Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 300.00 |
P121495
Closed
Carlos Bellas Lamas , Eric Lancelot
State of Tocantins
August 19, 2010
(as of board presentation)
July 26, 2012
February 14, 2013
US$ 300.00 million
SEPLAN
2013
US$ 300.00 million
B
Not Applicable
December 31, 2021
Yes
BANK APPROVED
November 1, 2023
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 300.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 300.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 300.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 300.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 9, 2021 | IBRD-81850 | Loan Disb | 4,372,267.50 |
Mar 31, 2022 | IBRD-81850 | Loan Disb | 4,613,586.00 |
Jun 3, 2022 | IBRD-81850 | Loan Disb | -1,049,708.10 |
May 15, 2022 | IBRD-81850 | Int Charges | 163.65 |
May 15, 2022 | IBRD-81850 | Int Charges | 980,152.25 |
May 15, 2022 | IBRD-81850 | Loan Repay | 7,657,897.50 |
May 15, 2022 | IBRD-81850 | Int Charges | 7,093.96 |
Jun 3, 2022 | IBRD-81850 | Loan Cancel | 8,975,342.00 |
Feb 9, 2022 | IBRD-81850 | Loan Disb | 3,727,244.00 |
Dec 27, 2021 | IBRD-81850 | Loan Disb | 4,527,009.50 |
Nov 15, 2022 | IBRD-81850 | Int Charges | 4,959.60 |
Nov 15, 2022 | IBRD-81850 | Int Charges | 3,486,743.80 |
Nov 15, 2022 | IBRD-81850 | Loan Repay | 7,780,479.50 |
May 15, 2023 | IBRD-81850 | Loan Repay | 7,780,479.50 |
May 15, 2023 | IBRD-81850 | Int Charges | 317,089.30 |
May 15, 2023 | IBRD-81850 | Int Charges | 5,533,838.50 |
Nov 15, 2023 | IBRD-81850 | Int Charges | 130,780.78 |
Nov 15, 2023 | IBRD-81850 | Int Charges | 6,432,917.00 |
Nov 15, 2023 | IBRD-81850 | Loan Repay | 7,780,479.50 |
May 15, 2024 | IBRD-81850 | Loan Repay | 7,780,479.50 |
May 15, 2024 | IBRD-81850 | Int Charges | 41,510.00 |
May 15, 2024 | IBRD-81850 | Int Charges | 6,509,190.00 |
May 15, 2024 | IBRD-81850 | Int Charges | 41,510.00 |
Jul 26, 2012 | IBRD-81850 | Loan Commitment | 300,000,000.00 |
Nov 29, 2018 | IBRD-81850 | Loan Disb | 5,070,441.50 |
Jan 7, 2019 | IBRD-81850 | Loan Disb | 5,248,004.00 |
May 15, 2019 | IBRD-81850 | Int Charges | 30,829.91 |
May 15, 2019 | IBRD-81850 | Int Charges | 2,999,344.20 |
May 15, 2019 | IBRD-81850 | Loan Repay | 4,848,793.50 |
Aug 19, 2019 | IBRD-81850 | Loan Disb | 6,024,726.50 |
Jun 5, 2019 | IBRD-81850 | Loan Disb | 5,609,259.50 |
Nov 15, 2019 | IBRD-81850 | Int Charges | 2,923,861.50 |
Nov 15, 2019 | IBRD-81850 | Loan Repay | 5,301,970.00 |
Sep 12, 2019 | IBRD-81850 | Loan Disb | 4,266,947.00 |
Nov 14, 2019 | IBRD-81850 | Loan Disb | 6,065,065.50 |
Mar 11, 2020 | IBRD-81850 | Loan Disb | 3,009,436.80 |
Jan 31, 2020 | IBRD-81850 | Loan Disb | 5,680,135.50 |
May 28, 2020 | IBRD-81850 | Loan Disb | 2,979,757.80 |
May 15, 2020 | IBRD-81850 | Int Charges | 537.43 |
May 15, 2020 | IBRD-81850 | Int Charges | 2,423,815.00 |
May 15, 2020 | IBRD-81850 | Loan Repay | 5,735,756.50 |
Jun 25, 2020 | IBRD-81850 | Loan Disb | 4,954,873.50 |
Aug 25, 2020 | IBRD-81850 | Loan Disb | 3,464,135.50 |
Oct 9, 2020 | IBRD-81850 | Loan Disb | 3,802,035.20 |
Nov 20, 2020 | IBRD-81850 | Loan Disb | 4,380,537.00 |
Dec 23, 2020 | IBRD-81850 | Loan Cancel | 10,000,000.00 |
Feb 4, 2021 | IBRD-81850 | Loan Disb | 2,951,458.00 |
Nov 15, 2020 | IBRD-81850 | Int Charges | 1,283,787.10 |
Nov 15, 2020 | IBRD-81850 | Loan Repay | 6,079,999.00 |
May 21, 2021 | IBRD-81850 | Loan Disb | 4,705,944.00 |
May 15, 2021 | IBRD-81850 | Int Charges | 4,962.71 |
May 15, 2021 | IBRD-81850 | Int Charges | 869,517.75 |
May 15, 2021 | IBRD-81850 | Int Charges | 4,962.71 |
May 15, 2021 | IBRD-81850 | Loan Repay | 6,427,381.00 |
Jul 15, 2021 | IBRD-81850 | Loan Disb | 3,882,912.20 |
Nov 16, 2021 | IBRD-81850 | Loan Repay | 6,850,612.00 |
Nov 19, 2021 | IBRD-81850 | Loan Disb | 4,053,518.50 |
Nov 3, 2021 | IBRD-81850 | Loan Disb | 2,965,096.80 |
May 13, 2016 | IBRD-81850 | Loan Disb | 4,109,401.20 |
May 15, 2016 | IBRD-81850 | Int Charges | 291,362.56 |
Jan 13, 2017 | IBRD-81850 | Loan Disb | 8,514,904.00 |
Sep 1, 2016 | IBRD-81850 | Loan Disb | 8,468,441.00 |
Nov 16, 2016 | IBRD-81850 | Int Charges | 239.72 |
Nov 16, 2016 | IBRD-81850 | Int Charges | 490,660.22 |
May 15, 2017 | IBRD-81850 | Int Charges | 14,046.75 |
May 15, 2017 | IBRD-81850 | Int Charges | 904,901.75 |
Mar 17, 2017 | IBRD-81850 | Loan Disb | 5,588,195.50 |
Oct 28, 2016 | IBRD-81850 | Loan Disb | 6,808,483.00 |
Dec 5, 2016 | IBRD-81850 | Loan Disb | 6,658,751.50 |
May 10, 2017 | IBRD-81850 | Loan Disb | 7,455,839.00 |
Jul 12, 2017 | IBRD-81850 | Loan Disb | 6,406,528.00 |
Aug 22, 2017 | IBRD-81850 | Loan Disb | 7,946,496.50 |
Oct 19, 2017 | IBRD-81850 | Loan Disb | 8,026,792.50 |
Nov 29, 2017 | IBRD-81850 | Loan Disb | 7,398,643.00 |
Jul 20, 2017 | IBRD-81850 | Loan Disb | 2,329,040.00 |
Sep 15, 2017 | IBRD-81850 | Loan Disb | 5,873,993.00 |
Nov 15, 2017 | IBRD-81850 | Loan Repay | 3,435,942.80 |
Nov 15, 2017 | IBRD-81850 | Int Charges | 18,043.33 |
Nov 15, 2017 | IBRD-81850 | Int Charges | 1,299,775.50 |
Nov 16, 2017 | IBRD-81850 | Loan Repay | 18,043.33 |
Jan 4, 2018 | IBRD-81850 | Loan Disb | 7,310,438.50 |
Sep 21, 2018 | IBRD-81850 | Loan Disb | 6,530,606.50 |
Jun 25, 2018 | IBRD-81850 | Loan Disb | 6,505,526.50 |
Nov 15, 2018 | IBRD-81850 | Int Charges | 2,541,569.20 |
Nov 15, 2018 | IBRD-81850 | Loan Repay | 4,382,075.00 |
May 15, 2018 | IBRD-81850 | Int Charges | 31,786.77 |
May 15, 2018 | IBRD-81850 | Int Charges | 1.09 |
May 15, 2018 | IBRD-81850 | Int Charges | 1,726,128.40 |
May 15, 2018 | IBRD-81850 | Loan Repay | 4,206,425.50 |
Nov 21, 2014 | IBRD-81850 | Loan Disb | 8,234,303.00 |
Oct 2, 2014 | IBRD-81850 | Loan Disb | 4,329,970.00 |
Nov 15, 2014 | IBRD-81850 | Int Charges | 55,931.00 |
Nov 18, 2013 | IBRD-81850 | Int Charges | 2,355.33 |
Nov 18, 2013 | IBRD-81850 | Int Charges | 23,146.36 |
May 23, 2014 | IBRD-81850 | Loan Disb | 2,737,479.20 |
May 15, 2014 | IBRD-81850 | Int Charges | 21,067.22 |
Aug 5, 2014 | IBRD-81850 | Loan Disb | 8,821,843.00 |
Mar 23, 2015 | IBRD-81850 | Loan Disb | 6,822,296.50 |
Aug 20, 2014 | IBRD-81850 | Loan Disb | 3,181,473.00 |
Sep 10, 2014 | IBRD-81850 | Loan Disb | 3,084,473.80 |
May 15, 2015 | IBRD-81850 | Int Charges | 3,651.61 |
May 15, 2015 | IBRD-81850 | Int Charges | 131,603.42 |
Nov 15, 2015 | IBRD-81850 | Int Charges | 7,332.08 |
Nov 15, 2015 | IBRD-81850 | Int Charges | 192,971.31 |
Aug 20, 2015 | IBRD-81850 | Loan Disb | 4,219,203.00 |
Dec 3, 2015 | IBRD-81850 | Loan Disb | 4,873,483.50 |
Jan 28, 2016 | IBRD-81850 | Loan Disb | 5,603,733.50 |
Oct 7, 2016 | IBRD-81850 | Loan Disb | 6,253,442.00 |
Jul 19, 2016 | IBRD-81850 | Loan Disb | 6,733,600.50 |
Sep 16, 2021 | IBRD-81850 | Loan Disb | 4,597,678.50 |
Aug 26, 2021 | IBRD-81850 | Loan Disb | 4,554,966.50 |
Nov 15, 2021 | IBRD-81850 | Int Charges | 875,066.56 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2021-12-22 |
Project Management | Moderately Satisfactory | 2021-12-22 |
Financial Management | Moderately Satisfactory | 2021-12-22 |
Progress towards achievement of PDO | Moderately Satisfactory | 2021-12-22 |
Monitoring and Evaluation | Moderately Satisfactory | 2021-12-22 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2021-12-22 |
Counterpart Funding | Satisfactory | 2021-12-22 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 06-30-2022 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 04-03-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Percentage of CREMA State road network in good condition | Value | 9.00 | 100.00 | 100.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Improved public services delivery as measured by substantial achievement of intermediate indicators of Component 2 | Value | 0.00 | 3.00 | 3.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Vehicle-km travelled on State paved roads under good condition | Value | 260000.00 | 5750000.00 | 2320000.00 |
Date | July 26, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Share of rural population with access to an all-season road | Value | 85.00 | 100.00 | 92.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Number of rural people with access to an all-season road | Value | 802733.00 | 96573100.00 | 0.00 |
Date | July 31, 2012 | November 2, 2017 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Extension of municipal roads with all-season accessibility | Value | 0.00 | 5500.00 | 5500.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Agencies with implemented results agreements between the secretaries and responsible units | Value | 0.00 | 5.00 | 5.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Producers which upgrade from subsistence farming to market farming in selected areas | Value | 0.00 | 150.00 | 120.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Average time to concession environmental licensing for complex State road activities with environmental impact | Value | 100.00 | 36.00 | 40.00 |
Date | July 31, 2012 | December 1, 2021 | December 31, 2021 | |
Comment |
Municipal Education Plans (with Early Childhood Education (ECE) component) agreed with municipalities | Value | 0.00 | 6.00 | 6.00 |
Date | July 31, 2012 | November 1, 2021 | December 30, 2021 | |
Comment |
Roads rehabilitated, Rural | Value | 0.00 | 2250.00 | 1500.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Cooperation agreements on rural road maintenance financing signed between the state and municipal government | Value | 0.00 | 0.00 | 111.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Concessioned and Operational Municipal Slaughterhouses built related to the project | Value | 0.00 | 0.00 | 7.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Instruments from the Brazilian Forestry code applied by the State of Tocantins | Value | 0.00 | 4.00 | 4.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Teachers in state system trained in 7 schools identified by the SoT | Value | 0.00 | 85.00 | 90.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Water management pilot projects implemented in the SoT priority river basins with committees | Value | 0.00 | 3.00 | 3.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |
Reduction of dropout rate in 7 pilot state schools identified by the the SoT | Value | 0.00 | 61.00 | 25.00 |
Date | July 31, 2012 | November 1, 2021 | December 31, 2021 | |
Comment |