Financier | Commitments |
---|---|
Global Food Crisis Response Program | 4.30 |
P120214
Closed
Aniceto Bila
N/A
December 9, 2009
(as of board presentation)
February 22, 2010
May 14, 2010
US$ 4.30 million
N/A
2010
US$ 4.30 million
B
Not Applicable
December 31, 2011
BANK APPROVED
January 15, 2013
Financier | Commitments |
---|---|
Global Food Crisis Response Program | 4.30 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 4.30 |
Total Project Cost** | 4.30 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2012-01-02 |
Monitoring and Evaluation | Moderately Satisfactory | 2012-01-02 |
Counterpart Funding | Satisfactory | 2012-01-02 |
Project Management | Satisfactory | 2012-01-02 |
Financial Management | Moderately Satisfactory | 2012-01-02 |
Progress towards achievement of PDO | Satisfactory | 2012-01-02 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2012-01-02 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Pre-school and primary students receiving at least one meal per day | Value | 0.00 | 28040.00 | 28000.00 |
Date | March 30, 2010 | December 21, 2011 | December 31, 2011 | |
Comment | This reflects the average number of students that received one meal per day under project assistance from March 2010 to June 2011 |
Work-days (rations distributed to rural producers) in food-for-work activities | Value | 0.00 | 168000.00 | 162000.00 |
Date | March 30, 2010 | December 21, 2011 | December 31, 2011 | |
Comment | The end target has been exceeded |
Beneficiaries of food-for-work program | Value | 0.00 | 53452.00 | 18900.00 |
Date | March 30, 2010 | December 21, 2011 | December 31, 2011 | |
Comment | End target exceeded |
Rice produced in the new rehabilitated areas under the Project | Value | 0.00 | 0.00 | 1000.00 |
Date | March 30, 2010 | December 31, 2011 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads rehabilitated, Rural | Value | 0.00 | 170.00 | 300.00 |
Date | March 30, 2010 | December 21, 2011 | December 31, 2011 | |
Comment | Only 170 Km have been fully completed and handed over. The number of km is apparently reduced from previous ISR because we haveonly consider those roads that have been fully completed and handed over to government. In the previous ISR the team took thepercentage completed in each road to calculated the total roads. If the same methodology was used, by December 7, 2011 there wereabout 270 km of feeder roads completed. | Final data on the total feeder roads rehabilitated will be available after the project is closed and will be reported on the ICR.The ICR mission is scheduled for February 2012. |
Fertilizer procured and distributed to farmers | Value | 0.00 | 50.00 | 50.00 |
Date | March 30, 2010 | December 21, 2011 | December 31, 2011 | |
Comment | Fertyilzer was distributed to farmers cultivating lowland areas, and covered approximately 600ha |
Area cultivated with improved seeds and adequate dosage of fertilizers | Value | 0.00 | 1000.00 | 1000.00 |
Date | March 30, 2010 | December 21, 2011 | December 31, 2011 | |
Comment | 400 ha is mangrove land and 600ha lowland |
Meals served per day | Value | 0.00 | 28040.00 | 28000.00 |
Date | March 30, 2010 | July 16, 2011 | December 31, 2011 | |
Comment | This indicator has been achieved and the school feeding closed in June 2011 |
Seeds procured and distributed to farmers | Value | 0.00 | 60.00 | 60.00 |
Date | March 30, 2010 | December 21, 2011 | December 31, 2011 | |
Comment | The seed was distributed to about 200 farmers and will cover about 1,000ha of cultivated land |
Sub-projects approved and under implementation (excluding seeds and fertilizers) | Value | 0.00 | 64.00 | 64.00 |
Date | March 30, 2010 | December 21, 2011 | December 31, 2011 | |
Comment | 64 micro-project were approved and benefited equal number of communities. |