Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 4.80 |
Borrower/Recipient | 20.25 |
P121263
Closed
Binyam Reja
International Department, Ministry of Finance
June 18, 2010
(as of board presentation)
March 29, 2012
June 20, 2012
US$ 25.05 million
Ministry of Transport
2012
US$ 4.80 million
B
Not Applicable
June 30, 2016
BANK APPROVED
July 15, 2021
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 4.80 |
Borrower/Recipient | 20.25 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 4.80 |
Total Project Cost** | 25.05 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2016-06-27 |
Project Management | Moderately Satisfactory | 2016-06-27 |
Overall Implementation Progress (IP) | Satisfactory | 2016-06-27 |
Procurement | Moderately Satisfactory | 2016-06-27 |
Summary Global Objective Rating | Satisfactory | 2016-06-27 |
Financial Management | Satisfactory | 2016-06-27 |
Monitoring and Evaluation | Satisfactory | 2016-06-27 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-26-2016 |
---|---|
Outcomes | Substantial |
Risk to Development Outcome | Modest |
Bank Performance | Substantial |
Borrower Performance | Substantial |
Government Performance | Substantial |
Implementing Agency | Substantial |
INDICATOR | ICR REVIEW: 05-26-2017 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | Modest | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Satisfactory | N/a |
Government Performance | Satisfactory | N/a |
Implementing Agency | Satisfactory | N/a |
Icr Quality | Modest | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Eco-transport development strategies for city clusters proposed | Value | Not yet proposed | Completed | Completed |
Date | May 31, 2012 | June 2, 2016 | June 30, 2016 | |
Comment |
Technical guidelines for integrated eco-transport planning for city clusters prepared | Value | Not yet available | Completed | Completed |
Date | May 31, 2012 | June 2, 2016 | June 30, 2016 | |
Comment |
Integrated eco-transport strategic planning guidelines developed and adopted by MOT | Value | Noy yet exist | Endorsement by MOT | Endorsement by MOT |
Date | May 31, 2012 | June 2, 2016 | June 30, 2016 | |
Comment |
Annual transport CO2 emissions of local trips via the two project terminals at least 5% lower than BAU scenario | Value | 0.00 | 49.00 | 5.00 |
Date | May 31, 2012 | June 2, 2016 | June 30, 2016 | |
Comment |
Level of passenger satisfaction for the use of multi-modal terminals for pilot demonstration reported as higher than similar facilities around the country | Value | Not yet available | Lituo Terminal: satisfaction level: 4.3 Western C | Not established at appraisal |
Date | May 31, 2012 | June 20, 2016 | June 30, 2016 | |
Comment |
M&E methodologies established and used for measuring energy savings and CO2 emission reduction | Value | Not yet created | Completed and used | Completed and used |
Date | May 31, 2012 | June 2, 2016 | June 30, 2016 | |
Comment |
CZT Comprehensive Transport Integration Implementation Plan prepared | Value | Not yet prepared | Completed | Completed |
Date | May 31, 2012 | June 2, 2016 | June 30, 2016 | |
Comment |
Two multi-modal passenger terminals completed as technical specifications | Value | Not yet built | Completed | Completed |
Date | May 31, 2012 | June 2, 2016 | June 30, 2016 | |
Comment |
A website for city cluster eco-transport development and demonstration established and functioning | Value | Not yet established | Website completed. | Functional |
Date | May 31, 2012 | June 2, 2016 | June 30, 2016 | |
Comment |
At least 5 national workshops for eco-transport knowledge exchange and experience dissemination held | Value | 0 | 10 | 5 |
Date | May 31, 2012 | June 2, 2016 | June 30, 2016 | |
Comment |
At least 150 central and local government officials, planners and designers trained for integrated transport policy, planning and design | Value | 0 | 735 | 150 |
Date | May 31, 2012 | December 3, 2015 | June 30, 2016 | |
Comment |
Chengdu-Chongqing (ChengYu) City Cluster Integrated Transport Plan prepared | Value | Not Yet available | Completion of the Study | Completion of the Study |
Date | December 12, 2014 | June 2, 2016 | June 30, 2016 | |
Comment |
Beijing-Tianjin-Hebei (JingJinJi) City Cluster Transport Integration Plan prepared | Value | Not Yet available | Completion of the Study | Completion of the Study |
Date | December 12, 2014 | June 2, 2016 | June 30, 2016 | |
Comment |