Skip to Main Navigation

Pakistan: Khyber Pakhtunkhwa (KP) and Federally Administered Tribal Areas (FATA) Emergency Recovery Project

Development Objective

To support the Government of Pakistan, and specifically the Khyber Pakhtunkhwa (KP) province and Federally Administered Tribal Areas (FATA), in their recovery efforts through (a) providing safety net support grants to poor and vulnerable households affected by the militancy crisis in the target areas; (b) providing conditional cash transfers (CCTs) for human development to poor and vulnerable households in the target areas; and (c) strengthening necessary capacities and systems for post-disaster safety nets.

Key Details

Project Details

  • P121394

  • Closed

  • Cem Mete

  • N/A

  • Pakistan

  • October 15, 2010

  • (as of board presentation)

    January 20, 2011

  • N/A

  • US$ 285.00 million

  • N/A

  • South Asia

  • 2011

  • US$ 285.00 million

  • C

  • Not Applicable

  • October 16, 2011

  • BANK APPROVED

  • January 15, 2013

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 250.00
MDTF for Crisi Affected Areas of NWFP/FATA/Balochistan 35.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 250.00
IBRD + IDA Commitment 250.00
Lending Instrument
Grant Amount 35.00
Total Project Cost** 285.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jan 20, 2011 IDA-48360 Loan Commitment 250,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Moderately Unsatisfactory 2011-09-21
Counterpart Funding Satisfactory 2011-09-21
Monitoring and Evaluation Satisfactory 2011-09-21
Procurement Satisfactory 2011-09-21
Project Management Satisfactory 2011-09-21
Financial Management Satisfactory 2011-09-21
Progress towards achievement of PDO Moderately Unsatisfactory 2011-09-21
Overall High 2011-09-21

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 11-09-2012PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingNot Rated N/a
Risk To Development OutcomeNot RatedN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceUnsatisfactoryN/a
Government PerformanceUnsatisfactoryN/a
Implementing AgencyUnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.000.00250000.00
    DateSeptember 7, 2011September 7, 2011January 1, 2015
    Comment
  • At least 70% of beneficiary households are in bottom 2 quintiles of the household consumption distributionValue0.000.0070.00
    DateSeptember 7, 2011September 7, 2011January 1, 2015
    Comment
  • At least 50% of households signed up for education CCT show increase in primary school enrolmentValue0.000.0050.00
    DateSeptember 7, 2011September 7, 2011January 1, 2015
    Comment
  • Institutional arrangements along with a Management Information System are in place to coordinate post-disaster safety nets in at least 5 districts of KP and 2 tribal areas of FATAValueInstitutional arrangements and MIS not in placeInstitutional arrangements are in place but not thBoth institutional arrangements and MIS are in pla
    DateSeptember 7, 2011September 7, 2011December 22, 2011
    Comment
  • Female beneficiariesValue0.000.000.00
    DateSeptember 7, 2011September 7, 2011January 1, 2015
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Component 1. At least 50% of the households in the affected Union Councils have completed the targeting forms.Value0.000.000.00
    DateSeptember 7, 2011September 7, 2011December 22, 2011
    Comment
  • At least 75% of the eligible household head with CNICs are receiving the cash assistance.Value0.000.0075.00
    DateSeptember 7, 2011September 7, 2011December 22, 2012
    Comment
  • At least 50% of grievances attended to within 45 days.Value0.000.0050.00
    DateSeptember 7, 2011September 7, 2011January 1, 2015
    Comment
  • At least 60% of beneficiaries express satisfaction with the cash transfer process.Value0.000.0050.00
    DateSeptember 7, 2011September 7, 2011January 1, 2015
    Comment
  • Component 2. At least 75% of primary schools in the project area linked to the human development cash grant program, through regular submission of children#s attendance recordsValue0.000.0075.00
    DateSeptember 7, 2011September 7, 2011January 1, 2015
    Comment
  • At least 60% CCT program beneficiaries are satisfied with the cash assistance.Value0.000.0060.00
    DateSeptember 7, 2011September 7, 2011January 1, 2015
    Comment
  • Component 3. At least 7 data resource centers are functional to support administration of the cash grants program and providing information to the design of other long term rehabilitation programsValueData resource centers are not functional.Data resource centers are not functional.At least 7 data resource centers are functional.
    DateSeptember 7, 2011September 7, 2011January 2, 2012
    Comment