Skip to Main Navigation

GZ-Palestinian P. NGO IV

Abstract*

The objective of the Fourth Palestinian Non-Governmental Organization (NGO) Project for West Bank and Gaza is to provide social services to those who are poor, vulnerable or marginalized through NGOs and to strengthen the institutional capacity of these organizations. There are three components to the project, the first component being NGO grants for social and productive services. This component includes four sub-grants to NGOs for social service...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To provide social services to those who are poor, vulnerable or marginalized through NGOs and to strengthen the institutional capacity of these organizations

Key Details

Project Details

  • P117444

  • Closed

  • Christianna Brotsis

  • NGO Development Center

  • West Bank and Gaza

  • January 13, 2010

  • (as of board presentation)

    July 8, 2010

  • September 3, 2010

  • US$ 8.00 million

  • B

  • October 31, 2022

  • December 31, 2016

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Special Financing 2.00
FRANCE: French Agency for Development 6.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 8.00
Total Project Cost** 8.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2016-12-28
Procurement Satisfactory 2016-12-28
Monitoring and Evaluation Highly Satisfactory 2016-12-28
Financial Management Satisfactory 2016-12-28
Overall Implementation Progress (IP) Satisfactory 2016-12-28
Project Management Highly Satisfactory 2016-12-28

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-28-2017
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-11-2018PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeModestN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately SatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualityModestN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Vulnerable/marginalized people in project area that are project beneficiaries (%)Value0.0088.6080.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • People with access to social and/or economic services (#) [disaggregated by type of service and gender].Value0.0071750.0047260.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • Satisfaction of users with services (%)Value0.0080.0070.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • NGOs whose self-assessment has beeen validated (#)Value0.0077.0060.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • Direct project beneficiariesValue0.0071750.0047260.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • Female beneficiariesValue0.0056.0054.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Health facilities constructed, renovated, and/or equipped (number)Value0.001.001.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • Participants in consultation activities during project implementation (number)Value0.00441.0060.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • NGOs making their annual audited financial reports public (%)Value0.0094.0090.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • NGOs receiving self-assessment support through their networks as part of the Code of Conduct ComplianceValue0.00275.00200.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • NGOs having approved financial management manual, systems and documented procedures (%)Value0.0064.0090.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • Infrastructure rehabiliated or built (#) [disaggregated by type]Value0484230
    DateAugust 31, 2010December 20, 2016August 1, 2016
    Comment
  • NGOs with regulatory framework for their Board of Directors and General Assembly developed and documented (%)Value0.0057.0090.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • People with access to income generating opportunities/Jobs (#) [disaggregated by income generating opportunities, jobs, short term jobs and self-employmentValue022701500
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • NGOs receiving support from NDC rate its services satisfactory (%)Value0.0093.0090.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • NDC makes its annual financial statements public (yes/no)ValueNoYesYes
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment
  • Participants in consultation activities during project implementation - femaleValue0.00283.001200.00
    DateAugust 31, 2010December 20, 2016September 30, 2016
    Comment