Financier | Commitments |
---|---|
IDA Credit | 125.00 |
IDA Shorter Maturity Loan (SML) | 30.00 |
IDA Grant | 150.00 |
P119063
Active
Harold Esseku , Christian Yeakula
Republic of Ghana
April 25, 2013
(as of board presentation)
June 6, 2013
August 7, 2014
US$ 150.00 million
GWCL /PIU,Ministry of Sanitation and Water Resources
2013
US$ 305.00 million
A
May 28, 2024
June 30, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 125.00 |
IDA Shorter Maturity Loan (SML) | 30.00 |
IDA Grant | 150.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 305.00 |
IBRD + IDA Commitment | 305.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 27, 2022 | IDA-67810 | Loan Disb | 10,100,000.00 |
Dec 14, 2022 | IDA-67810 | Int Charges | 273,498.34 |
Dec 14, 2022 | IDA-67810 | Int Charges | 273,498.34 |
Dec 14, 2022 | IDA-67810 | Int Charges | 244,392.50 |
Mar 10, 2023 | IDA-67810 | Loan Disb | 10,100,000.00 |
Jun 12, 2024 | IDA-67810 | Int Charges | 651,619.75 |
Jun 12, 2024 | IDA-67810 | Int Charges | 30,440.19 |
Jun 17, 2024 | IDA-67810 | Loan Disb | 4,500,000.00 |
Jun 1, 2023 | IDA-67810 | Int Charges | 35,417.34 |
Jun 1, 2023 | IDA-67810 | Int Charges | 353,677.53 |
Jun 1, 2023 | IDA-67810 | Int Charges | 353,677.53 |
Jun 1, 2023 | IDA-67810 | Int Charges | 354,679.88 |
Nov 30, 2023 | IDA-67810 | Int Charges | 7,159.45 |
Dec 5, 2023 | IDA-67810 | Loan Disb | 15,000,000.00 |
Nov 10, 2023 | IDA-67810 | Loan Disb | 2,334,332.00 |
Oct 18, 2023 | IDA-67810 | Loan Disb | 15,000,000.00 |
May 1, 2023 | IDA-67810 | Loan Disb | 7,000,000.00 |
Jun 12, 2024 | IDA-67810 | Int Charges | 636,921.50 |
Jun 12, 2024 | IDA-67810 | Int Charges | 636,921.50 |
Aug 8, 2024 | IDA-76210 | Loan Commitment | 30,000,000.00 |
Sep 22, 2020 | IDA-67810 | Loan Commitment | 125,000,000.00 |
Jun 6, 2013 | IDA-H8540 | Loan Commitment | 150,000,000.00 |
Feb 14, 2018 | IDA-H8540 | Loan Disb | 7,429,430.50 |
Aug 7, 2017 | IDA-H8540 | Loan Disb | 234,023.23 |
Oct 12, 2017 | IDA-H8540 | Loan Disb | 192,999.34 |
Sep 28, 2017 | IDA-H8540 | Loan Disb | 529,832.06 |
Jan 31, 2018 | IDA-H8540 | Loan Disb | 203,496.47 |
Jan 26, 2018 | IDA-H8540 | Loan Disb | 165,605.55 |
May 13, 2021 | IDA-67810 | Loan Disb | 6,000,000.00 |
Nov 29, 2021 | IDA-67810 | Int Charges | 4,188.89 |
Nov 29, 2021 | IDA-67810 | Int Charges | 4,188.89 |
Nov 29, 2021 | IDA-67810 | Int Charges | 4,285.56 |
Nov 29, 2021 | IDA-67810 | Int Charges | 124,117.49 |
Nov 29, 2021 | IDA-67810 | Int Charges | 124,117.49 |
Nov 29, 2021 | IDA-67810 | Int Charges | 125,732.49 |
Jun 1, 2022 | IDA-67810 | Int Charges | 1,249.24 |
Jun 1, 2022 | IDA-67810 | Int Charges | 188,519.88 |
Jun 1, 2022 | IDA-67810 | Int Charges | 188,519.88 |
Jun 1, 2022 | IDA-67810 | Int Charges | 192,870.34 |
Jun 21, 2022 | IDA-67810 | Loan Disb | 684,640.00 |
Jun 21, 2022 | IDA-67810 | Loan Disb | 3,000,000.00 |
Mar 9, 2022 | IDA-67810 | Loan Disb | 7,200,000.00 |
Mar 9, 2022 | IDA-67810 | Loan Disb | 4,535,623.00 |
May 7, 2021 | IDA-67810 | Loan Disb | 13,000,000.00 |
Nov 12, 2021 | IDA-67810 | Loan Disb | 5,700,000.00 |
Nov 30, 2023 | IDA-67810 | Int Charges | 452,628.16 |
Nov 30, 2023 | IDA-67810 | Int Charges | 452,628.16 |
Nov 30, 2023 | IDA-67810 | Int Charges | 432,633.28 |
Feb 22, 2018 | IDA-H8540 | Loan Disb | 9,467,465.00 |
Jun 12, 2017 | IDA-H8540 | Loan Disb | 15,150,736.00 |
Oct 17, 2017 | IDA-H8540 | Loan Disb | 205,901.22 |
Feb 28, 2017 | IDA-H8540 | Loan Disb | 2,886,508.20 |
May 16, 2017 | IDA-H8540 | Loan Disb | 247,644.16 |
Mar 28, 2017 | IDA-H8540 | Loan Disb | 201,120.08 |
Sep 27, 2017 | IDA-H8540 | Loan Disb | 204,334.05 |
Nov 21, 2016 | IDA-H8540 | Loan Disb | 436,473.88 |
Jul 13, 2016 | IDA-H8540 | Loan Disb | 1,384,208.40 |
Dec 23, 2016 | IDA-H8540 | Loan Disb | 534,916.94 |
Nov 21, 2016 | IDA-H8540 | Loan Disb | 436,473.88 |
Nov 21, 2016 | IDA-H8540 | Loan Disb | 1,876,599.20 |
Nov 21, 2016 | IDA-H8540 | Loan Disb | 408,803.66 |
Apr 21, 2017 | IDA-H8540 | Loan Disb | 148,220.14 |
Apr 10, 2017 | IDA-H8540 | Loan Disb | 510,134.34 |
Feb 24, 2016 | IDA-H8540 | Loan Disb | 9,739,191.00 |
Sep 16, 2016 | IDA-H8540 | Loan Disb | 6,445,824.00 |
Jan 23, 2017 | IDA-H8540 | Loan Disb | 9,787,546.00 |
Nov 3, 2016 | IDA-H8540 | Loan Disb | 8,151,219.00 |
Aug 3, 2015 | IDA-H8540 | Loan Disb | 2,875,550.80 |
Mar 19, 2015 | IDA-H8540 | Loan Disb | 1,140,000.00 |
Sep 9, 2014 | IDA-H8540 | Loan Disb | 5,000,000.00 |
Apr 14, 2015 | IDA-H8540 | Loan Disb | 1,830,000.00 |
Apr 9, 2019 | IDA-H8540 | Loan Disb | 9,000,000.00 |
Oct 15, 2019 | IDA-H8540 | Loan Disb | 2,100,000.00 |
Oct 23, 2019 | IDA-H8540 | Loan Disb | 4,900,000.00 |
Aug 11, 2020 | IDA-H8540 | Loan Disb | 3,000,000.00 |
Feb 5, 2020 | IDA-H8540 | Loan Disb | 9,700,000.00 |
Jun 30, 2021 | IDA-H8540 | Loan Cancel | 1,640.57 |
Jun 15, 2021 | IDA-H8540 | Loan Disb | 19,128.89 |
Dec 18, 2020 | IDA-H8540 | Loan Disb | 165,500.00 |
Oct 16, 2020 | IDA-H8540 | Loan Disb | 1,951,228.10 |
Dec 28, 2017 | IDA-H8540 | Loan Disb | 311,022.03 |
Dec 22, 2017 | IDA-H8540 | Loan Disb | 777,412.06 |
Dec 22, 2017 | IDA-H8540 | Loan Disb | 107,625.55 |
Jun 25, 2018 | IDA-H8540 | Loan Disb | 4,999,999.00 |
Oct 15, 2018 | IDA-H8540 | Loan Disb | 9,874,311.00 |
Jan 16, 2019 | IDA-H8540 | Loan Disb | 5,000,000.00 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 07-24-2020 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 07-20-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with access to "improved sanitation facilities” under the proj. | Value | 0.00 | 217936.00 | 75000.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 368000.00 | 250000.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
Volume(mass) of BOD pollution load removed by treatment plant under the project | Value | 0.00 | 114.00 | 400.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
Share of households in the low-income communities benefited under the project that live in a single room | Value | 0.00 | 75.00 | 75.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 368000.00 | 250000.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
People provided with access to “improved sanitation facilities” - urban | Value | 0.00 | 217936.00 | 75000.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
School Pupils provided with improved sanitation facilities | Value | 0.00 | 231872.00 | 200000.00 |
Date | August 7, 2014 | February 28, 2020 | December 31, 2020 | |
Comment |
Female beneficiaries | Value | 0.00 | 53.00 | 0.00 |
Date | March 4, 2013 | May 1, 2018 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Improved latrines constructed under the project | Value | 0.00 | 27242.00 | 12500.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
Improved community water points constructed or rehabilitated under the project | Value | 0.00 | 114.00 | 114.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
Capacity of sludge treatment plants constructed or rehabilitated under the project | Value | 0.00 | 50.00 | 900.00 |
Date | March 4, 2013 | September 30, 2019 | December 31, 2020 | |
Comment |
People trained to improve hygiene behavior/sanitation practices under the proj | Value | 0.00 | 298712.00 | 250000.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 10200.00 | 3500.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
Integrated master plans for liquid waste, solid waste and drainage in the GAMA | Value | No | No | Yes |
Date | March 4, 2013 | September 30, 2019 | December 31, 2020 | |
Comment |
Of which in rental accommodation | Value | 0.00 | 19614.00 | 5000.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
People trained to improve hygiene behavior/sanitation practices - female | Value | 0.00 | 155330.00 | 127000.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
Water distribution mains installed under the project | Value | 0.00 | 281.00 | 150.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
Drainage interventions in low-income communities (length of lined drains) | Value | 0.00 | 20.00 | 20.00 |
Date | June 6, 2013 | May 29, 2020 | December 31, 2020 | |
Comment |
GWCL low-income unit established | Value | No | Yes | Yes |
Date | March 4, 2013 | September 30, 2019 | December 31, 2020 | |
Comment |
Of which in schools, markets and health centers | Value | 0.00 | 339.00 | 200.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
People provided with access to septage emptying services or sewerage under the project | Value | 0.00 | 205000.00 | 225000.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
Number of water utilities that the project is supporting | Value | 0.00 | 1.00 | 0.00 |
Date | March 4, 2013 | February 28, 2020 | ||
Comment |
Drainage interventions in low-income communities (length of unlined drains) | Value | 0.00 | 30.00 | 30.00 |
Date | June 6, 2013 | May 29, 2020 | December 31, 2020 | |
Comment |
Inter-MMA coordination mechanism established | Value | No | Yes | Yes |
Date | March 4, 2013 | September 30, 2019 | December 31, 2020 | |
Comment |
Piped household water connections that are benefiting from rehabilitation works undertaken by the project | Value | 0.00 | 73000.00 | 50000.00 |
Date | March 4, 2013 | April 30, 2019 | December 31, 2020 | |
Comment |
Regulatory system for septage management in place | Value | No | No | Yes |
Date | March 4, 2013 | September 30, 2019 | December 31, 2020 | |
Comment |
Number of MMA's scoring at least 75% of maximum on DDF sanitation indicators | Value | 1.00 | 11.00 | 11.00 |
Date | March 4, 2013 | February 28, 2020 | December 31, 2020 | |
Comment |
WSS data on target communities publicly available | Value | No | Yes | Yes |
Date | March 4, 2013 | September 30, 2019 | December 31, 2020 | |
Comment |
Number of micro-enterprises providing sanitation services | Value | 0.00 | 12.00 | 12.00 |
Date | March 4, 2013 | September 30, 2019 | December 31, 2020 | |
Comment |