Financier | Commitments |
---|---|
Bilateral Agencies (unidentified) | 2.92 |
Global Environment Facility (GEF) | 1.00 |
Borrower/Recipient | 0.05 |
P121878
Closed
Kamleshwar Prasad Khelawan
N/A
March 12, 2013
(as of board presentation)
March 12, 2013
June 18, 2013
US$ 3.97 million
N/A
2013
US$ 3.92 million
N/A
Not Applicable
October 31, 2018
BANK APPROVED
August 8, 2019
Financier | Commitments |
---|---|
Bilateral Agencies (unidentified) | 2.92 |
Global Environment Facility (GEF) | 1.00 |
Borrower/Recipient | 0.05 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 3.92 |
Total Project Cost** | 3.97 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2014-12-12 |
Project Management | Moderately Satisfactory | 2014-12-12 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2014-12-12 |
Financial Management | Satisfactory | 2014-12-12 |
Monitoring and Evaluation | Satisfactory | 2014-12-12 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2014-12-12 |
Procurement | Moderately Unsatisfactory | 2014-12-12 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Medium term renewable energy plan and PUB capacity to increase renewable generation | Value | No | Yes | Yes |
Date | April 15, 2012 | October 15, 2014 | December 31, 2016 | |
Comment | Limited. Lack of ongoing local capacity and commitment to diversification. | Feasibility study on grid connected renewable energy finalized. Other donors working on investment options. | Feasibility study on amount of renewable energy on grid and 30 (over 3 years) trained staff to integrate RE into grid. |
Energy from renewables | Value | 0.00 | 0.00 | 7.00 |
Date | April 15, 2012 | October 15, 2014 | December 31, 2016 | |
Comment | Not available | Project implementation yet to start - no indicators to report. |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Solar energy kWh per year (Component 1) | Value | 0.00 | 0.00 | 850.00 |
Date | April 15, 2012 | October 15, 2014 | December 31, 2016 | |
Comment | Not available | Project implementation yet to start - no indicators to report. | Solar radiation and capacity factor realized. |
Training plan to "build" local capacity for maintenance and expansion (Component 2) | Value | No | No | Yes |
Date | April 15, 2012 | October 15, 2014 | December 31, 2016 | |
Comment | Limited capacity | Project implementation yet to start - no indicators to report. | At least 30 PUB, KESC, and KIT staff trained. At least 10 per annum. |
Reduction in diesel use l/yr (Component 1) | Value | 0.00 | 0.00 | 230000.00 |
Date | April 15, 2012 | October 15, 2014 | December 31, 2016 | |
Comment | Not available | Project implementation yet to start - no indicators to report. | Solar radiation and capacity factor realized. |
Savings $/yr (Component 1) | Value | 0.00 | 0.00 | 290000.00 |
Date | April 15, 2012 | October 15, 2014 | December 31, 2016 | |
Comment | Not available | Project implementation yet to start - no indicators to report. | Solar radiation and capacity factor realized. |
Maintenance program developed and implemented (Component 2) | Value | No | No | Yes |
Date | April 15, 2012 | October 15, 2014 | December 31, 2016 | |
Comment | Project implementation yet to start - no indicators to report. | Installations serviceable. Maintenance program adequate. At least two programmed maintenance undertaken per annum. |
Tons per annum CO2 reductions (Component 1) | Value | 0.00 | 0.00 | 765.00 |
Date | April 15, 2012 | October 15, 2014 | December 31, 2016 | |
Comment | Not available | Project implementation yet to start - no indicators to report. | Solar radiation and capacity factor realized. |