The objective of the Urban Governance and Development Program: Emerging Town Project for Nepal is to improve delivery and sustainable provision of basic services and priority infrastructure in the participating municipalities. There are three components to the project, the first component being service delivery improvement. This component will, over time, aim to establish rules, and capacitate systems for improving the transparency, predictability...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The revised PDO is 'to improve the capacity of the participating municipalities to plan, implement and fund urban development activities'.

Key Details

Project Details

  • P120265

  • Closed

  • Yoonhee Kim , Jonas Parby, Harsh Goyal

  • TOWN DEVELOPMENT FUND,Ministry of Urban Development

  • Nepal

  • May 10, 2011

  • (as of board presentation)

    May 10, 2011

  • October 2, 2011

  • US$ 35.14 million

  • Department of Urban Development and Building Construction (DUDBC)

  • South Asia

  • 2011

  • US$ 28.00 million

  • B

  • August 9, 2023

  • January 31, 2017

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
GERMANY: German Technical Assistance Corporation (GTZ) 3.00
IDA Credit 25.00
Local Communities 2.14
Borrower/Recipient 5.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 25.00
IBRD + IDA Commitment 25.00
Lending Instrument
Grant Amount 3.00
Total Project Cost** 35.14

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 15, 2018 IDA-49050 Int Charges 87.11
Apr 15, 2018 IDA-49050 Int Charges 16,398.18
Apr 15, 2018 IDA-49050 Int Charges 16,398.18
Jul 28, 2017 IDA-49050 Loan Disb -56,763.31
Jun 28, 2016 IDA-H6610 Loan Disb -30.00
Aug 7, 2017 IDA-49050 Loan Cancel 58,071.37
Jun 29, 2017 IDA-H6610 Loan Cancel 1,652,790.50
Aug 7, 2017 IDA-49050 Loan Disb 49.99
Aug 7, 2017 IDA-49050 Loan Disb -49.99
Jun 28, 2016 IDA-H6610 Loan Disb 30.00
Oct 15, 2017 IDA-49050 Int Charges 103.28
Oct 15, 2017 IDA-49050 Int Charges 103.28
Oct 15, 2017 IDA-49050 Int Charges 15,989.01
Apr 15, 2019 IDA-49050 Int Charges 162.27
Apr 15, 2019 IDA-49050 Int Charges 162.27
Apr 15, 2019 IDA-49050 Int Charges 15,632.73
Apr 15, 2019 IDA-49050 Int Charges 15,632.73
Oct 15, 2018 IDA-49050 Int Charges 47.26
Oct 15, 2018 IDA-49050 Int Charges 47.26
Oct 15, 2018 IDA-49050 Int Charges 15,549.98
Oct 15, 2018 IDA-49050 Int Charges 15,549.98
Oct 15, 2020 IDA-49050 Int Charges 10.15
Oct 15, 2020 IDA-49050 Int Charges 15,883.59
Oct 15, 2020 IDA-49050 Int Charges 15,883.59
Oct 15, 2020 IDA-49050 Int Charges 10.15
Apr 15, 2020 IDA-49050 Int Charges 41.38
Apr 15, 2020 IDA-49050 Int Charges 41.38
Apr 15, 2020 IDA-49050 Int Charges 15,366.76
Apr 15, 2020 IDA-49050 Int Charges 15,366.76
Oct 15, 2019 IDA-49050 Int Charges 44.25
Nov 10, 2013 IDA-49050 Loan Disb 2,000,000.00
Nov 22, 2013 IDA-49050 Loan Disb 684,641.70
Jan 2, 2014 IDA-H6610 Loan Disb 353,126.66
Nov 8, 2013 IDA-H6610 Loan Disb 1,049,749.90
Sep 26, 2014 IDA-49050 Loan Disb 112,937.04
Oct 15, 2014 IDA-49050 Int Charges 11,342.18
Oct 15, 2014 IDA-49050 Int Charges 11,342.18
Oct 15, 2014 IDA-49050 Int Charges 189.74
Oct 15, 2014 IDA-49050 Int Charges 189.74
Oct 28, 2014 IDA-H6610 Loan Disb 3,650.60
Oct 28, 2014 IDA-H6610 Loan Disb 46,035.18
Apr 15, 2016 IDA-49050 Int Charges 153.81
Apr 15, 2016 IDA-49050 Int Charges 153.81
Apr 15, 2016 IDA-49050 Int Charges 14,395.32
Apr 15, 2016 IDA-49050 Int Charges 14,395.32
Mar 14, 2016 IDA-H6610 Loan Disb 289,351.47
Oct 8, 2015 IDA-H6610 Loan Disb 131,334.20
Oct 8, 2015 IDA-49050 Loan Disb 160,519.56
Oct 15, 2015 IDA-49050 Int Charges 345.53
Oct 15, 2015 IDA-49050 Int Charges 345.53
Oct 15, 2015 IDA-49050 Int Charges 12,590.70
Oct 15, 2015 IDA-49050 Int Charges 12,590.70
Apr 15, 2015 IDA-49050 Int Charges 10,987.06
Apr 15, 2015 IDA-49050 Int Charges 10,987.06
Apr 15, 2015 IDA-49050 Int Charges 301.51
Apr 15, 2015 IDA-49050 Int Charges 301.51
May 15, 2015 IDA-H6610 Loan Disb 309,914.80
Jul 23, 2015 IDA-49050 Loan Disb 222,652.36
Jul 23, 2015 IDA-49050 Loan Disb 149,702.19
Jul 23, 2015 IDA-H6610 Loan Disb 295,772.00
May 15, 2015 IDA-49050 Loan Disb 117,256.33
Jul 23, 2015 IDA-H6610 Loan Disb 182,170.11
Apr 10, 2015 IDA-49050 Loan Disb 66,832.95
Feb 5, 2015 IDA-H6610 Loan Disb 178,319.40
Feb 5, 2015 IDA-49050 Loan Disb 37,271.09
Mar 2, 2015 IDA-H6610 Loan Disb 58,180.86
Oct 15, 2019 IDA-49050 Int Charges 44.25
Oct 15, 2019 IDA-49050 Int Charges 15,454.60
Oct 15, 2019 IDA-49050 Int Charges 15,454.60
Oct 15, 2021 IDA-49050 Loan Repay 42,312.41
Oct 15, 2021 IDA-49050 Int Charges 15,918.55
Oct 15, 2021 IDA-49050 Int Charges 15,918.55
Oct 15, 2021 IDA-49050 Loan Repay 137.16
Mar 19, 2015 IDA-H6610 Loan Disb 182,446.00
Dec 29, 2014 IDA-H6610 Loan Disb 124,002.71
Oct 15, 2017 IDA-49050 Int Charges 15,989.01
Apr 15, 2017 IDA-49050 Int Charges 15,234.22
Apr 15, 2017 IDA-49050 Int Charges 15,234.22
Apr 15, 2017 IDA-49050 Int Charges 190.07
Apr 15, 2017 IDA-49050 Int Charges 190.07
Oct 15, 2016 IDA-49050 Int Charges 172.62
Oct 15, 2016 IDA-49050 Int Charges 172.62
Oct 15, 2016 IDA-49050 Int Charges 15,305.72
Oct 15, 2016 IDA-49050 Int Charges 15,305.72
Jun 28, 2016 IDA-49050 Loan Disb 149,505.19
Jun 28, 2016 IDA-H6610 Loan Disb 355,581.80
Jun 28, 2016 IDA-H6610 Loan Disb 412,502.30
Oct 15, 2023 IDA-49050 Int Charges 682.39
Oct 15, 2023 IDA-49050 Loan Repay 39,384.04
Oct 15, 2023 IDA-49050 Int Charges 14,178.26
Oct 15, 2023 IDA-49050 Int Charges 14,178.26
Apr 15, 2023 IDA-49050 Loan Repay 1,804.54
Jun 28, 2016 IDA-49050 Loan Disb 147,888.36
Jul 21, 2016 IDA-H6610 Loan Cancel 1,278,991.40
Jul 21, 2016 IDA-49050 Loan Cancel 2,162,378.50
Feb 16, 2016 IDA-49050 Loan Disb 144,360.94
Apr 15, 2018 IDA-49050 Int Charges 87.11
Apr 15, 2021 IDA-49050 Int Charges 21.00
Apr 15, 2021 IDA-49050 Int Charges 21.00
Apr 15, 2021 IDA-49050 Int Charges 16,107.06
Apr 15, 2021 IDA-49050 Int Charges 16,107.06
Apr 15, 2023 IDA-49050 Loan Repay 38,922.55
Apr 15, 2023 IDA-49050 Int Charges 14,108.81
Apr 15, 2023 IDA-49050 Int Charges 14,108.81
Oct 15, 2022 IDA-49050 Loan Repay 36,959.36
Oct 15, 2022 IDA-49050 Int Charges 14,104.38
Oct 15, 2022 IDA-49050 Int Charges 14,104.38
Oct 15, 2022 IDA-49050 Loan Repay 1,419.88
Apr 15, 2022 IDA-49050 Loan Repay 40,732.02
Apr 15, 2022 IDA-49050 Int Charges 15,251.76
Apr 15, 2022 IDA-49050 Int Charges 15,251.76
Apr 15, 2022 IDA-49050 Loan Repay 350.15
May 10, 2011 IDA-H6610 Loan Commitment 11,250,000.00
May 10, 2011 IDA-49050 Loan Commitment 13,750,000.00
Apr 15, 2024 IDA-49050 Loan Repay 38,649.12
Apr 15, 2024 IDA-49050 Int Charges 14,099.67
Apr 15, 2024 IDA-49050 Int Charges 14,099.67
Apr 15, 2024 IDA-49050 Loan Repay 928.84
Oct 15, 2023 IDA-49050 Int Charges 682.39
Dec 29, 2014 IDA-49050 Loan Disb 37,111.42
Jun 18, 2014 IDA-49050 Loan Disb 32,126.83
Jun 18, 2014 IDA-49050 Loan Disb 236,428.64
Jun 18, 2014 IDA-H6610 Loan Disb 193,441.61
Apr 30, 2014 IDA-49050 Int Charges 8,577.86
Apr 30, 2014 IDA-49050 Int Charges 8,577.86
Mar 7, 2014 IDA-H6610 Loan Disb 41,232.65
Mar 13, 2014 IDA-49050 Loan Disb 5,523.84
Mar 13, 2014 IDA-H6610 Loan Disb 198,611.55
Mar 13, 2014 IDA-49050 Loan Disb 242,747.47
Mar 6, 2014 IDA-49050 Loan Disb 2,471.91
Mar 13, 2014 IDA-H6610 Loan Disb 47,078.59
Sep 29, 2013 IDA-49050 Loan Cancel 6,425,091.50
Nov 10, 2013 IDA-H6610 Loan Disb -2,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Satisfactory 2016-12-22
Project Management Moderately Satisfactory 2016-12-22
Monitoring and Evaluation Moderately Satisfactory 2016-12-22
Counterpart Funding Satisfactory 2016-12-22
Progress towards achievement of PDO Moderately Satisfactory 2016-12-22
Procurement Moderately Satisfactory 2016-12-22
Financial Management Moderately Satisfactory 2016-12-22

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 08-08-2017
OutcomesModerately Satisfactory
Risk to Development OutcomeSubstantial
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Unsatisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-24-2017PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSubstantialN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately SatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately SatisfactoryN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Total number of people benefited from urban services and infrastructure improvements, of which females and from disadvantaged groups.Value0.00124224.0092000.00
    DateOctober 3, 2011November 18, 2016January 31, 2017
    Comment
  • Number of participating municipalities with funded investment and O&M PlansValue0.006.006.00
    DateJune 3, 2013November 18, 2016January 31, 2017
    Comment
  • Municipal sub-projects under implementation with construction works on track as per the signed contractValue0.0076.7090.00
    DateJune 3, 2013November 18, 2016January 31, 2017
    Comment
  • Increase in municipal own source revenues in the participating municipalities.Value15.0040.2025.00
    DateOctober 3, 2011November 18, 2016January 31, 2017
    Comment
  • Total number of female beneficiariesValue0.0044.1010.00
    DateOctober 3, 2011November 18, 2016January 31, 2017
    Comment
  • Total number of beneficiaries from disadvantage groupsValue0.0049.6010.00
    DateOctober 3, 2011November 18, 2016January 31, 2017
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Municipal grant allocated to programs targeting women, children and disadvantaged groupsValue0.0034.9735.00
    DateOctober 3, 2011November 18, 2016January 31, 2017
    Comment
  • Number of municipalities submitting satisfactory annual plans for the municipal block grants to the MoUD by August 15 (one month after the start of the Fiscal Year)Value0.006.006.00
    DateJune 3, 2013November 18, 2016January 31, 2017
    Comment
  • Number municipalities submitting satisfactory annual progress reports to MoUD for the municipal block grants by September15 (two months after the end of the Fiscal Year)Value0.006.006.00
    DateJune 3, 2013November 18, 2016January 31, 2017
    Comment
  • Number of municipal infrastructure sub-projects successfully appraised and ready for bidding (i.e. bidding notice published)Value0.0015.0018.00
    DateOctober 3, 2011November 18, 2016January 31, 2017
    Comment
  • Percentage of funds for municipal sub-projects disbursed.Value0.0060.92100.00
    DateOctober 3, 2011November 18, 2016January 31, 2017
    Comment
  • TDF’s collection ratio meet prescribed thresholdsValue75.00100.0090.00
    DateOctober 3, 2011November 18, 2016January 31, 2017
    Comment
  • Standard project appraisal systems established and applied to all ETP sub-projects.ValueNoYesYes
    DateOctober 2, 2011November 18, 2016January 31, 2017
    Comment
  • Number of municipalities that have developed and approved planning norms and building byelaws based on the guidelines by MoUDValue0.006.006.00
    DateOctober 3, 2011November 18, 2016January 31, 2017
    Comment
  • Policy guidelines and procedures for municipalities on governance and budget planning updated and implemented by MoFALDValueNoYesYes (implemented)
    DateOctober 3, 2011November 18, 2016January 31, 2017
    Comment
  • Policy guidelines and procedures for municipalities on physical planning and infrastructure development developed/updated and implemented by MoUDValueNoYes (developed)Yes (implemented)
    DateOctober 3, 2011November 18, 2016January 31, 2017
    Comment