Development Objective

The objective of the Project is to support the poorest rural municipalities in planning and implementing local development activities in a participatory and sustainable manner. The Project contributes to the second phase of the National Program for Decentralized Rural Development.The specific objectives of this grant are a) to build community capacity to actively engage in local service delivery outcomes (local empowerment); b) to strengthen transparency and social accountability mechanisms in health and education programs; c) to increase communication and collaboration among different stakeholders involved in providing health and education services; d) to help improve delivery of services at the decentralized level.

Key Details

Project Details

  • P121714

  • Closed

  • Serdar Yilmaz

  • N/A

  • Burkina Faso

  • March 4, 2010

  • (as of board presentation)

    March 4, 2010

  • July 10, 2010

  • US$ 1.48 million

  • Higher Institute of Population Studies

  • Western and Central Africa

  • 2010

  • US$ 1.48 million

  • C

  • Not Applicable

  • March 1, 2015

  • BANK APPROVED

  • June 3, 2016

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Japan Social Development Fund 1.48

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 1.48
Total Project Cost** 1.48

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2014-10-25
Progress towards achievement of PDO Satisfactory 2014-10-25
Procurement Satisfactory 2014-10-25
Financial Management Moderately Satisfactory 2014-10-25
Project Management Satisfactory 2014-10-25
Counterpart Funding Satisfactory 2014-10-25
Monitoring and Evaluation Satisfactory 2014-10-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Increase in participatory activitiesValue0.00100.00100.00
    DateJanuary 27, 2014June 30, 2014
    CommentThere is 100 percent increase in participatory activities.100 percent increase
  • Joint actionValue0.0050.0080.00
    DateJanuary 27, 2014June 30, 2014
    Comment50 percent increase in joint action by local stakeholders (including local government, service providers and service users) inthecommunes.80 percent increasein joint-actions takento improve servicedelivery
  • Decrease in absenteeismValue0.000.0050.00
    DateSeptember 30, 2014June 30, 2014
    CommentThe endline survey will be conducted after the project closes.50 % decrease inabsenteeism
  • Skills acquiredValue0.00100.0060.00
    DateJuly 2, 2014August 15, 2012
    CommentAll of the community members have received training by the NGOs.60% of community members receiving training
  • Institutional skillsValue0.0080.000.00
    DateJuly 16, 2014
    CommentCVD committees received training and started the implementation of monitoring activities.

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct project beneficiariesValue0.00250.00250.00
    DateJanuary 27, 2014June 30, 2014
    Comment
  • Female beneficiariesValue0.00125.00125.00
    DateJanuary 27, 2014June 30, 2014
    Comment