Uganda Support to Municipal Infrastructure Development Program

Abstract*

The objective of the Uganda Support to Municipal Infrastructure Development Program Project (USMID) is to enhance the institutional performance of program Local Governments (LGs) to improve urban service delivery. The core of the program will comprise two grant flows to Municipalities: (i) the Municipal Development Grant (MDG) which will provide substantial additional funds to the targeted Municipalities for investment in urban infrastructure, designed...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To enhance institutional capacity of selected municipalities to address urban service delivery gaps

Key Details

Project Details

  • P117876

  • Closed

  • John Stephen Ajalu , Phan Huyen

  • Ministry of Finance, Planning and Economic Development

  • Uganda

  • September 14, 2010

  • (as of board presentation)

    March 28, 2013

  • September 30, 2011

  • US$ 150.00 million

  • Ministry of Lands, Housing and Urban Development

  • Eastern and Southern Africa

  • 2013

  • US$ 150.00 million

  • N/A

  • June 11, 2024

  • June 30, 2024

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 150.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 150.00
IBRD + IDA Commitment 150.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 150.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 21, 2022 IDA-52230 Int Charges 480,347.38
Jan 15, 2019 IDA-52230 Int Charges 6,576.07
Jan 15, 2019 IDA-52230 Int Charges 6,576.07
Jan 25, 2019 IDA-52230 Int Charges 498,017.25
Jan 25, 2019 IDA-52230 Int Charges 498,017.25
Oct 19, 2016 IDA-52230 Loan Disb 26,405,636.00
Oct 19, 2016 IDA-52230 Loan Disb 2,974,378.20
Jan 15, 2017 IDA-52230 Int Charges 3,420.22
Jan 15, 2017 IDA-52230 Int Charges 3,420.22
Jan 15, 2017 IDA-52230 Int Charges 339,821.40
Jan 15, 2017 IDA-52230 Int Charges 339,821.40
Jul 15, 2017 IDA-52230 Int Charges 3,124.43
Jul 15, 2017 IDA-52230 Int Charges 3,124.43
Jul 15, 2017 IDA-52230 Int Charges 402,143.94
Jul 15, 2017 IDA-52230 Int Charges 402,143.94
Nov 3, 2017 IDA-52230 Loan Disb 23,831,880.00
Sep 28, 2015 IDA-52230 Loan Disb 17,891,112.00
Feb 9, 2024 IDA-52230 Int Charges 11,092.75
Feb 9, 2024 IDA-52230 Int Charges 11,092.75
Feb 9, 2024 IDA-52230 Loan Repay 1,290,686.40
Feb 9, 2024 IDA-52230 Int Charges 134.45
Feb 9, 2024 IDA-52230 Int Charges 134.45
Feb 9, 2024 IDA-52230 Int Charges 479,108.25
Feb 9, 2024 IDA-52230 Int Charges 479,108.25
Feb 15, 2024 IDA-62330 Int Charges 1,091,723.00
Feb 15, 2024 IDA-62330 Int Charges 1,091,723.00
Feb 15, 2024 IDA-62330 Int Charges 9,135.16
Feb 15, 2024 IDA-62330 Int Charges 9,135.16
Jul 15, 2024 IDA-52230 Loan Repay 1,626.27
Jul 16, 2024 IDA-52230 Int Charges 645.86
Aug 7, 2024 IDA-62330 Loan Disb 15,494,419.00
Mar 28, 2013 IDA-52230 Loan Commitment 150,000,000.00
Aug 6, 2024 IDA-D3100 Loan Disb 3,607,675.50
Jul 16, 2024 IDA-52230 Int Charges 645.86
Jul 16, 2024 IDA-52230 Int Charges 470,808.97
Jul 16, 2024 IDA-52230 Int Charges 470,808.97
Jul 16, 2024 IDA-52230 Loan Repay 1,290,093.90
May 15, 2018 IDA-D3100 Loan Commitment 25,000,000.00
May 15, 2018 IDA-62330 Loan Commitment 335,000,000.00
Jan 15, 2023 IDA-52230 Int Charges 474,930.38
Jan 15, 2023 IDA-52230 Int Charges 474,930.38
Aug 15, 2023 IDA-62330 Int Charges 4,059.99
Aug 15, 2023 IDA-62330 Int Charges 4,059.99
Aug 15, 2023 IDA-62330 Int Charges 827,867.20
Aug 15, 2023 IDA-62330 Int Charges 827,867.20
Aug 8, 2023 IDA-62330 Loan Disb 73,050,576.00
Jul 20, 2023 IDA-52230 Int Charges 11,870.46
Jul 20, 2023 IDA-52230 Int Charges 11,870.46
Jul 20, 2023 IDA-52230 Loan Repay 1,315,922.80
Jul 20, 2023 IDA-52230 Int Charges 482,101.12
Jul 20, 2023 IDA-52230 Int Charges 482,101.12
Aug 15, 2024 IDA-62330 Loan Repay 4,831,087.00
Aug 15, 2024 IDA-62330 Int Charges 1,011,585.94
Aug 15, 2024 IDA-62330 Int Charges 1,011,585.94
Aug 15, 2024 IDA-62330 Loan Repay 14,954.73
Aug 15, 2022 IDA-62330 Int Charges 819,027.25
Aug 15, 2022 IDA-62330 Int Charges 819,027.25
Aug 15, 2022 IDA-62330 Int Charges 2,427.39
Aug 15, 2022 IDA-62330 Int Charges 2,427.39
Jan 15, 2022 IDA-52230 Int Charges 5,239.71
Jan 15, 2022 IDA-52230 Int Charges 5,239.71
Jan 15, 2022 IDA-52230 Int Charges 507,848.30
Jan 15, 2022 IDA-52230 Int Charges 507,848.30
Feb 15, 2023 IDA-62330 Int Charges 7,110.96
Feb 15, 2023 IDA-62330 Int Charges 7,110.96
Feb 15, 2023 IDA-62330 Int Charges 818,379.75
Feb 15, 2023 IDA-62330 Int Charges 818,379.75
Aug 8, 2023 IDA-D3100 Loan Disb 4,536,434.00
Jan 15, 2023 IDA-52230 Int Charges 5,668.97
Jan 15, 2023 IDA-52230 Int Charges 5,668.97
Jul 15, 2021 IDA-52230 Int Charges 520,264.30
Aug 15, 2021 IDA-62330 Int Charges 516,533.10
Aug 15, 2021 IDA-62330 Int Charges 516,533.10
Aug 30, 2021 IDA-D3100 Loan Disb 10,284,919.00
Aug 30, 2021 IDA-62330 Loan Disb 97,353,600.00
Aug 15, 2021 IDA-62330 Int Charges 1,098.64
Aug 15, 2021 IDA-62330 Int Charges 1,098.64
Jul 21, 2022 IDA-52230 Int Charges 1,013.30
Jul 21, 2022 IDA-52230 Int Charges 1,013.30
Jul 21, 2022 IDA-52230 Int Charges 480,347.38
Sep 28, 2015 IDA-52230 Loan Disb 5,022,436.00
Apr 19, 2016 IDA-52230 Loan Disb 10,976,099.00
Jul 15, 2016 IDA-52230 Int Charges 279,533.00
Jul 15, 2016 IDA-52230 Int Charges 279,533.00
Jul 15, 2016 IDA-52230 Int Charges 85.75
Jul 15, 2016 IDA-52230 Int Charges 85.75
Jan 15, 2015 IDA-52230 Int Charges 150.63
Jan 15, 2015 IDA-52230 Int Charges 150.63
Jan 15, 2015 IDA-52230 Int Charges 92,076.33
Jan 15, 2015 IDA-52230 Int Charges 92,076.33
Jul 15, 2015 IDA-52230 Int Charges 2,361.98
Jul 15, 2015 IDA-52230 Int Charges 2,361.98
Jul 16, 2015 IDA-52230 Int Charges 126,823.68
Jul 16, 2015 IDA-52230 Int Charges 126,823.68
Apr 21, 2015 IDA-52230 Loan Disb 18,055,728.00
Apr 22, 2015 IDA-52230 Loan Disb 4,333,659.50
Jan 15, 2016 IDA-52230 Int Charges 2,274.22
Jan 15, 2016 IDA-52230 Int Charges 2,274.22
Jan 15, 2016 IDA-52230 Int Charges 221,578.30
Jan 15, 2016 IDA-52230 Int Charges 221,578.30
Jan 27, 2014 IDA-52230 Loan Disb 2,001,922.00
Jan 27, 2014 IDA-52230 Loan Disb 5,235,796.00
Jan 28, 2014 IDA-52230 Loan Disb 19,227,750.00
Jul 15, 2014 IDA-52230 Int Charges 92,447.83
Jul 15, 2014 IDA-52230 Int Charges 92,447.83
Feb 15, 2022 IDA-62330 Int Charges 6,858.75
Feb 15, 2022 IDA-62330 Int Charges 6,858.75
Feb 15, 2022 IDA-62330 Int Charges 829,538.06
Feb 15, 2022 IDA-62330 Int Charges 829,538.06
Jul 21, 2020 IDA-52230 Int Charges 2,559.31
Jul 21, 2020 IDA-52230 Int Charges 2,559.31
Jul 21, 2020 IDA-52230 Int Charges 496,399.25
Jul 21, 2020 IDA-52230 Int Charges 496,399.25
Jul 15, 2020 IDA-62330 Loan Disb 78,735,344.00
Jul 15, 2020 IDA-D3100 Loan Disb 3,903,600.20
Aug 15, 2020 IDA-62330 Int Charges 205,529.84
Aug 15, 2020 IDA-62330 Int Charges 205,529.84
Aug 15, 2020 IDA-62330 Int Charges 3,177.69
Aug 15, 2020 IDA-62330 Int Charges 3,177.69
Jan 21, 2021 IDA-52230 Int Charges 11,857.24
Jan 21, 2021 IDA-52230 Int Charges 11,857.24
Jan 21, 2021 IDA-52230 Int Charges 518,339.25
Jan 21, 2021 IDA-52230 Int Charges 518,339.25
Feb 15, 2021 IDA-62330 Int Charges 55,682.67
Feb 15, 2021 IDA-62330 Int Charges 55,682.67
Feb 15, 2021 IDA-62330 Int Charges 522,837.47
Feb 15, 2021 IDA-62330 Int Charges 522,837.47
Jul 15, 2021 IDA-52230 Int Charges 520,264.30
Jul 15, 2021 IDA-52230 Int Charges 8,374.96
Jul 15, 2021 IDA-52230 Int Charges 8,374.96
Jun 27, 2019 IDA-62330 Loan Disb 56,089,900.00
Jun 28, 2019 IDA-D3100 Loan Disb 1,602,603.50
Jul 15, 2019 IDA-52230 Int Charges 3,978.37
Jul 15, 2019 IDA-52230 Int Charges 3,978.37
Jul 15, 2019 IDA-52230 Int Charges 504,827.47
Jul 15, 2019 IDA-52230 Int Charges 504,827.47
Feb 15, 2020 IDA-62330 Int Charges 55,177.61
Feb 15, 2020 IDA-62330 Int Charges 55,177.61
Feb 15, 2020 IDA-62330 Int Charges 206,916.02
Feb 15, 2020 IDA-62330 Int Charges 206,916.02
Jan 15, 2020 IDA-52230 Int Charges 884.96
Jan 15, 2020 IDA-52230 Int Charges 884.96
Jan 15, 2020 IDA-52230 Int Charges 501,974.03
Jan 15, 2020 IDA-52230 Int Charges 501,974.03
Jun 5, 2018 IDA-52230 Loan Disb 2,184,466.80
Jan 15, 2018 IDA-52230 Int Charges 6,129.00
Jan 15, 2018 IDA-52230 Int Charges 6,129.00
Jan 15, 2018 IDA-52230 Int Charges 453,767.44
Jan 15, 2018 IDA-52230 Int Charges 453,767.44
Jul 23, 2018 IDA-52230 Int Charges 6,386.86
Jul 23, 2018 IDA-52230 Int Charges 6,386.86
Jul 23, 2018 IDA-52230 Int Charges 506,861.72
Jul 23, 2018 IDA-52230 Int Charges 506,861.72

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-06-15
Monitoring and Evaluation Moderately Satisfactory 2024-06-15
Overall Implementation Progress (IP) Moderately Satisfactory 2024-06-15

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • 2. Local infrastructure targets as set out in the annual work plans delivered by municipal LGs utilizing the Program funds.Value60.0093.2085.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • 3.1 Indicator Three: Number of project beneficiaries of which x% femaleValue1,400,000.003,052,8003,500,000.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • 1. Average annual performance score of participating LGs in the seven thematic areas as assessed by the independent annual performance assessmentValue60.0070.7290.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • 3.2 Direct Program beneficiaries (number), of which female (percentage)Value685700.001573576.001785000.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • Direct beneficiaries of the infrastructure improved in the refugee hosting districtsValue0.003108600.002500000.00
    DateJune 29, 2018April 15, 2024June 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 7. Municipal LGs with qualified core staffValue14.0022.0022.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • 4. Municipal roads built or rehabilitated with related infrastructure using urban LDGValue78.00171.78190.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • 11. Technical support by MoLHUD and implementation of the Program action plan to ensure achievement of Program results.Value0.0091.0090.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • Land titles prepared through systematic land adjudication and certificationValue0.001137.005000.00
    DateJune 29, 2018April 15, 2024June 30, 2024
    Comment
  • 8. Municipal LGs with at least 10% annual increase in own source revenue (OSR)Value6.0013.0022.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • 5. Garbage collected and disposedValue520000.00522136.00696938.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • 12. Valuation Services strengthened by CGV officeValuePIP developedPIP implementation 78%PIP implemented
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • Physical Development Plans (PDPs) prepared for the refugee hosting districtsValue0.002.0011.00
    DateJune 29, 2018April 15, 2024June 30, 2024
    Comment
  • 9. Municipal LGs with clean audit reports for previous yearValue8.0022.0022.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • 6. Municipal local economic infrastructure (bus parks, markets, parking lots etc) built or rehabilitated using the urban LDG.Value3.008.009.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • District and community access roads made motorable throughout the yearValue0.0075.00285.00
    DateJune 29, 2018April 15, 2024June 30, 2024
    Comment
  • 10. Municipal LGs with actual expenditures on O&M more than 75% of the O&M budgeted amountValue6.0017.0022.00
    DateJune 29, 2018April 15, 2024December 29, 2023
    Comment
  • Roads upgraded from gravel to sealed surfacing/asphaltValue0.000.0012.00
    DateJune 29, 2018April 15, 2024June 30, 2024
    Comment
  • Infrastructure built to strengthen interaction and peaceful co-existence between host communities and refugees (playgrounds, resource centers, markets, leisure parks)Value0.009.0047.00
    DateJune 29, 2018April 15, 2024June 30, 2024
    Comment