Fostering Innovation through Research, Science and Technology (FIRST)

Abstract*

The development objective of the Fostering Innovation through Research, Science and Technology (FIRST) Project for Vietnam is to support science, technology and innovation (STI) in Vietnam by designing and piloting of STI policies, enhancing the effectiveness of project-aided research and development (R and D) institutions, and encouraging the development of innovative technology enterprises. The project has three components. The first component is...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to support science, technology and innovation (STI) in Vietnam by designing and piloting of STI policies, enhancing the effectiveness of project-aided research and development (R&D) institutions, and encouraging the development of innovative technology enterprises.

Key Details

Project Details

  • P117394

  • Closed

  • Dilip Parajuli , Dung Dao

  • Socialist Republic of Vietnam

  • Viet Nam

  • February 8, 2013

  • (as of board presentation)

    May 31, 2013

  • October 22, 2013

  • US$ 110.00 million

  • Ministry of Science and Technology

  • East Asia and Pacific

  • 2013

  • US$ 100.00 million

  • B

  • Not Applicable

  • December 31, 2019

  • Yes

  • BANK APPROVED

  • August 15, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 100.00
Borrower/Recipient 10.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 110.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Nov 1, 2015 IDA-52570 Int Charges 12,476.26
Nov 1, 2015 IDA-52570 Int Charges 12,476.26
Nov 1, 2015 IDA-52570 Int Charges 20,793.78
Nov 1, 2015 IDA-52570 Int Charges 851.66
May 1, 2016 IDA-52570 Int Charges 268.46
May 1, 2016 IDA-52570 Int Charges 268.46
May 1, 2016 IDA-52570 Int Charges 20,708.40
May 1, 2016 IDA-52570 Int Charges 12,670.86
May 1, 2016 IDA-52570 Int Charges 12,670.86
Nov 1, 2016 IDA-52570 Int Charges 833.22
Nov 1, 2016 IDA-52570 Int Charges 15,074.48
Nov 1, 2016 IDA-52570 Int Charges 15,074.48
Nov 1, 2016 IDA-52570 Int Charges 25,124.18
Mar 26, 2015 IDA-52570 Loan Disb 437,884.28
May 1, 2015 IDA-52570 Int Charges 911.22
May 1, 2015 IDA-52570 Int Charges 911.22
May 1, 2015 IDA-52570 Int Charges 9,654.35
Jun 24, 2015 IDA-52570 Loan Disb 251,927.23
May 1, 2017 IDA-52570 Int Charges 527.75
Oct 11, 2017 IDA-52570 Loan Disb 2,868,000.00
Jun 13, 2016 IDA-52570 Loan Disb 887,610.20
Nov 1, 2021 IDA-52570 Int Charges 168,561.70
Nov 1, 2021 IDA-52570 Int Charges 168,561.70
Nov 1, 2021 IDA-52570 Int Charges 280,936.12
Nov 1, 2021 IDA-52570 Loan Repay 653.70
Nov 1, 2020 IDA-52570 Int Charges 291,461.00
Nov 1, 2020 IDA-52570 Loan Repay 3,858.80
Nov 1, 2020 IDA-52570 Loan Repay 819,784.44
Nov 1, 2020 IDA-52570 Int Charges 174,876.60
Nov 1, 2020 IDA-52570 Int Charges 174,876.60
Dec 26, 2019 IDA-52570 Loan Cancel 3,499,129.50
May 1, 2020 IDA-52570 Int Charges 11,132.19
May 1, 2020 IDA-52570 Loan Repay 862,897.00
May 1, 2020 IDA-52570 Int Charges 167,592.95
May 1, 2020 IDA-52570 Int Charges 167,592.95
May 1, 2020 IDA-52570 Int Charges 279,321.60
May 29, 2020 IDA-52570 Loan Disb -65,982.75
May 29, 2020 IDA-52570 Loan Cancel 3,628,302.00
Nov 1, 2019 IDA-52570 Loan Repay 0.01
Nov 1, 2019 IDA-52570 Int Charges -0.01
Nov 1, 2019 IDA-52570 Int Charges -0.01
Nov 5, 2019 IDA-52570 Loan Disb 3,366,076.50
Dec 18, 2019 IDA-52570 Loan Disb 5,351,924.00
Apr 8, 2019 IDA-52570 Loan Disb 11,739,445.00
May 1, 2019 IDA-52570 Loan Repay 14,499.93
May 1, 2019 IDA-52570 Loan Repay 1,143,586.00
May 1, 2019 IDA-52570 Int Charges 96,487.55
May 1, 2019 IDA-52570 Int Charges 96,487.55
May 1, 2019 IDA-52570 Int Charges 152,879.06
Nov 1, 2019 IDA-52570 Int Charges 7,890.90
May 31, 2013 IDA-52570 Loan Commitment 100,000,000.00
Nov 1, 2023 IDA-52570 Int Charges 133,493.95
Nov 1, 2023 IDA-52570 Int Charges 133,493.95
Nov 1, 2023 IDA-52570 Int Charges 222,489.95
Nov 1, 2023 IDA-52570 Int Charges 19,444.43
Nov 1, 2023 IDA-52570 Loan Repay 1,527,629.40
May 1, 2024 IDA-52570 Int Charges 213,861.34
May 1, 2024 IDA-52570 Loan Repay 1,503,810.80
May 1, 2024 IDA-52570 Int Charges 128,316.79
May 1, 2024 IDA-52570 Int Charges 128,316.79
May 1, 2024 IDA-52570 Loan Repay 30,411.71
May 1, 2023 IDA-52570 Int Charges 218,856.81
May 1, 2023 IDA-52570 Loan Repay 23,687.65
May 1, 2023 IDA-52570 Loan Repay 1,548,950.20
May 1, 2023 IDA-52570 Int Charges 0.01
May 1, 2023 IDA-52570 Int Charges 143,324.45
May 1, 2023 IDA-52570 Int Charges 143,324.45
Nov 1, 2022 IDA-52570 Loan Repay 1,425,992.90
Nov 1, 2022 IDA-52570 Int Charges 142,361.34
Nov 1, 2022 IDA-52570 Int Charges 142,361.34
Nov 1, 2022 IDA-52570 Int Charges 237,268.88
Nov 1, 2022 IDA-52570 Loan Repay 74,341.98
May 1, 2022 IDA-52570 Loan Repay 18,450.40
May 1, 2022 IDA-52570 Loan Repay 1,550,254.90
May 1, 2022 IDA-52570 Int Charges 154,731.40
May 1, 2022 IDA-52570 Int Charges 154,731.40
May 1, 2022 IDA-52570 Int Charges 257,885.66
May 1, 2021 IDA-52570 Loan Repay 826,976.20
May 1, 2021 IDA-52570 Int Charges 174,710.94
May 1, 2021 IDA-52570 Int Charges 174,710.94
May 1, 2021 IDA-52570 Loan Repay 10,874.44
May 1, 2021 IDA-52570 Int Charges 291,184.84
Nov 1, 2021 IDA-52570 Loan Repay 1,645,675.90
May 1, 2015 IDA-52570 Int Charges 9,654.35
May 1, 2015 IDA-52570 Int Charges 16,751.28
Mar 31, 2014 IDA-52570 Loan Disb 3,000,000.00
Nov 1, 2014 IDA-52570 Int Charges 1,853.15
Nov 1, 2014 IDA-52570 Int Charges 1,853.15
Nov 1, 2014 IDA-52570 Int Charges 3,088.56
Nov 1, 2014 IDA-52570 Int Charges 10,760.17
Nov 1, 2014 IDA-52570 Int Charges 10,760.17
Nov 1, 2014 IDA-52570 Int Charges 17,933.58
Nov 1, 2019 IDA-52570 Loan Repay 930,513.80
Aug 19, 2019 IDA-52570 Loan Cancel 12,898,210.00
Nov 1, 2019 IDA-52570 Int Charges 145,202.42
Nov 1, 2019 IDA-52570 Int Charges 145,202.42
Nov 1, 2019 IDA-52570 Int Charges 230,784.55
Nov 1, 2019 IDA-52570 Int Charges 0.01
May 1, 2018 IDA-52570 Int Charges 41,205.26
May 1, 2018 IDA-52570 Int Charges 41,205.26
May 1, 2018 IDA-52570 Int Charges 62,086.94
May 1, 2018 IDA-52570 Int Charges 2,717.92
Nov 1, 2018 IDA-52570 Int Charges 6,365.83
Nov 1, 2018 IDA-52570 Loan Repay 1,156,967.50
Nov 1, 2018 IDA-52570 Int Charges 57,985.81
Nov 1, 2018 IDA-52570 Int Charges 57,985.81
Nov 1, 2018 IDA-52570 Int Charges 96,643.05
Jan 28, 2019 IDA-52570 Loan Disb 3,057,280.00
Dec 14, 2018 IDA-52570 Loan Disb 4,114,280.20
Jan 25, 2019 IDA-52570 Loan Disb 3,574,855.50
Mar 28, 2018 IDA-52570 Loan Disb 4,016,242.20
Aug 29, 2018 IDA-52570 Loan Disb 3,403,000.00
Aug 29, 2018 IDA-52570 Loan Disb 1,661,574.00
Aug 3, 2017 IDA-52570 Loan Disb 2,909,804.00
Nov 1, 2017 IDA-52570 Int Charges 689.09
Nov 1, 2017 IDA-52570 Int Charges 22,644.20
Nov 1, 2017 IDA-52570 Int Charges 22,644.20
Nov 1, 2017 IDA-52570 Int Charges 35,078.36
Mar 31, 2017 IDA-52570 Loan Cancel 22,000,000.00
May 8, 2017 IDA-52570 Int Charges 15,222.38
May 8, 2017 IDA-52570 Int Charges 15,222.38
May 8, 2017 IDA-52570 Int Charges 25,578.84
May 1, 2017 IDA-52570 Int Charges 527.75

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2019-12-30
Project Management Satisfactory 2019-12-30
Financial Management Moderately Satisfactory 2019-12-30
Progress towards achievement of PDO Satisfactory 2019-12-30
Monitoring and Evaluation Satisfactory 2019-12-30
Counterpart Funding Satisfactory 2019-12-30
Overall Implementation Progress (IP) Satisfactory 2019-12-30

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-29-2020
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 12-04-2020PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Consortia and start-up projects (grants) completed successfully with new products and processes developedValue0.0015.000.00
    DateOctober 1, 2013December 31, 2019
    Comment
  • Number of international scientific publications made by beneficiary organizations (disaggregated by gender)Value0.00105.0010.00
    DateOctober 1, 2013December 31, 2019January 22, 2019
    Comment
  • Number of innovative activity by beneficiary organizations (disaggregated by gender)Value0.00108.0010.00
    DateOctober 1, 2013December 31, 2019January 22, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of international researchers participated in project (disaggregated by gender)Value0.00102.000.00
    DateOctober 1, 2013December 31, 2019
    Comment
  • Number of GRIs with satisfactory implementation of GRI grantValue0.0016.003.00
    DateOctober 1, 2013December 31, 2019
    Comment
  • Research report producedValueNoYes
    DateOctober 1, 2013December 31, 2019
    Comment
  • Number of know-how, new knowledge and new methodologies transferredValue0.0015.000.00
    DateOctober 1, 2013December 31, 2019
    Comment
  • Number of competitive grants awarded and successfully completed to innovative technology enterprisesValue0.003.003.00
    DateOctober 1, 2013December 31, 2019December 31, 2019
    Comment
  • Conduct STI SurveyValueNoYesYes
    DateOctober 1, 2013December 31, 2019
    Comment
  • Number of matching grants successfully implemented by research-innovation consortiaValue0.0011.0015.00
    DateOctober 1, 2013December 31, 2019December 31, 2019
    Comment
  • S&T Management Information systemValueNoYes
    DateOctober 1, 2013June 30, 2020
    Comment