Financier | Commitments |
---|---|
West African Economic and Monetary Union | 4.00 |
IDA Grant | 12.70 |
Economic Community of West African States | 6.00 |
P120910
Closed
Leopold Sedogo
Government of Guinea Bissau
May 20, 2010
(as of board presentation)
July 23, 2010
December 6, 2010
US$ 22.70 million
Agência de Execução : UI-PMRI/PURSEA
2011
US$ 22.70 million
B
Not Applicable
June 30, 2015
BANK APPROVED
October 3, 2023
Financier | Commitments |
---|---|
West African Economic and Monetary Union | 4.00 |
IDA Grant | 12.70 |
Economic Community of West African States | 6.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 12.70 |
IBRD + IDA Commitment | 12.70 |
Lending Instrument | |
---|---|
Grant Amount | 10.00 |
Total Project Cost** | 22.70 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 3, 2014 | IDA-H6060 | Loan Disb | 27,145.71 |
Sep 6, 2013 | IDA-H6060 | Loan Disb | 190.76 |
Jan 14, 2015 | IDA-H6060 | Loan Disb | 99,415.06 |
Dec 8, 2014 | IDA-H6060 | Loan Disb | 51,896.82 |
Dec 8, 2014 | IDA-H6060 | Loan Disb | 74,775.02 |
Jul 28, 2014 | IDA-H6060 | Loan Disb | 31,022.95 |
Jul 28, 2014 | IDA-H6060 | Loan Disb | 36,489.79 |
Jan 28, 2015 | IDA-H6060 | Loan Disb | 92,258.15 |
Sep 2, 2014 | IDA-H6060 | Loan Disb | 35,817.50 |
Sep 12, 2014 | IDA-H6060 | Loan Disb | 61,592.07 |
Feb 19, 2016 | IDA-H6060 | Loan Cancel | 31.84 |
Jan 19, 2016 | IDA-H6060 | Loan Cancel | 209,478.40 |
Sep 16, 2015 | IDA-H6060 | Loan Disb | 162,200.40 |
Jul 23, 2010 | IDA-H6060 | Loan Commitment | 12,700,000.00 |
May 17, 2011 | IDA-H6890 | Loan Commitment | 2,200,000.00 |
Dec 29, 2015 | IDA-H6060 | Loan Disb | -95,894.25 |
Feb 19, 2016 | IDA-H6060 | Loan Disb | -31.84 |
Dec 15, 2014 | IDA-H6060 | Loan Disb | 286,062.80 |
Oct 20, 2014 | IDA-H6060 | Loan Disb | 58,986.90 |
Apr 10, 2014 | IDA-H6060 | Loan Disb | 171,261.67 |
May 22, 2014 | IDA-H6060 | Loan Disb | 297,519.75 |
May 13, 2014 | IDA-H6060 | Loan Disb | 20,119.88 |
Apr 9, 2014 | IDA-H6060 | Loan Disb | 29,607.04 |
Nov 12, 2013 | IDA-H6060 | Loan Disb | 19,536.61 |
Jan 23, 2014 | IDA-H6060 | Loan Disb | 24,072.23 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2015-06-29 |
Monitoring and Evaluation | Satisfactory | 2015-06-29 |
Progress towards achievement of PDO | Moderately Satisfactory | 2015-06-29 |
Procurement | Satisfactory | 2015-06-29 |
Project Management | Satisfactory | 2015-06-29 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2015-06-29 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 08-15-2018 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | High |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 01-24-2019 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Unsatisfactory | N/a |
Risk To Development Outcome | High | N/a |
Bank Performance | Moderately Unsatisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Unsatisfactory | N/a |
Implementing Agency | Moderately Satisfactory | N/a |
Icr Quality | Modest | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 115000.00 | 218700.00 | 140000.00 |
Date | December 31, 2009 | June 19, 2015 | June 30, 2015 | |
Comment |
Direct project beneficiaries | Value | 101300.00 | 81925.00 | 118500.00 |
Date | December 31, 2009 | June 19, 2015 | June 30, 2015 | |
Comment |
% of female beneficiaries | Value | 49.80 | 49.80 | 49.80 |
Date | December 31, 2009 | June 19, 2015 | June 30, 2015 | |
Comment |
% of female beneficiaries | Value | 49.80 | 49.80 | 49.80 |
Date | December 31, 2009 | June 19, 2015 | June 30, 2015 | |
Comment |
Annual public electricity supply to end-users | Value | 7.40 | 40.00 | 35.00 |
Date | December 31, 2009 | June 19, 2015 | June 30, 2015 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of EAGB operating cost covered by EAGB's cashflow | Value | 75.00 | 70.00 | 100.00 |
Date | December 31, 2009 | June 19, 2015 | June 30, 2015 | |
Comment |
Power generation capacity owned by EAGB through the project | Value | 3.00 | 8.00 | 8.00 |
Date | December 31, 2009 | June 19, 2015 | June 30, 2015 | |
Comment |
Collection rate of electricity bills | Value | 81.00 | 93.00 | 95.00 |
Date | December 31, 2009 | June 19, 2015 | June 30, 2015 | |
Comment |
Volume of water storage capacity | Value | 0.00 | 800.00 | 800.00 |
Date | December 31, 2009 | June 19, 2015 | June 30, 2015 | |
Comment |