Financier | Commitments |
---|---|
Borrower/Recipient | 42.00 |
International Bank for Reconstruction and Development | 42.00 |
P118064
Closed
Jean-Martin Brault
Obras Sanitarias del Estado (OSE)
April 22, 2011
(as of board presentation)
July 5, 2012
March 7, 2013
US$ 84.00 million
Obras Sanitarias del Estado (OSE)
2013
US$ 42.00 million
B
November 14, 2022
December 31, 2019
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Borrower/Recipient | 42.00 |
International Bank for Reconstruction and Development | 42.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 42.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 42.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 84.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 15, 2014 | IBRD-81830 | Int Charges | 1,354.34 |
May 21, 2014 | IBRD-81830 | Loan Disb | 1,500,000.00 |
Jun 17, 2014 | IBRD-81830 | Loan Disb | 424,069.75 |
Oct 21, 2014 | IBRD-81830 | Loan Disb | 1,859,547.20 |
Aug 15, 2013 | IBRD-81830 | Int Charges | 385.05 |
Jul 5, 2012 | IBRD-81830 | Loan Commitment | 42,000,000.00 |
Aug 15, 2024 | IBRD-81830 | Int Charges | 5,107.72 |
Aug 15, 2024 | IBRD-81830 | Int Charges | 859,107.60 |
Aug 15, 2024 | IBRD-81830 | Loan Repay | 1,209,628.40 |
Feb 15, 2024 | IBRD-81830 | Int Charges | 895,326.56 |
Feb 15, 2024 | IBRD-81830 | Loan Repay | 1,209,628.40 |
Feb 15, 2024 | IBRD-81830 | Int Charges | 8,433.63 |
Feb 15, 2023 | IBRD-81830 | Int Charges | 50,742.04 |
Feb 15, 2023 | IBRD-81830 | Int Charges | 681,241.60 |
Feb 15, 2023 | IBRD-81830 | Loan Repay | 1,209,628.40 |
Aug 15, 2023 | IBRD-81830 | Int Charges | 31,679.52 |
Aug 15, 2023 | IBRD-81830 | Int Charges | 806,101.50 |
Aug 15, 2023 | IBRD-81830 | Loan Repay | 1,209,628.40 |
Feb 15, 2022 | IBRD-81830 | Int Charges | 131,757.88 |
Dec 12, 2018 | IBRD-81830 | Loan Disb | 4,000,000.00 |
Aug 15, 2018 | IBRD-81830 | Int Charges | 6,027.67 |
Aug 15, 2018 | IBRD-81830 | Int Charges | 396,012.72 |
Aug 15, 2018 | IBRD-81830 | Loan Repay | 884,933.75 |
Feb 15, 2019 | IBRD-81830 | Loan Repay | 1,095,651.10 |
Feb 15, 2019 | IBRD-81830 | Int Charges | 4,945.28 |
Feb 15, 2019 | IBRD-81830 | Int Charges | 529,794.30 |
Feb 15, 2018 | IBRD-81830 | Int Charges | 9,608.89 |
Feb 15, 2018 | IBRD-81830 | Int Charges | 289,125.28 |
Feb 15, 2018 | IBRD-81830 | Loan Repay | 836,843.25 |
Jul 23, 2018 | IBRD-81830 | Loan Disb | 2,954,370.20 |
Oct 10, 2017 | IBRD-81830 | Loan Disb | 3,682,601.00 |
Aug 15, 2017 | IBRD-81830 | Int Charges | 189,146.03 |
Aug 15, 2017 | IBRD-81830 | Loan Repay | 617,120.80 |
Dec 11, 2017 | IBRD-81830 | Loan Disb | 1,635,731.90 |
Aug 15, 2016 | IBRD-81830 | Int Charges | 60,517.01 |
May 25, 2017 | IBRD-81830 | Loan Disb | 4,000,000.00 |
Feb 15, 2017 | IBRD-81830 | Int Charges | 6,549.19 |
Feb 15, 2017 | IBRD-81830 | Int Charges | 134,783.19 |
Jun 30, 2017 | IBRD-81830 | Loan Disb | 4,000,000.00 |
Feb 15, 2016 | IBRD-81830 | Int Charges | 37,240.64 |
Nov 14, 2016 | IBRD-81830 | Loan Disb | 1,000,000.00 |
Jul 6, 2016 | IBRD-81830 | Loan Disb | 1,950,027.90 |
Jun 15, 2016 | IBRD-81830 | Loan Disb | 1,627,383.80 |
Jun 7, 2016 | IBRD-81830 | Loan Disb | 1,000,000.00 |
Nov 28, 2016 | IBRD-81830 | Loan Disb | 4,000,000.00 |
Dec 10, 2015 | IBRD-81830 | Loan Disb | 1,377,748.50 |
Sep 23, 2015 | IBRD-81830 | Loan Disb | 1,101,889.90 |
Aug 15, 2014 | IBRD-81830 | Int Charges | 4,637.61 |
Feb 15, 2015 | IBRD-81830 | Int Charges | 486.50 |
Feb 15, 2015 | IBRD-81830 | Int Charges | 13,848.02 |
Mar 24, 2015 | IBRD-81830 | Loan Disb | 1,752,923.80 |
Aug 15, 2015 | IBRD-81830 | Int Charges | 23,552.11 |
Nov 19, 2013 | IBRD-81830 | Loan Disb | 500,000.00 |
Feb 15, 2022 | IBRD-81830 | Loan Repay | 1,209,628.40 |
Aug 15, 2022 | IBRD-81830 | Int Charges | 201,117.48 |
Aug 15, 2022 | IBRD-81830 | Loan Repay | 1,209,628.40 |
Feb 15, 2021 | IBRD-81830 | Loan Repay | 1,209,628.40 |
Feb 15, 2021 | IBRD-81830 | Int Charges | 168,398.40 |
Aug 15, 2021 | IBRD-81830 | Int Charges | 141,220.02 |
Aug 15, 2021 | IBRD-81830 | Loan Repay | 1,209,628.40 |
Aug 15, 2020 | IBRD-81830 | Int Charges | 419,792.06 |
Aug 15, 2020 | IBRD-81830 | Loan Repay | 1,209,628.40 |
Aug 15, 2019 | IBRD-81830 | Int Charges | 588,364.25 |
Aug 15, 2019 | IBRD-81830 | Loan Repay | 1,095,651.10 |
Nov 26, 2019 | IBRD-81830 | Loan Disb | 603,518.20 |
Jul 18, 2019 | IBRD-81830 | Loan Disb | 2,925,187.80 |
Feb 15, 2020 | IBRD-81830 | Int Charges | 7,598.98 |
Feb 15, 2020 | IBRD-81830 | Int Charges | 497,238.20 |
Feb 15, 2020 | IBRD-81830 | Loan Repay | 1,209,628.40 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2019-12-30 |
Project Management | Satisfactory | 2019-12-30 |
Financial Management | Satisfactory | 2019-12-30 |
Monitoring and Evaluation | Satisfactory | 2019-12-30 |
Overall Implementation Progress (IP) | Satisfactory | 2019-12-30 |
Counterpart Funding | Satisfactory | 2019-12-30 |
Procurement | Satisfactory | 2019-12-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-29-2020 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 12-23-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Piped household water connections that are benefiting from rehabilitation works undertaken by the project | Value | 0.00 | 433900.00 | 433900.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Cumulative volume of non-revenue water recovered under the project (m3) | Value | 0.00 | 89290000.00 | 81900000.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Energy saved in the systems where the Project is being implemented | Value | 0.00 | 26250.00 | 20780.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Reach satisfactory level in the Business Management Efficiency Index (BMEI) | Value | Low | Excellent | Satisfactory |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
New water intake point at the Aguas Corrientes plant constructed and in operation (m3/h) | Value | 0.00 | 15000.00 | 15000.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Reduction of non revenue water in the Montevideo system (liters/connection/day) | Value | 799.00 | 696.00 | 736.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Water Security Plans (PSA) | Value | 0.00 | 18.00 | 0.00 |
Date | September 7, 2016 | December 31, 2019 | ||
Comment |
Durazno and Treinta y Tres water treatment plants reconstructed and in operation (m3/h) | Value | 0.00 | 1150.00 | 1150.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Reduction of non revenue water in the Rivera system (liters/connection/day) | Value | 668.00 | 420.00 | 483.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Reach "Satisfactory" level in the Environmental Index (EI) | Value | Low | Excellent | Satisfactory |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Number of electric motors installed and in operation at Aguas Corrientes | Value | 0.00 | 10.00 | 10.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Reduction of non revenue water in the Salto system (liters/connection/day) | Value | 579.00 | 418.00 | 483.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2020 | |
Comment |
Number of equipment (pumps, motors and electrical systems) replaced and in operation outside Aguas Corrientes Water | Value | 0.00 | 51.00 | 51.00 |
Date | June 13, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Reduction of non revenue water in Las Piedras system (liters/connection/day) | Value | 703.00 | 391.00 | 555.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Number of people that are benefiting from rehabilitation works undertaken by the Project | Value | 0.00 | 1860000.00 | 1860000.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Development of an Energy Management Program | Value | No | Program Ready | |
Date | July 5, 2012 | December 31, 2019 | ||
Comment |
Asset Management Plan for electromechanical equipament implemented in one pilot region | Value | No | 100% | Phase 2 Asset Program Operational |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |
Number of south-south knowledge exchange activities | Value | 0.00 | 12.00 | 10.00 |
Date | July 5, 2012 | December 31, 2019 | December 31, 2019 | |
Comment |