AF On-Farm Water Management (OFWM)

Development Objective

The PDO of the project is to improve agricultural productivity in project areas by enhancing the efficiency of water used.

Key Details

Project Details

  • P120398

  • Closed

  • Amanullah Alamzai

  • Islamic Republic of Afghanistan,MAIL

  • Afghanistan

  • April 27, 2010

  • (as of board presentation)

    February 16, 2011

  • March 16, 2011

  • US$ 25.00 million

  • MAIL

  • South Asia

  • 2011

  • US$ 25.00 million

  • B

  • March 8, 2022

  • December 31, 2019

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Afghanistan Resilience Trust Fund 25.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 25.00
Total Project Cost** 25.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2019-12-19
Project Management Satisfactory 2019-12-19
Progress towards achievement of PDO Satisfactory 2019-12-19
Monitoring and Evaluation Satisfactory 2019-12-19
Overall Implementation Progress (IP) Satisfactory 2019-12-19
Financial Management Moderately Satisfactory 2019-12-19

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 07-31-2020
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceModerately Satisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-22-2020PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceNot RatedN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Land productivityValue2.293.402.40
    DateMarch 16, 2011November 20, 2019December 31, 2019
    Comment
  • Water productivityValue0.630.840.76
    DateMarch 16, 2011December 31, 2019December 31, 2019
    Comment
  • Number of beneficiariesValue0.00120000.000.00
    DateJanuary 1, 2011December 31, 2019
    Comment
  • Area with improved irrigationValue0.0064000.000.00
    DateMarch 16, 2011December 31, 2019
    Comment
  • Number of Operational IAs established and StrengthenedValue0.00325.000.00
    DateJanuary 2, 2011December 31, 2019
    Comment
  • Improved agriculture productivity due to the conversion to the higher value crop due to improved irrigation servicesValue0.0031.700.00
    DateJanuary 1, 2011December 31, 2019
    Comment
  • Percentage of IAs expressing satisfaction with the project activitiesValue0.0097.000.00
    DateJanuary 1, 2011December 31, 2019
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Proportion of rehabilitated schemes obtaining at least satisfactory� rating from irrigation water usersValue0.0097.0080.00
    DateMarch 16, 2011December 31, 2019December 31, 2019
    Comment
  • Number of persons MAIL staff trained for water management and irrigated agricultureValue15.00350.000.00
    DateMarch 11, 2011November 20, 2019
    Comment
  • Number of farmers participating in irrigation demonstrationsValue0.003938.000.00
    DateMarch 16, 2011November 20, 2019
    Comment
  • Conveyance efficiency %Value40.0083.0065.00
    DateMarch 16, 2011July 7, 2020December 31, 2019
    Comment
  • Preparation of a draft Law on Irrigation and DrainageValue0.001.000.00
    DateDecember 16, 2015December 31, 2019
    Comment
  • Hectares of irrigation demonstration sites including land leveling and advanced irrigation technologyValue0.00408.00120.00
    DateMarch 16, 2011November 20, 2019December 31, 2019
    Comment
  • Decrease in conveyance duration (%)Value0.0064.0065.00
    DateMarch 16, 2011December 31, 2019December 31, 2019
    Comment
  • Recruitment of CBR based Staff in the IDValue0.0046.000.00
    DateDecember 16, 2015December 31, 2019
    Comment
  • Number of farmers’ information center built and operationalValue0.005.000.00
    DateDecember 16, 2015December 31, 2019
    Comment
  • Decrease in time to divert water to farmer's fieldValue0.0065.0065.00
    DateMarch 16, 2011December 31, 2019December 31, 2019
    Comment
  • Length of watercourse rehabilitatedValue0.00743.00138.00
    DateMarch 16, 2011December 31, 2019December 31, 2019
    Comment
  • Annual On Farm Job CreatedValue0.001937000.000.00
    DateJanuary 1, 2011December 31, 2019
    Comment