Financier | Commitments |
---|---|
IDA Credit | 40.00 |
P121152
Closed
Enrique Pantoja , Ivonne Moreno Horta
Republic of Nicaragua
August 22, 2012
(as of board presentation)
March 26, 2013
July 12, 2013
US$ 40.00 million
Procuraduria General de la Republica (PGR)
2013
US$ 40.00 million
B
June 30, 2022
June 30, 2020
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 40.00 |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 40.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 15, 2020 | IDA-60870 | Int Charges | 127,395.11 |
Oct 15, 2020 | IDA-60870 | Int Charges | 127,395.11 |
Oct 15, 2020 | IDA-60870 | Int Charges | 119,595.41 |
Sep 1, 2020 | IDA-52250 | Int Charges | 836.33 |
Sep 1, 2020 | IDA-52250 | Int Charges | 836.33 |
Nov 29, 2018 | IDA-52250 | Loan Disb | 138,660.27 |
Oct 29, 2018 | IDA-52250 | Loan Disb | 647,671.00 |
Oct 26, 2018 | IDA-60870 | Loan Disb | 1,397,648.00 |
Apr 15, 2019 | IDA-52250 | Loan Disb | -52,729.88 |
Oct 15, 2018 | IDA-60870 | Int Charges | 14,700.00 |
Oct 15, 2018 | IDA-60870 | Int Charges | 14,700.00 |
Oct 15, 2018 | IDA-60870 | Int Charges | 13,800.00 |
Apr 15, 2019 | IDA-52250 | Loan Disb | -23,519.02 |
Mar 1, 2019 | IDA-52250 | Int Charges | 120,602.43 |
Mar 1, 2019 | IDA-52250 | Int Charges | 120,602.43 |
Mar 1, 2019 | IDA-52250 | Int Charges | 439.79 |
Mar 1, 2019 | IDA-52250 | Int Charges | 439.79 |
Apr 15, 2019 | IDA-60870 | Int Charges | 26,771.21 |
Apr 15, 2019 | IDA-60870 | Int Charges | 26,771.21 |
Apr 15, 2019 | IDA-60870 | Int Charges | 20,428.17 |
May 29, 2019 | IDA-60870 | Loan Disb | 1,737,978.40 |
Mar 14, 2019 | IDA-60870 | Loan Disb | 1,916,737.80 |
May 8, 2019 | IDA-52250 | Loan Cancel | 76,337.27 |
Oct 15, 2019 | IDA-60870 | Int Charges | 52,711.09 |
Dec 2, 2019 | IDA-60870 | Loan Disb | 230,570.89 |
Sep 1, 2019 | IDA-52250 | Int Charges | 119,900.14 |
Sep 1, 2019 | IDA-52250 | Int Charges | 119,900.14 |
Sep 1, 2019 | IDA-52250 | Int Charges | 315.13 |
Sep 1, 2019 | IDA-52250 | Int Charges | 315.13 |
Oct 27, 2017 | IDA-52250 | Loan Disb | 2,200,000.00 |
Sep 1, 2017 | IDA-52250 | Int Charges | 295.59 |
Sep 1, 2017 | IDA-52250 | Int Charges | 295.59 |
Sep 1, 2017 | IDA-52250 | Int Charges | 101,303.01 |
Sep 1, 2017 | IDA-52250 | Int Charges | 101,303.01 |
Mar 1, 2018 | IDA-52250 | Int Charges | 1,932.16 |
Mar 1, 2018 | IDA-52250 | Int Charges | 1,932.16 |
Mar 1, 2018 | IDA-52250 | Int Charges | 112,571.11 |
Mar 1, 2018 | IDA-52250 | Int Charges | 112,571.11 |
Apr 15, 2018 | IDA-60870 | Int Charges | 5,961.67 |
Sep 1, 2016 | IDA-52250 | Int Charges | 241.55 |
Sep 1, 2016 | IDA-52250 | Int Charges | 89,831.54 |
Sep 1, 2016 | IDA-52250 | Int Charges | 89,831.54 |
Apr 27, 2017 | IDA-52250 | Loan Disb | 2,500,000.00 |
Mar 1, 2017 | IDA-52250 | Int Charges | 34.84 |
Mar 1, 2017 | IDA-52250 | Int Charges | 34.84 |
Mar 1, 2017 | IDA-52250 | Int Charges | 91,505.57 |
Mar 1, 2017 | IDA-52250 | Int Charges | 91,505.57 |
Nov 6, 2017 | IDA-52250 | Loan Disb | 40,183.40 |
Jul 14, 2015 | IDA-52250 | Loan Disb | 5,674,739.00 |
Sep 1, 2015 | IDA-52250 | Int Charges | 3,292.80 |
Sep 1, 2015 | IDA-52250 | Int Charges | 3,292.80 |
Sep 1, 2015 | IDA-52250 | Int Charges | 66,590.38 |
Sep 1, 2015 | IDA-52250 | Int Charges | 66,590.38 |
Mar 1, 2016 | IDA-52250 | Int Charges | 5,775.67 |
Mar 1, 2016 | IDA-52250 | Int Charges | 5,775.67 |
Mar 1, 2016 | IDA-52250 | Int Charges | 86,703.29 |
Mar 1, 2016 | IDA-52250 | Int Charges | 86,703.29 |
Jun 30, 2016 | IDA-52250 | Loan Disb | 2,000,000.00 |
Aug 29, 2013 | IDA-52250 | Loan Disb | 2,000,000.00 |
Jul 12, 2013 | IDA-52250 | Loan Disb | 2,365,799.20 |
Mar 1, 2014 | IDA-52250 | Int Charges | 2,574.44 |
Mar 1, 2014 | IDA-52250 | Int Charges | 2,574.44 |
Mar 1, 2014 | IDA-52250 | Int Charges | 27,233.37 |
Mar 1, 2014 | IDA-52250 | Int Charges | 27,233.37 |
Dec 2, 2013 | IDA-52250 | Loan Disb | 5,648,147.50 |
Mar 24, 2014 | IDA-52250 | Loan Cancel | 4,000,000.00 |
Jan 7, 2015 | IDA-52250 | Loan Disb | 4,373,604.50 |
Jul 31, 2014 | IDA-52250 | Loan Disb | 4,632,843.50 |
Sep 1, 2014 | IDA-52250 | Int Charges | 140.56 |
Sep 1, 2014 | IDA-52250 | Int Charges | 140.56 |
Mar 1, 2015 | IDA-52250 | Int Charges | 2,061.25 |
Mar 1, 2015 | IDA-52250 | Int Charges | 2,061.25 |
Mar 1, 2015 | IDA-52250 | Int Charges | 52,256.42 |
Mar 1, 2015 | IDA-52250 | Int Charges | 52,256.42 |
Sep 1, 2014 | IDA-52250 | Int Charges | 38,218.66 |
Sep 1, 2014 | IDA-52250 | Int Charges | 38,218.66 |
Oct 15, 2019 | IDA-60870 | Int Charges | 56,613.76 |
Aug 8, 2019 | IDA-60870 | Loan Disb | 2,805,837.00 |
Mar 1, 2020 | IDA-52250 | Int Charges | 118,528.85 |
Mar 1, 2020 | IDA-52250 | Int Charges | 118,528.85 |
Mar 1, 2020 | IDA-52250 | Int Charges | 1,735.13 |
Mar 1, 2020 | IDA-52250 | Int Charges | 1,735.13 |
Sep 19, 2019 | IDA-60870 | Loan Disb | 212,070.12 |
Dec 2, 2019 | IDA-60870 | Loan Disb | 1,394,163.00 |
Mar 2, 2020 | IDA-60870 | Loan Disb | 4,010,000.00 |
Jun 5, 2020 | IDA-60870 | Loan Disb | 1,400,000.00 |
Apr 15, 2020 | IDA-60870 | Int Charges | 436.51 |
Apr 15, 2020 | IDA-60870 | Int Charges | 89,881.04 |
Apr 15, 2020 | IDA-60870 | Int Charges | 89,881.04 |
Apr 15, 2020 | IDA-60870 | Int Charges | 70,727.42 |
Jun 11, 2020 | IDA-60870 | Loan Disb | 894,994.80 |
Oct 15, 2020 | IDA-60870 | Int Charges | 13,650.71 |
Apr 15, 2018 | IDA-60870 | Int Charges | 5,961.67 |
Apr 15, 2018 | IDA-60870 | Int Charges | 5,596.67 |
Feb 2, 2018 | IDA-60870 | Loan Disb | 2,000,000.00 |
May 11, 2018 | IDA-52250 | Loan Disb | 1,800,000.00 |
Sep 1, 2018 | IDA-52250 | Int Charges | 117,459.45 |
Sep 1, 2018 | IDA-52250 | Int Charges | 117,459.45 |
Sep 1, 2018 | IDA-52250 | Int Charges | 1,519.65 |
Sep 1, 2018 | IDA-52250 | Int Charges | 1,519.65 |
Sep 1, 2016 | IDA-52250 | Int Charges | 241.55 |
Mar 1, 2024 | IDA-52250 | Loan Repay | 16.07 |
Jun 14, 2017 | IDA-60870 | Loan Commitment | 18,000,000.00 |
Mar 26, 2013 | IDA-52250 | Loan Commitment | 40,000,000.00 |
Mar 1, 2023 | IDA-52250 | Int Charges | 114,096.99 |
Mar 1, 2023 | IDA-52250 | Int Charges | 114,096.99 |
Mar 1, 2023 | IDA-52250 | Int Charges | 2,450.35 |
Mar 1, 2023 | IDA-52250 | Int Charges | 2,450.35 |
Apr 15, 2023 | IDA-60870 | Loan Repay | 292,727.88 |
Apr 15, 2023 | IDA-60870 | Int Charges | 128,245.42 |
Apr 15, 2023 | IDA-60870 | Int Charges | 128,245.42 |
Sep 1, 2023 | IDA-52250 | Int Charges | 264.58 |
Sep 1, 2023 | IDA-52250 | Int Charges | 264.58 |
Sep 1, 2023 | IDA-52250 | Loan Repay | 310,601.38 |
Sep 1, 2023 | IDA-52250 | Int Charges | 116,475.52 |
Sep 1, 2023 | IDA-52250 | Int Charges | 116,475.52 |
Oct 15, 2023 | IDA-60870 | Loan Repay | 114,871.77 |
Oct 15, 2023 | IDA-60870 | Loan Repay | 177,856.12 |
Oct 15, 2023 | IDA-60870 | Int Charges | 126,093.88 |
Oct 15, 2023 | IDA-60870 | Int Charges | 126,093.88 |
Oct 15, 2023 | IDA-60870 | Int Charges | 118,373.82 |
Apr 15, 2024 | IDA-60870 | Loan Repay | 292,727.88 |
Apr 15, 2024 | IDA-60870 | Int Charges | 123,942.32 |
Apr 15, 2024 | IDA-60870 | Int Charges | 123,942.32 |
Apr 15, 2024 | IDA-60870 | Int Charges | 116,354.04 |
Mar 1, 2024 | IDA-52250 | Loan Repay | 309,798.30 |
Mar 1, 2024 | IDA-52250 | Int Charges | 115,018.57 |
Mar 1, 2024 | IDA-52250 | Int Charges | 115,018.57 |
Apr 15, 2022 | IDA-60870 | Int Charges | 130,396.98 |
Apr 15, 2022 | IDA-60870 | Int Charges | 130,396.98 |
Apr 15, 2022 | IDA-60870 | Int Charges | 122,413.50 |
Mar 1, 2022 | IDA-52250 | Int Charges | 60.43 |
Mar 1, 2022 | IDA-52250 | Int Charges | 60.43 |
Mar 1, 2022 | IDA-52250 | Int Charges | 122,082.89 |
Mar 1, 2022 | IDA-52250 | Int Charges | 122,082.89 |
Oct 15, 2022 | IDA-60870 | Loan Repay | 292,727.88 |
Oct 15, 2022 | IDA-60870 | Int Charges | 130,396.98 |
Oct 15, 2022 | IDA-60870 | Int Charges | 130,396.98 |
Oct 15, 2022 | IDA-60870 | Int Charges | 122,413.50 |
Sep 1, 2022 | IDA-52250 | Int Charges | 113,589.07 |
Sep 1, 2022 | IDA-52250 | Int Charges | 113,589.07 |
Sep 1, 2022 | IDA-52250 | Int Charges | 424.74 |
Sep 1, 2022 | IDA-52250 | Int Charges | 424.74 |
Apr 15, 2023 | IDA-60870 | Int Charges | 120,393.66 |
Sep 1, 2020 | IDA-52250 | Int Charges | 119,759.54 |
Sep 1, 2020 | IDA-52250 | Int Charges | 119,759.54 |
Mar 1, 2021 | IDA-52250 | Int Charges | 4,107.24 |
Mar 1, 2021 | IDA-52250 | Int Charges | 125,818.82 |
Mar 1, 2021 | IDA-52250 | Int Charges | 125,818.82 |
Mar 1, 2021 | IDA-52250 | Int Charges | 4,107.24 |
Dec 9, 2020 | IDA-60870 | Loan Disb | -706.21 |
Dec 9, 2020 | IDA-60870 | Loan Disb | -258,209.27 |
Dec 9, 2020 | IDA-60870 | Loan Cancel | 258,915.48 |
Sep 1, 2021 | IDA-52250 | Int Charges | 124,317.25 |
Sep 1, 2021 | IDA-52250 | Int Charges | 124,317.25 |
Oct 15, 2021 | IDA-60870 | Int Charges | 130,396.98 |
Oct 15, 2021 | IDA-60870 | Int Charges | 130,396.98 |
Oct 15, 2021 | IDA-60870 | Int Charges | 122,413.50 |
Sep 1, 2021 | IDA-52250 | Int Charges | 321.94 |
Sep 1, 2021 | IDA-52250 | Int Charges | 321.94 |
Apr 15, 2021 | IDA-60870 | Int Charges | 130,967.89 |
Apr 15, 2021 | IDA-60870 | Int Charges | 130,967.89 |
Apr 15, 2021 | IDA-60870 | Int Charges | 122,949.45 |
Oct 15, 2019 | IDA-60870 | Int Charges | 4,703.99 |
Oct 15, 2019 | IDA-60870 | Int Charges | 56,613.76 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2019-10-11 |
Overall Implementation Progress (IP) | Satisfactory | 2019-10-11 |
Procurement | Satisfactory | 2019-10-11 |
Progress towards achievement of PDO | Satisfactory | 2019-10-11 |
Monitoring and Evaluation | Satisfactory | 2019-10-11 |
Project Management | Satisfactory | 2019-10-11 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-19-2021 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 05-04-2021 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | High | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Direct project beneficiaries | Value | 0.00 | 952814.00 | 1016000.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
Time to disburse funds requested by Government for an eligible emergency | Value | 0.00 | 1.00 | 4.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
Female beneficiaries | Value | 0.00 | 50.00 | 0.00 |
Date | November 30, 2012 | December 31, 2017 | ||
Comment |
Number of households receiving legal documents through the Project | Value | 0.00 | 120965.00 | 118900.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
of which new titles | Value | 0.00 | 92022.00 | 84800.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
of which 50% benefit women or couples jointly | Value | 0.00 | 53.00 | 0.00 |
Date | November 30, 2012 | |||
Comment |
SIICAR is evaluated independently as satisfactory in terms of operation, data and security | Value | No | Yes | Yes |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
Avg no. of days to complete recording of purchase/sale of property in land adm systm | Value | 50.00 | 18.00 | 25.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Land parcels with use or ownership rights recorded as a result of the project | Value | 0.00 | 229699.00 | 187400.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
Baseline for project impact evaluation, Mid-term Report, and Final Evaluation Report completed in a timely and satisfactory manner | Value | 0.00 | 2.00 | 2.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
CERC established and ready to provide access to financial resources to Nicaragua in case of an eligible emergency | Value | No | Yes | Yes |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
SIICAR is redesigned satisfactorily in terms of operations security, business objectives, and policies and procedures | Value | 1.00 | 95.00 | 100.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
Technical acceditations issued by INETER to staff of municipalities | Value | 0.00 | 24.00 | 0.00 |
Date | February 15, 2016 | June 30, 2020 | ||
Comment |
Land parcels with use/ownership rights recorded as a result of project-female | Value | 0.00 | 95678.00 | 74960.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
Establishment of SISCAT (municipal cadasre)-SISCAF (national cadastre) link | Value | 0.00 | 15.00 | 0.00 |
Date | February 15, 2016 | June 30, 2020 | ||
Comment |
Households with surveyed parcels report a substantial improvement in land tenure security | Value | 0.00 | 100.00 | 70.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
The database of fiscal cadastre is increased by participating municipalities | Value | 0.00 | 170.37 | 35.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
Grievances registered related to delivery of project benefits addressed (%) | Value | 0.00 | 100.00 | 98.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
Conflict resolution agreements, pre-qualified as registrable, are formalized in the Property Registry | Value | 0.00 | 72.00 | 70.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
Grievances related to delivery of project benefits that are addressed-(number) | Value | 0.00 | 1116.00 | 0.00 |
Date | November 30, 2012 | December 31, 2017 | ||
Comment |
Complementary areas in the indigenous territories in the Special Development Zone of Bosawas are demarcated and titled | Value | 0.00 | 2.00 | 2.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
Protected areas are demarcated and registered in the database of the National System of Protected Areas | Value | 0.00 | 5.00 | 5.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |
Comment |
SIICAR is implemented on a pilot basis to incorporate the registry & cadastral data of the Dept. of Esteli | Value | 0.00 | 15.00 | 0.00 |
Date | April 21, 2017 | June 30, 2020 | ||
Comment |
SIICAR is implemented on a pilot basis to incorporate the registry & cadastral data of the Dept. of Managua | Value | 0.00 | 51.00 | 50.00 |
Date | February 15, 2016 | June 30, 2020 | June 26, 2017 | |
Comment |
Reduction in number of days to issue a cadastral certificate | Value | 12.00 | 7.00 | 6.00 |
Date | November 1, 2013 | June 30, 2020 | June 26, 2017 | |