Financier | Commitments |
---|---|
IDA Grant | 50.00 |
P121755
Closed
Rajendra Singh
Ministry of Finance
March 29, 2011
(as of board presentation)
April 26, 2011
June 14, 2011
US$ 50.00 million
Ministry of Communications and IT (MCIT); Islamic Republic of Afghanistan; Kabul
2011
US$ 50.00 million
B
March 6, 2022
December 30, 2017
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 50.00 |
IBRD + IDA Commitment | 50.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 50.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Aug 15, 2017 | IDA-H6650 | Loan Disb | 495,764.22 |
Nov 27, 2017 | IDA-H6650 | Loan Disb | 75,825.50 |
Jun 28, 2016 | IDA-H6650 | Loan Disb | 184,390.62 |
Aug 8, 2016 | IDA-H6650 | Loan Disb | 245,118.16 |
Nov 4, 2016 | IDA-H6650 | Loan Disb | 122,785.64 |
Nov 14, 2016 | IDA-H6650 | Loan Disb | 482,431.06 |
Jun 28, 2016 | IDA-H6650 | Loan Disb | 689,577.94 |
Nov 14, 2016 | IDA-H6650 | Loan Disb | 499,331.16 |
Jul 5, 2016 | IDA-H6650 | Loan Disb | 496,485.03 |
May 11, 2016 | IDA-H6650 | Loan Disb | 313,644.88 |
Sep 7, 2016 | IDA-H6650 | Loan Disb | 224,400.25 |
Oct 3, 2016 | IDA-H6650 | Loan Disb | 349,358.62 |
Dec 28, 2016 | IDA-H6650 | Loan Disb | 272,899.20 |
Aug 15, 2016 | IDA-H6650 | Loan Disb | 532,650.60 |
Dec 28, 2016 | IDA-H6650 | Loan Disb | 263,322.30 |
Nov 2, 2016 | IDA-H6650 | Loan Disb | 389,929.10 |
Sep 2, 2014 | IDA-H6650 | Loan Disb | 276,662.80 |
Jul 20, 2015 | IDA-H6650 | Loan Disb | 86,606.08 |
Jun 1, 2015 | IDA-H6650 | Loan Disb | 765,322.60 |
Apr 20, 2015 | IDA-H6650 | Loan Disb | 53,634.70 |
May 18, 2015 | IDA-H6650 | Loan Disb | 136,237.73 |
May 26, 2015 | IDA-H6650 | Loan Disb | 101,846.49 |
Jun 29, 2015 | IDA-H6650 | Loan Disb | 239,195.73 |
Aug 12, 2015 | IDA-H6650 | Loan Disb | 158,427.69 |
Oct 5, 2015 | IDA-H6650 | Loan Disb | 646,560.25 |
Nov 30, 2015 | IDA-H6650 | Loan Disb | 197,450.28 |
Nov 23, 2015 | IDA-H6650 | Loan Disb | 221,975.16 |
Dec 16, 2015 | IDA-H6650 | Loan Disb | 221,426.06 |
Jan 4, 2016 | IDA-H6650 | Loan Disb | 153,646.23 |
Nov 23, 2015 | IDA-H6650 | Loan Disb | 15,679.55 |
Dec 14, 2015 | IDA-H6650 | Loan Disb | 106,667.23 |
Feb 1, 2016 | IDA-H6650 | Loan Disb | 151,698.55 |
Jan 11, 2016 | IDA-H6650 | Loan Disb | 1,463,499.90 |
Sep 16, 2015 | IDA-H6650 | Loan Disb | 31,262.01 |
Dec 21, 2015 | IDA-H6650 | Loan Disb | 190,080.00 |
Oct 13, 2015 | IDA-H6650 | Loan Disb | 410,263.78 |
Apr 28, 2016 | IDA-H6650 | Loan Disb | 57,755.70 |
Mar 30, 2016 | IDA-H6650 | Loan Disb | 218,845.83 |
Dec 10, 2013 | IDA-H6650 | Loan Disb | 512,723.84 |
Jan 13, 2014 | IDA-H6650 | Loan Disb | 232,852.67 |
Feb 10, 2014 | IDA-H6650 | Loan Disb | 96,380.27 |
Sep 18, 2013 | IDA-H6650 | Loan Disb | 263,391.62 |
Dec 30, 2013 | IDA-H6650 | Loan Disb | 132,966.77 |
Dec 30, 2013 | IDA-H6650 | Loan Disb | 515,639.84 |
Nov 12, 2013 | IDA-H6650 | Loan Disb | 450,217.60 |
Nov 4, 2013 | IDA-H6650 | Loan Disb | 529,935.00 |
Oct 9, 2013 | IDA-H6650 | Loan Disb | 124,346.25 |
Dec 2, 2013 | IDA-H6650 | Loan Disb | 1,187,303.60 |
Apr 26, 2011 | IDA-H6650 | Loan Commitment | 50,000,000.00 |
Jul 30, 2018 | IDA-H6650 | Loan Cancel | 4,947,504.00 |
Jul 30, 2018 | IDA-H6650 | Loan Disb | -2,013,687.20 |
Dec 19, 2016 | IDA-H6650 | Loan Disb | 330,833.88 |
Dec 5, 2016 | IDA-H6650 | Loan Disb | 600,124.90 |
Dec 9, 2016 | IDA-H6650 | Loan Disb | 396,793.16 |
Jun 22, 2017 | IDA-H6650 | Loan Disb | 102,463.69 |
Jun 21, 2017 | IDA-H6650 | Loan Disb | 138,760.60 |
Oct 11, 2017 | IDA-H6650 | Loan Disb | 108,528.92 |
Mar 28, 2017 | IDA-H6650 | Loan Disb | 72,362.39 |
Sep 12, 2017 | IDA-H6650 | Loan Disb | 247,317.08 |
Oct 6, 2017 | IDA-H6650 | Loan Disb | 13,211.48 |
Jul 17, 2017 | IDA-H6650 | Loan Disb | 573,065.50 |
Jul 26, 2017 | IDA-H6650 | Loan Disb | 344,260.53 |
Apr 7, 2014 | IDA-H6650 | Loan Disb | 190,628.31 |
May 12, 2014 | IDA-H6650 | Loan Disb | 517,646.75 |
Dec 29, 2014 | IDA-H6650 | Loan Disb | 1,566,288.50 |
Jul 8, 2014 | IDA-H6650 | Loan Disb | 649,687.50 |
Jun 18, 2014 | IDA-H6650 | Loan Disb | 531,848.50 |
Dec 22, 2014 | IDA-H6650 | Loan Disb | 129,901.49 |
Dec 22, 2014 | IDA-H6650 | Loan Disb | 262,531.20 |
Jul 16, 2014 | IDA-H6650 | Loan Disb | 118,304.06 |
Jan 5, 2015 | IDA-H6650 | Loan Disb | 725,270.40 |
Jan 7, 2015 | IDA-H6650 | Loan Disb | 593,651.80 |
Sep 10, 2014 | IDA-H6650 | Loan Disb | 179,348.92 |
Feb 26, 2015 | IDA-H6650 | Loan Disb | 139,725.00 |
Feb 26, 2015 | IDA-H6650 | Loan Disb | 42,964.97 |
Mar 16, 2015 | IDA-H6650 | Loan Disb | 39,823.99 |
Mar 25, 2015 | IDA-H6650 | Loan Disb | 295,318.20 |
Jun 9, 2015 | IDA-H6650 | Loan Disb | 467,607.72 |
Nov 17, 2014 | IDA-H6650 | Loan Disb | 573,407.20 |
Jan 13, 2015 | IDA-H6650 | Loan Disb | 501,170.00 |
Oct 20, 2014 | IDA-H6650 | Loan Disb | 300,947.22 |
Jul 10, 2013 | IDA-H6650 | Loan Disb | 1,533,513.90 |
Aug 21, 2013 | IDA-H6650 | Loan Disb | 769,470.10 |
Jul 9, 2013 | IDA-H6650 | Loan Disb | 131,208.00 |
Jul 22, 2013 | IDA-H6650 | Loan Disb | 237,538.30 |
Aug 5, 2013 | IDA-H6650 | Loan Disb | 1,151,459.00 |
Nov 25, 2014 | IDA-H6650 | Loan Disb | 45,000.00 |
Nov 25, 2014 | IDA-H6650 | Loan Disb | 593,651.80 |
Mar 4, 2014 | IDA-H6650 | Loan Disb | 365,308.66 |
Nov 13, 2013 | IDA-H6650 | Loan Disb | 533,168.00 |
Sep 3, 2013 | IDA-H6650 | Loan Disb | 800,028.50 |
Sep 3, 2013 | IDA-H6650 | Loan Disb | 110,013.76 |
Aug 20, 2013 | IDA-H6650 | Loan Disb | 554,572.06 |
Aug 6, 2013 | IDA-H6650 | Loan Disb | 309,764.72 |
Aug 12, 2013 | IDA-H6650 | Loan Disb | 45,907.32 |
Dec 9, 2014 | IDA-H6650 | Loan Disb | 521,258.66 |
Oct 2, 2013 | IDA-H6650 | Loan Disb | 40,868.99 |
Jan 6, 2014 | IDA-H6650 | Loan Disb | 192,517.27 |
Oct 2, 2013 | IDA-H6650 | Loan Disb | 196,377.75 |
Oct 8, 2013 | IDA-H6650 | Loan Disb | 636,736.06 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2017-06-30 |
Financial Management | Satisfactory | 2017-06-30 |
Monitoring and Evaluation | Satisfactory | 2017-06-30 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2017-06-30 |
Procurement | Moderately Satisfactory | 2017-06-30 |
Project Management | Moderately Satisfactory | 2017-06-30 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 08-10-2018 |
---|---|
Outcomes | Moderately Unsatisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 11-21-2018 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Modest | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Length of fiber optic network built under the project | Value | 0.00 | 1000.00 | 1014.00 |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Number of people trained under the project | Value | 0.00 | 2025.00 | 2352.00 |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Direct project beneficiaries | Value | 0.00 | 1000000.00 | 1100000.00 |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Access to Internet services | Value | 3.00 | 10.00 | 25.00 |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Access to telephone services | Value | 55.00 | 80.00 | 85.00 |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Number of ministry CIOs and other officials trained under the Project services | Value | 0.00 | 100.00 | 189.00 |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Number of Government agencies or programs using m-apps for public service delivery or program management | Value | 0.00 | 10.00 | 0.00 |
Date | April 25, 2011 | June 30, 2017 | December 30, 2017 | |
Comment |
Impact of Technical Assistance | Value | 2003 Policy | Revised ICT Policy adopted by Government | Optical Fiber liberalization policy along with uni |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Female beneficiaries | Value | 0.00 | 100000.00 | 110000.00 |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Revised ICT Policy adopted by the Government | Value | None | Yes | Expected to be adopted by Jan 2019 |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Average retail price of Internet connectivity | Value | US$450 | US$250 | US$37 |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Number of transactions conducted | Value | 0.00 | 150000.00 | 0.00 |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Service Delivery Platform established | Value | No | Yes | Yes |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Internet users | Value | 15000.00 | 50000.00 | 3500000.00 |
Date | April 25, 2011 | December 30, 2017 | December 30, 2017 | |
Comment |
Participation in incubation activities | Value | 0.00 | 10.00 | 30.00 |
Date | April 25, 2011 | June 30, 2017 | December 30, 2017 | |
Comment |