Financier | Commitments |
---|---|
Special Financing | 1.75 |
P119947
Closed
Ashok Kumar
N/A
December 19, 2011
(as of board presentation)
December 19, 2011
N/A
US$ 1.75 million
N/A
2012
US$ 1.75 million
C
N/A
September 30, 2019
BANK APPROVED
August 1, 2023
Financier | Commitments |
---|---|
Special Financing | 1.75 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 1.75 |
Total Project Cost** | 1.75 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2019-12-10 |
Counterpart Funding | Moderately Unsatisfactory | 2019-12-10 |
Project Management | Moderately Satisfactory | 2019-12-10 |
Financial Management | Moderately Satisfactory | 2019-12-10 |
Procurement | Satisfactory | 2019-12-10 |
Monitoring and Evaluation | Moderately Satisfactory | 2019-12-10 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2019-12-10 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Secondary road network in good or fair condition (Percentage, Custom) | Value | 25.00 | 40.00 | 0.00 |
Date | January 1, 2012 | September 30, 2019 | ||
Comment |
Improved Asset Management (Number, Custom) | Value | 0.00 | 50.00 | 0.00 |
Date | January 1, 2012 | September 30, 2019 | ||
Comment |
Reduction in travel time on the project corridors (Percentage, Custom) | Value | 0.00 | 20.00 | 0.00 |
Date | January 1, 2012 | September 30, 2019 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Road improvement and rehabilitation of 500 km core network roads (Kilometers, Custom) | Value | 0.00 | 943.00 | 1000.00 |
Date | January 1, 2012 | September 30, 2019 | March 20, 2018 | |
Comment |
Training of PWRD staff - percent staff receving minimum 2 day training annually (Percentage, Custom) | Value | 0.00 | 25.00 | 0.00 |
Date | January 1, 2012 | September 30, 2019 | ||
Comment |
Development and Implementation of Road Safety strategy (Yes/No, Custom) | Value | No | Yes | |
Date | March 13, 2012 | September 30, 2019 | ||
Comment |
Pilot projects on innovative design of bridges (Text, Custom) | Value | None | Length-wise 168 m has been completed. In addition, | |
Date | March 13, 2012 | September 30, 2019 | ||
Comment |
Institutional strengthening of PWRD (Text, Custom) | Value | Not applicable | 1. Road Maintenance Fund operational.2. Strategic | |
Date | March 13, 2012 | September 30, 2019 | ||
Comment |
Road safety improvements (Kilometers, Custom) | Value | 0 | 300 | |
Date | January 1, 2012 | September 30, 2019 | ||
Comment |
Increased Maintenance Funding (INR million) (Number, Custom) | Value | 1800.00 | 5000.00 | 0.00 |
Date | March 31, 2012 | September 30, 2019 | ||
Comment |