Financier | Commitments |
---|---|
Borrower/Recipient | 99.00 |
International Bank for Reconstruction and Development | 90.00 |
P118540
Closed
Diego Arias Carballo
State Government of Santa Catarina
November 25, 2009
(as of board presentation)
September 2, 2010
December 24, 2010
US$ 189.00 million
Secretaria Executiva Estadual - SEE
2011
US$ 90.00 million
B
Not Applicable
June 30, 2017
BANK APPROVED
April 22, 2024
Financier | Commitments |
---|---|
Borrower/Recipient | 99.00 |
International Bank for Reconstruction and Development | 90.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 90.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 90.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 189.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 15, 2024 | IBRD-79520 | Int Charges | 36,950.64 |
Feb 24, 2014 | IBRD-79520 | Loan Disb | 571,677.60 |
Mar 15, 2024 | IBRD-79520 | Loan Repay | 2,997,000.00 |
Sep 2, 2010 | IBRD-79520 | Loan Commitment | 90,000,000.00 |
Sep 15, 2023 | IBRD-79520 | Int Charges | 28,651.05 |
Sep 15, 2023 | IBRD-79520 | Loan Repay | 2,997,000.00 |
Mar 15, 2023 | IBRD-79520 | Loan Repay | 2,997,000.00 |
Mar 15, 2023 | IBRD-79520 | Int Charges | 88,980.18 |
Mar 15, 2023 | IBRD-79520 | Int Charges | 1,892,618.40 |
Sep 15, 2023 | IBRD-79520 | Int Charges | 2,101,929.00 |
Sep 15, 2022 | IBRD-79520 | Int Charges | 732,148.80 |
Sep 15, 2022 | IBRD-79520 | Loan Repay | 2,997,000.00 |
Mar 15, 2022 | IBRD-79520 | Int Charges | 358,419.80 |
Mar 15, 2022 | IBRD-79520 | Loan Repay | 2,997,000.00 |
Sep 15, 2021 | IBRD-79520 | Int Charges | 390,721.22 |
Sep 15, 2021 | IBRD-79520 | Loan Repay | 2,997,000.00 |
Mar 15, 2021 | IBRD-79520 | Int Charges | 428,683.10 |
Mar 15, 2021 | IBRD-79520 | Loan Repay | 2,997,000.00 |
Sep 15, 2020 | IBRD-79520 | Int Charges | 653,200.00 |
Sep 15, 2020 | IBRD-79520 | Loan Repay | 2,997,000.00 |
Sep 15, 2019 | IBRD-79520 | Int Charges | 1,554,800.00 |
Mar 15, 2020 | IBRD-79520 | Int Charges | 1,246,700.00 |
Mar 15, 2019 | IBRD-79520 | Int Charges | 1,470,625.00 |
Sep 15, 2018 | IBRD-79520 | Int Charges | 1,361,600.00 |
Oct 26, 2017 | IBRD-79520 | Loan Disb | 5,989,649.50 |
Mar 15, 2018 | IBRD-79520 | Int Charges | 940,381.56 |
Sep 15, 2017 | IBRD-79520 | Int Charges | 216.95 |
Sep 15, 2017 | IBRD-79520 | Int Charges | 888,829.50 |
Mar 15, 2017 | IBRD-79520 | Int Charges | 751,594.80 |
Dec 12, 2016 | IBRD-79520 | Loan Disb | 6,745,206.50 |
May 23, 2016 | IBRD-79520 | Loan Disb | 6,745,206.50 |
Oct 25, 2016 | IBRD-79520 | Loan Disb | 444,929.30 |
Jul 13, 2016 | IBRD-79520 | Loan Disb | 617,868.40 |
Feb 27, 2017 | IBRD-79520 | Loan Disb | 262,443.78 |
Mar 15, 2016 | IBRD-79520 | Int Charges | 357,195.44 |
Mar 15, 2016 | IBRD-79520 | Int Charges | 1,998.09 |
Feb 16, 2016 | IBRD-79520 | Loan Disb | 448,882.78 |
Sep 15, 2016 | IBRD-79520 | Int Charges | 380.55 |
Sep 15, 2016 | IBRD-79520 | Int Charges | 556,934.94 |
Sep 4, 2015 | IBRD-79520 | Loan Disb | 6,252,433.50 |
Sep 15, 2015 | IBRD-79520 | Int Charges | 231,005.69 |
Dec 15, 2015 | IBRD-79520 | Loan Disb | 7,851,180.50 |
Sep 15, 2015 | IBRD-79520 | Int Charges | 5,265.21 |
Mar 5, 2015 | IBRD-79520 | Loan Disb | 537,565.06 |
Mar 15, 2015 | IBRD-79520 | Int Charges | 2,580.78 |
Mar 15, 2015 | IBRD-79520 | Int Charges | 151,577.56 |
Aug 18, 2015 | IBRD-79520 | Loan Disb | 306,023.22 |
Jun 24, 2015 | IBRD-79520 | Loan Disb | 10,329,217.00 |
Apr 16, 2015 | IBRD-79520 | Loan Disb | 389,051.50 |
Mar 15, 2014 | IBRD-79520 | Int Charges | 76,353.10 |
Aug 8, 2014 | IBRD-79520 | Loan Disb | 2,695,356.50 |
Aug 12, 2014 | IBRD-79520 | Loan Disb | 403,286.50 |
Sep 15, 2014 | IBRD-79520 | Int Charges | 4,635.19 |
Sep 15, 2014 | IBRD-79520 | Int Charges | 135,850.38 |
Feb 10, 2015 | IBRD-79520 | Loan Disb | 6,757,419.00 |
Sep 15, 2013 | IBRD-79520 | Int Charges | 159.25 |
Sep 15, 2013 | IBRD-79520 | Int Charges | 44,973.40 |
Sep 16, 2013 | IBRD-79520 | Loan Disb | 326,201.50 |
Dec 18, 2013 | IBRD-79520 | Loan Disb | 16,154,683.00 |
Feb 14, 2014 | IBRD-79520 | Loan Disb | 3,580,615.80 |
Feb 14, 2014 | IBRD-79520 | Loan Disb | 2,814,276.50 |
Mar 15, 2024 | IBRD-79520 | Int Charges | 2,237,067.20 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2017-11-21 |
Financial Management | Satisfactory | 2017-11-21 |
Project Management | Satisfactory | 2017-11-21 |
Overall Safeguards Rating | Satisfactory | 2017-11-21 |
Progress towards achievement of PDO | Highly Satisfactory | 2017-11-21 |
Counterpart Funding | Satisfactory | 2017-11-21 |
Overall Implementation Progress (IP) | Satisfactory | 2017-11-21 |
Monitoring and Evaluation | Highly Satisfactory | 2017-11-21 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-22-2017 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-15-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
share of state's water resources under decentralized and participatory planning and management. | Value | 0 | 65% | 65% |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
share of state's territory managed under an "ecological corridor" concept ( coexistence of sustainable production and preservation) | Value | 0 | 10% | 10% |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
share of public financing to family agriculture enterprises channeled through the new rural extension/Technical Assistance strategy | Value | 0 | 60% | 60% |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Restructured Sanitary Phytosanitary and Services (SPS), generating the following results in support of FAFs: | Value | 0 | 2,740 | 2,788 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
rural schools carrying out interdisciplinary actions under PEEA (State Environ. Education Policy) | Value | 0 | 600 | 1,437 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
100% rehabilitation of rural roads associated with business plans | Value | 0 | 100% | 110.4% |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
(ii) Number of enterprises legalized, complying with sanitary standards | Value | 440 | 460 (Increm) | 477 (Increm) |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
(iii) Number of farms certified for absence of animal tuberculosis and brucellosis | Value | 0 | 700 | 728 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
(i) Number of Family Agriculture production and processing units registered and certified as complying with phytosanitary requirements | Value | 6000.00 | 2740.00 | 2788.00 |
Date | March 5, 2010 | June 30, 2017 | ||
Comment |
Increase in total value of annual sales for participating FAPOs | Value | 0.00 | 30.00 | 62.00 |
Date | March 5, 2010 | September 30, 2016 | April 24, 2017 | |
Comment |
Coordinated implementation of six public programs to improve the rural business environment, as measured by: | Value | 0 | 6 public programs | 6 public programs |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Satisfactory technical, financial and procurement audits | Value | 0.00 | 6.00 | 6.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
New, market-oriented, regional, rural extension strategy implemented | Value | 0.00 | 1.00 | 1.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Agro-livestock SPS Services restructured to include specific support for FAPO | Value | 0.00 | 1.00 | 1.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Compliance with Project Operational Manual, including Safeguards and Anti-corruption Policies | Value | 0.00 | 1.00 | 1.00 |
Date | March 16, 2015 | September 30, 2016 | June 30, 2017 | |
Comment |
Number of tourism plans implemented with project support | Value | 10.00 | 20.00 | 5.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Studies completed to implement target Ecological Corridors supporting biodiversity-friendly land use mosaics | Value | 0.00 | 2.00 | 2.00 |
Date | March 5, 2010 | September 30, 2016 | April 24, 2017 | |
Comment |
New added-value arrangements established (63) or strengthened (75) (i.e. alliances / networks and cooperatives) | Value | 55.00 | 138.00 | 259.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Number of existing, small agro-businesses made compliant with sanitary and phytosanitary (SPS) standards, and new agro-processing and non-agricultural businesses created | Value | 0.00 | 500.00 | 723.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Number of Executive Secretariats (“Entidades Delegatarias”) formalized by a legal instrument with the State Government | Value | 0.00 | 2.00 | 2.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Number of self-declaratory water users registered in River Basins | Value | 3.00 | 65000.00 | 74419.00 |
Date | March 5, 2010 | June 30, 2017 | June 30, 2017 | |
Comment |
Hectares of forests under Conservation Credits | Value | 0.00 | 950.00 | 1631.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Farm properties with SIEE (Integrated Economic-Ecological Systems) implemented (SIEE of livestock [meat and milk], grains, forestry, SAF and tourism) | Value | 0.00 | 200.00 | 461.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Kilometers of rural roads rehabilitated associated with business plans | Value | 0.00 | 1300.00 | 474.83 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Number of new regular Technical Assistance and Rural Extension professional staff allocated by EPAGRI in priority project municipalities, by CIDASC to phytosanitary certification and by FATMA to SIEE | Value | 510.00 | 176.00 | 176.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Project Strategic Plan prepared and implemented at the sector level (Rural, WRM, Environmental levels) | Value | 0.00 | 1.00 | 1.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Strategic planning developed and Results-Based Management implemented at the sector level (Rural, WRM, Environment) levels | Value | 0.00 | 1.00 | 1.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Number of additional tenured technical staff in the Water Resources Directorate | Value | 0.00 | 16.00 | 16.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Number of ancillary, climate-resilient production systems improvement and tourism plans executed through subprojects, with project support | Value | 0.00 | 20514.00 | 59834.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Annual Operations Plans successfully implemented | Value | 0.00 | 6.00 | 6.00 |
Date | March 5, 2010 | September 30, 2016 | June 30, 2017 | |
Comment |
Number of Pilot Digital Inclusion proejcts implemented with internet connection to support enterprises connected to networks | Value | 0.00 | 30.00 | 43.00 |
Date | March 16, 2015 | September 30, 2016 | June 30, 2017 | |
Comment |