Emergency Support to Enhance Food Security (ESEFS)

Development Objective

The project development objective is to increase domestic production of food crops (mainly maize and rice) in target areas.

Key Details

Project Details

  • P120052

  • Closed

  • Erick Abiassi

  • N/A

  • Benin

  • March 26, 2010

  • (as of board presentation)

    May 11, 2010

  • May 25, 2010

  • US$ 9.61 million

  • B

  • Not Applicable

  • December 31, 2011

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Food Crisis Response Program 9.61

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 9.61
Total Project Cost** 9.61

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2011-11-21
Progress towards achievement of PDO Satisfactory 2011-11-21
Financial Management Satisfactory 2011-11-21
Monitoring and Evaluation Satisfactory 2011-11-21
Overall Implementation Progress (IP) Moderately Satisfactory 2011-11-21
Counterpart Funding Satisfactory 2011-11-21
Project Management Satisfactory 2011-11-21

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-25-2012
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-13-2014PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeModerateN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.0014180.0015500.00
    DateMarch 31, 2010December 27, 2011December 31, 2011
    Comment
  • Rice production in project areasValue58000.0062094.0061500.00
    DateMarch 31, 2010December 27, 2011December 31, 2011
    CommentEstimate of 2009 production in target areasThe project has generated an additional 4,094 tons in target areas.The project is expected to generate an additional 3,500 tons in target areas
  • Maize production in target areasValue190000.00204066.00202000.00
    DateMarch 31, 2010December 27, 2011December 31, 2011
    CommentEstimate of 2009 production in target areasThe project has generated an additional 14,066 tons in target areas.The project is expected to generate an additional 12,000 tons
  • Female beneficiariesValue0.000.000.00
    DateMarch 31, 2010December 27, 2011December 31, 2011
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Fertilizer procured and distributed to farmersValue0.003275.003275.00
    DateMarch 31, 2010August 31, 2011December 31, 2011
    CommentThe entire 3275 tons of fertilizers were procured and successfully distributed to maize and rice farmers.
  • Improved seed distributed to farmersValue0.00784.00545.00
    DateMarch 31, 2010December 27, 2011December 31, 2011
    CommentOverall, 784 tons of improved seeds were financed out of counterpart funding and successfully distributed to farmers.
  • Producers using adequate dose of fertilizerValue0.004215.0015500.00
    DateMarch 31, 2010December 27, 2011December 31, 2011
    CommentThis is about 27.2% of the target value.
  • Area cultivated/treated with adequate dose of fertilizerValue0.007320.0015500.00
    DateMarch 31, 2010December 27, 2011December 31, 2011
    CommentThis is about 47.2% of the target value.
  • Proposal of market-based input delivery mechanism for food crop producers adopted and testedValueNoYesYes
    DateMarch 31, 2010July 31, 2011December 31, 2011
    CommentThe market-based input delivery mechanism for food crop producers was designed and adopted by the government and otherstakeholdersin July, 2011 but the mechanism is yet to be tested.
  • Small scale irrigation perimeters developed in the Niger river valleyValue0.002640.002000.00
    DateMarch 31, 2010December 27, 2011December 31, 2011
    CommentThis is about 132% of the target value.
  • Small scale irrigation primeters developed in the hill region and Mono and Couffo river valleysValue0.002360.001000.00
    DateMarch 31, 2010December 27, 2011December 31, 2011
    CommentThis is about 236% of the target value.
  • Producers settled/cultivating on the small scale irrigation perimetersValue0.005044.003000.00
    DateMarch 31, 2010December 27, 2011December 31, 2011
    CommentThis is about 168% of the target value.
  • 150 m2 capacity storage facilities constructedValue0.0035.0035.00
    DateMarch 31, 2010December 29, 2011December 31, 2011
    CommentAll the 35 storehouses has been completed and delivered to beneficiaries by December 29, 2011.
  • 200 m2 capacity drying areas constructedValue0.0048.0070.00
    DateMarch 31, 2010December 29, 2011December 31, 2011
    Comment48 out of the 70 drying areas has been completed and delivered to beneficiaries by December 29, 2011.