Financier | Commitments |
---|---|
Borrower/Recipient | 40.00 |
International Bank for Reconstruction and Development | 200.00 |
P120211
Closed
Victor Vazquez Alvarez , Maria Ramirez
The Argentine Republic
May 17, 2010
(as of board presentation)
December 20, 2010
July 4, 2011
US$ 240.00 million
Ministry of Interior, Public Works and Housing , UCPyPFE
2011
US$ 200.00 million
B
Not Applicable
April 26, 2019
BANK APPROVED
November 14, 2022
Financier | Commitments |
---|---|
Borrower/Recipient | 40.00 |
International Bank for Reconstruction and Development | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 200.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 240.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 15, 2016 | IBRD-79920 | Int Charges | 712,788.00 |
Apr 9, 2018 | IBRD-79920 | Loan Disb | 2,000,000.00 |
Feb 8, 2018 | IBRD-79920 | Loan Disb | 4,000,000.00 |
Mar 15, 2018 | IBRD-79920 | Int Charges | 637,508.50 |
Mar 15, 2018 | IBRD-79920 | Int Charges | 514,912.06 |
Mar 15, 2018 | IBRD-79920 | Int Charges | 72,937.50 |
Mar 15, 2018 | IBRD-79920 | Int Charges | 233,856.94 |
Mar 15, 2018 | IBRD-79920 | Int Charges | 292,847.00 |
Mar 15, 2018 | IBRD-79920 | Loan Repay | 106,858.67 |
Mar 15, 2018 | IBRD-79920 | Loan Repay | 89,106.23 |
Mar 15, 2018 | IBRD-79920 | Loan Repay | 596,039.10 |
Mar 15, 2018 | IBRD-79920 | Loan Repay | 27,395.64 |
Mar 15, 2018 | IBRD-79920 | Loan Repay | 162,007.22 |
Mar 15, 2018 | IBRD-79920 | Loan Repay | 317,999.70 |
Mar 15, 2018 | IBRD-79920 | Loan Repay | 322,826.30 |
Mar 15, 2018 | IBRD-79920 | Loan Repay | 423,668.20 |
Mar 15, 2018 | IBRD-79920 | Loan Repay | 430,455.12 |
Mar 15, 2018 | IBRD-79920 | Loan Repay | 1,850,043.80 |
Sep 15, 2017 | IBRD-79920 | Loan Disb | 8,813,950.00 |
Oct 26, 2017 | IBRD-79920 | Loan Disb | 6,000,000.00 |
Nov 29, 2017 | IBRD-79920 | Loan Disb | 6,000,000.00 |
Sep 15, 2017 | IBRD-79920 | Int Charges | 3,315.96 |
Sep 15, 2017 | IBRD-79920 | Int Charges | 1,461,382.50 |
Jul 14, 2017 | IBRD-79920 | Loan Disb | 7,027,987.50 |
Feb 28, 2017 | IBRD-79920 | Loan Disb | 4,278,663.00 |
May 21, 2019 | IBRD-79920 | Loan Disb | 2,000,027.80 |
Jun 11, 2019 | IBRD-79920 | Loan Disb | 1,605,033.80 |
Mar 15, 2019 | IBRD-79920 | Int Charges | 2,891,085.00 |
Mar 15, 2019 | IBRD-79920 | Loan Repay | 1,899,545.90 |
Mar 15, 2015 | IBRD-79920 | Int Charges | 207,892.50 |
Sep 15, 2014 | IBRD-79920 | Int Charges | 192.02 |
Mar 12, 2015 | IBRD-79920 | Loan Disb | 6,048,997.00 |
Sep 15, 2014 | IBRD-79920 | Int Charges | 128,673.07 |
Sep 24, 2014 | IBRD-79920 | Loan Disb | 5,702,739.00 |
Aug 11, 2014 | IBRD-79920 | Loan Disb | 3,535,478.20 |
Jul 14, 2017 | IBRD-79920 | Loan Disb | 5,000,000.00 |
May 3, 2017 | IBRD-79920 | Loan Disb | 8,071,426.00 |
Mar 15, 2017 | IBRD-79920 | Int Charges | 8,532.91 |
Mar 15, 2017 | IBRD-79920 | Int Charges | 1,085,356.50 |
Mar 15, 2023 | IBRD-79920 | Int Charges | 81,877.07 |
Mar 15, 2023 | IBRD-79920 | Loan Repay | 169,976.27 |
Mar 15, 2023 | IBRD-79920 | Loan Repay | 21,541.46 |
Mar 15, 2023 | IBRD-79920 | Int Charges | 338,137.53 |
Mar 15, 2020 | IBRD-79920 | Int Charges | 2,444,704.00 |
Mar 15, 2020 | IBRD-79920 | Loan Repay | 5,033,606.50 |
Jul 25, 2019 | IBRD-79920 | Loan Disb | 42,892.58 |
Sep 15, 2019 | IBRD-79920 | Int Charges | 8,627.36 |
Aug 27, 2019 | IBRD-79920 | Loan Cancel | 4,858,235.50 |
Sep 15, 2019 | IBRD-79920 | Int Charges | 3,101,188.00 |
Sep 15, 2019 | IBRD-79920 | Loan Repay | 539,183.50 |
Sep 15, 2019 | IBRD-79920 | Loan Repay | 4,493,200.50 |
Sep 15, 2021 | IBRD-79920 | Loan Repay | 750,613.94 |
Sep 15, 2021 | IBRD-79920 | Int Charges | 750,613.94 |
Sep 15, 2021 | IBRD-79920 | Loan Repay | 4,282,992.50 |
Mar 15, 2021 | IBRD-79920 | Int Charges | 819,975.50 |
Mar 15, 2021 | IBRD-79920 | Loan Repay | 5,033,606.50 |
Sep 15, 2020 | IBRD-79920 | Int Charges | 1,244,353.20 |
Sep 15, 2020 | IBRD-79920 | Loan Repay | 5,033,606.50 |
Nov 10, 2016 | IBRD-79920 | Loan Disb | 9,700,641.00 |
Nov 21, 2016 | IBRD-79920 | Loan Disb | 4,254,309.00 |
Dec 21, 2016 | IBRD-79920 | Loan Disb | 5,918,230.50 |
Aug 10, 2016 | IBRD-79920 | Loan Disb | 5,717,975.00 |
May 17, 2016 | IBRD-79920 | Loan Disb | 11,516,314.00 |
Aug 8, 2016 | IBRD-79920 | Loan Disb | 45,000.00 |
Sep 15, 2023 | IBRD-79920 | Int Charges | 378,540.00 |
Mar 15, 2023 | IBRD-79920 | Int Charges | 71,731.10 |
Mar 15, 2023 | IBRD-79920 | Int Charges | 2,886,340.80 |
Mar 15, 2023 | IBRD-79920 | Loan Repay | 714,665.06 |
Mar 15, 2023 | IBRD-79920 | Int Charges | 41,474.52 |
Mar 15, 2023 | IBRD-79920 | Int Charges | 336,689.70 |
Mar 15, 2023 | IBRD-79920 | Loan Repay | 338,137.53 |
Mar 15, 2023 | IBRD-79920 | Loan Repay | 227,018.88 |
Mar 15, 2023 | IBRD-79920 | Int Charges | 59,385.45 |
Mar 15, 2019 | IBRD-79920 | Int Charges | 23,544.42 |
Mar 18, 2019 | IBRD-79920 | Loan Disb | 1,000,001.25 |
Feb 5, 2019 | IBRD-79920 | Loan Disb | 2,514,857.80 |
Nov 13, 2018 | IBRD-79920 | Loan Disb | 3,225,000.20 |
Nov 1, 2018 | IBRD-79920 | Loan Disb | 1,653,974.50 |
Aug 7, 2018 | IBRD-79920 | Loan Disb | 7,342,331.50 |
Sep 15, 2018 | IBRD-79920 | Loan Repay | 4,484,200.00 |
Sep 15, 2018 | IBRD-79920 | Int Charges | 8,205.55 |
Sep 15, 2018 | IBRD-79920 | Int Charges | 0.02 |
Sep 15, 2018 | IBRD-79920 | Int Charges | 2,577,990.80 |
Mar 15, 2020 | IBRD-79920 | Int Charges | 209.41 |
Jul 2, 2019 | IBRD-79920 | Loan Disb | 757,645.56 |
Mar 15, 2019 | IBRD-79920 | Loan Repay | 2,914,629.50 |
Jun 12, 2014 | IBRD-79920 | Loan Disb | 5,835,016.50 |
Mar 15, 2014 | IBRD-79920 | Int Charges | 379.87 |
Mar 15, 2014 | IBRD-79920 | Int Charges | 96,376.68 |
Dec 20, 2013 | IBRD-79920 | Loan Disb | 1,320,348.80 |
Mar 13, 2014 | IBRD-79920 | Loan Disb | 4,066,393.80 |
Nov 21, 2013 | IBRD-79920 | Loan Disb | 1,869,376.20 |
Oct 23, 2013 | IBRD-79920 | Loan Disb | 2,124,678.50 |
Sep 15, 2013 | IBRD-79920 | Int Charges | 106.31 |
Sep 15, 2013 | IBRD-79920 | Int Charges | 76,459.26 |
Sep 3, 2013 | IBRD-79920 | Loan Disb | 1,266,268.80 |
Dec 16, 2014 | IBRD-79920 | Loan Disb | 9,764,019.00 |
Nov 14, 2014 | IBRD-79920 | Loan Disb | 2,648,786.80 |
Mar 15, 2016 | IBRD-79920 | Int Charges | 10,086.51 |
Mar 15, 2016 | IBRD-79920 | Int Charges | 469,478.20 |
Dec 7, 2015 | IBRD-79920 | Loan Disb | 241,122.06 |
Sep 15, 2015 | IBRD-79920 | Int Charges | 418.38 |
Sep 15, 2015 | IBRD-79920 | Int Charges | 309,155.97 |
Nov 2, 2015 | IBRD-79920 | Loan Disb | 5,116,375.50 |
Aug 25, 2015 | IBRD-79920 | Loan Disb | 7,993,507.50 |
Jul 23, 2015 | IBRD-79920 | Loan Disb | 4,121,882.50 |
Jun 29, 2015 | IBRD-79920 | Loan Disb | 7,191,266.00 |
Mar 15, 2015 | IBRD-79920 | Int Charges | 2,749.82 |
Mar 15, 2023 | IBRD-79920 | Int Charges | 47,654.78 |
Mar 15, 2023 | IBRD-79920 | Loan Repay | 1,872,063.90 |
Mar 15, 2023 | IBRD-79920 | Loan Repay | 1,254,545.80 |
Mar 15, 2023 | IBRD-79920 | Loan Repay | 264,356.03 |
Mar 15, 2023 | IBRD-79920 | Loan Repay | 171,301.38 |
Sep 15, 2022 | IBRD-79920 | Int Charges | 1,420,118.00 |
Sep 15, 2022 | IBRD-79920 | Loan Repay | 3,613,488.20 |
Sep 15, 2022 | IBRD-79920 | Loan Repay | 1,420,118.00 |
Mar 15, 2022 | IBRD-79920 | Loan Repay | 5,033,606.50 |
Mar 15, 2022 | IBRD-79920 | Int Charges | 691,762.70 |
Dec 20, 2010 | IBRD-79920 | Loan Commitment | 200,000,000.00 |
Mar 15, 2024 | IBRD-79920 | Loan Repay | 4,487,415.00 |
Mar 15, 2024 | IBRD-79920 | Loan Repay | 546,191.30 |
Mar 15, 2024 | IBRD-79920 | Int Charges | 72,471.52 |
Mar 15, 2024 | IBRD-79920 | Int Charges | 4,414,943.50 |
Sep 15, 2023 | IBRD-79920 | Int Charges | 1,793,416.50 |
Sep 15, 2023 | IBRD-79920 | Int Charges | 1,950,570.00 |
Sep 15, 2023 | IBRD-79920 | Loan Repay | 5,033,606.50 |
Sep 15, 2023 | IBRD-79920 | Int Charges | 55,870.96 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2019-04-26 |
Counterpart Funding | Satisfactory | 2019-04-26 |
Financial Management | Satisfactory | 2019-04-26 |
Progress towards achievement of PDO | Moderately Satisfactory | 2019-04-26 |
Project Management | Satisfactory | 2019-04-26 |
Monitoring and Evaluation | Satisfactory | 2019-04-26 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2019-04-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-15-2020 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 12-07-2020 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of people in urban areas provided with access to Improved Water Sources under the project | Value | 0.00 | 34000.00 | 50500.00 |
Date | November 17, 2010 | June 10, 2020 | December 10, 2015 | |
Comment |
Number of people in the NGR that benefits from urban drainage networks built under the Project | Value | 0.00 | 40000.00 | 40000.00 |
Date | November 17, 2010 | June 10, 2020 | December 10, 2015 | |
Comment |
Evidence that at least 30% percent of additional beneficiaries of the new water supply infrastructure built under the Project are poor | Value | 0.00 | 32.50 | 0.00 |
Date | November 17, 2010 | April 26, 2019 | ||
Comment |
Number of water providers that have implemented a monitoring system (management panel) as a tool for strategic decision making to improve management. | Value | 0.00 | 4.00 | 3.00 |
Date | November 17, 2010 | June 10, 2020 | December 10, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
New piped household water connections that are resulting from the project intervention | Value | 0.00 | 600.00 | 0.00 |
Date | December 20, 2010 | June 10, 2020 | ||
Comment |
Number of service providers at the provincial or municipal level enrolled in an institutional development program financed by the Project | Value | 0.00 | 6.00 | 0.00 |
Date | December 20, 2010 | June 10, 2020 | ||
Comment |
Project adequately managed | Value | Yes | Yes | |
Date | December 20, 2010 | June 10, 2020 | ||
Comment |
Number of piped households that receive safe water treated according to regulatory standards | Value | 0.00 | 3000.00 | 6000.00 |
Date | December 20, 2010 | June 10, 2020 | December 10, 2015 | |
Comment |
Number of more efficient and financially healthier providers of WSS services | Value | 0.00 | 2.00 | 0.00 |
Date | December 20, 2010 | June 10, 2020 | ||
Comment |
Disperse indigenous population with improved access to water from the works built under the project | Value | 0.00 | 6215.00 | 0.00 |
Date | October 29, 2015 | June 10, 2020 | ||
Comment |
Surface of urban area protected from flooding with drainage networks built under the project | Value | 0.00 | 750.00 | 0.00 |
Date | October 29, 2015 | June 10, 2020 | ||
Comment |