb 216,266.69
Jan 8, 2019 IDA-58260 Loan Disb 159,152.66
Feb 21, 2018 IDA-58260 Loan Disb 212,416.30
Feb 21, 2018 IDA-58260 Loan Disb 142,258.55
Apr 17, 2018 IDA-58260 Int Charges 6,423.52
Apr 17, 2018 IDA-58260 Int Charges 6,423.52
Apr 17, 2018 IDA-58260 Int Charges 9,606.94
Apr 17, 2018 IDA-58260 Int Charges 22.55
Apr 9, 2018 IDA-58260 Loan Disb 306,741.20
May 22, 2018 IDA-58260 Loan Disb 325,166.10
Jun 1, 2015 IDA-H7780 Loan Disb 36,509.49
Jul 20, 2015 IDA-H7780 Loan Disb 146,964.75
Jul 21, 2015 IDA-H7060 Loan Disb 98,725.48
Oct 26, 2015 IDA-H7060 Loan Disb 110,419.82
Aug 12, 2015 IDA-H7780 Loan Disb 116,769.29
Sep 8, 2015 IDA-H7780 Loan Disb 129,212.86
Nov 2, 2015 IDA-H7780 Loan Disb 38,568.53
May 12, 2014 IDA-H7780 Loan Disb 42,105.16
Jun 18, 2014 IDA-H7780 Loan Disb 55,632.51
Jun 11, 2014 IDA-H7060 Loan Disb 245,412.61
Jul 29, 2014 IDA-H7060 Loan Disb 243,173.73
Jan 5, 2015 IDA-H7780 Loan Disb 209,131.52
Feb 3, 2015 IDA-H7060 Loan Disb 67,558.95
Mar 9, 2015 IDA-H7780 Loan Disb 77,986.93
Mar 9, 2015 IDA-H7060 Loan Disb 38,769.67
Aug 20, 2014 IDA-H7060 Loan Disb 187,745.40
Aug 20, 2014 IDA-H7780 Loan Disb 75,081.70
Jun 29, 2015 IDA-H7060 Loan Disb 377,567.90
Oct 1, 2013 IDA-H7060 Loan Disb 115,987.21
Oct 1, 2013 IDA-H7060 Loan Disb 110,869.99
Dec 16, 2013 IDA-H7780 Loan Disb 163,725.48
Dec 16, 2013 IDA-H7060 Loan Disb 46,321.82
Feb 10, 2014 IDA-H7780 Loan Disb 8,244.68
Feb 13, 2014 IDA-H7060 Loan Disb 25,657.44
Dec 23, 2013 IDA-H7060 Loan Disb 68,007.39
Dec 4, 2013 IDA-H7060 Loan Disb 69,107.82
Feb 20, 2014 IDA-H7060 Loan Disb 96,954.13
Apr 2, 2014 IDA-H7060 Loan Disb 65,811.90
Apr 1, 2014 IDA-H7060 Loan Disb 99,883.22
Apr 11, 2022 IDA-58260 Int Charges 25,280.46
Apr 11, 2022 IDA-58260 Int Charges 42,134.10
Apr 12, 2021 IDA-58260 Int Charges 77.56
Apr 12, 2021 IDA-58260 Int Charges 26,728.50
Apr 12, 2021 IDA-58260 Int Charges 26,728.50
Apr 12, 2021 IDA-58260 Int Charges 44,547.47
Oct 1, 2021 IDA-58260 Loan Repay 639.70
Oct 1, 2020 IDA-58260 Int Charges 526.91
Oct 1, 2020 IDA-58260 Int Charges 526.91
Dec 2, 2019 IDA-58260 Loan Disb 117,813.87
Apr 30, 2020 IDA-58260 Int Charges 519.08
Apr 30, 2020 IDA-58260 Int Charges 25,397.36
Apr 30, 2020 IDA-58260 Int Charges 25,397.36
Apr 30, 2020 IDA-58260 Int Charges 42,328.90
Oct 19, 2020 IDA-58260 Int Charges 25,996.05
Oct 19, 2020 IDA-58260 Int Charges 25,996.05
Oct 19, 2020 IDA-58260 Int Charges 44,130.50
Oct 1, 2019 IDA-58260 Int Charges 226.14
Oct 1, 2019 IDA-58260 Int Charges 226.14

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2019-12-26
Financial Management Satisfactory 2019-12-26
Monitoring and Evaluation Satisfactory 2019-12-26
Counterpart Funding Satisfactory 2019-12-26
Overall Implementation Progress (IP) Satisfactory 2019-12-26
Procurement Satisfactory 2019-12-26
Project Management Satisfactory 2019-12-26

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-24-2020
OutcomesHighly Satisfactory
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-14-2020PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Satisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Indicator One: Increase in the number of rural households with more secure access to drinking water within a reasonable travel time(two hours roundtrip) in the project areasValue2160.009942.007470.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • Indicator Three: Communities in the project areas are organized in community-based structures (CPLs, CGEPs and women/fishermen associations) that actively prepare and implement SAAHPsValue4.00244.00144.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • Indicator Two: Increase in the number of heads of livestock with more secure access to water within a reasonable distance (20 km radius) in the project areasValue11075.00140459.0083400.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increase in the number of constructed/rehabilitated water structures supported by the project (Number, Custom)Value0.00116.00114.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • Increase in the percentage of women in the managing committees (CPL and CGEP) (Percentage, Custom)Value0.0033.0030.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • Number of SAAHPs prepared and being implemented (Number, Custom)Value0.0018.0018.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • Increase in the total capacity of constructed/rehabilitated water structures supported by the project (Number, Custom)Value0.001745000.000.00
    DateNovember 30, 2013June 20, 2018
    Comment
  • Area of grazing areas set aside and/or rehabilitated by soil and water conservation works (Hectare(Ha), Custom)Value0.008400.008400.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • Number of persons trained in: (i) water resource management, (ii) agro-pastoral resource management, (iii) participatory planning and development, and (iv) income-generating activities (Number, CustomValue0.002321.001860.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • Area provided with new/improved irrigation or drainage services (Hectare(Ha), Corporate)Value59.25171.00145.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • Grievences registred related to delivery of project benefits that are actually addressed. (Percentage, Custom)Value0.0080.000.00
    DateDecember 31, 2012December 31, 2019
    Comment
  • Number of income-generating activities supported by the project (Number, Custom) (Number, Custom)Value0.00110.0097.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • Number of functional income-generating activities (1 year after their creation) (Number, Custom Breakdown) (Number, Custom)Value0.00110.00100.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • Number of women income-generating activities created/reinforced (Number, Custom Breakdown) (Number, Custom)Value0.0056.0053.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • Number of functional sub-projects 1 year after their completion (Number, Custom)Value0.00235.00163.00
    DateDecember 31, 2012December 31, 2019May 31, 2017
    Comment
  • New fisheries marketing and storage infrastructure constructed/rehabilitated under the project (Number, Custom)Value0.0011.000.00
    DateDecember 31, 2012December 31, 2019
    Comment