Financier | Commitments |
---|---|
IDA Credit | 220.00 |
Borrower/Recipient | 39.00 |
P122096
Closed
Deepak Singh
Department of Economic Affairs, Ministry of Finance, Republic of India
July 20, 2010
(as of board presentation)
September 9, 2010
March 8, 2011
US$ 259.00 million
Government of Bihar, Bihar Aapada Punarwas Evam Punarnirman Society (BAPEPS)
2011
US$ 220.00 million
B
Not Applicable
June 30, 2018
BANK APPROVED
December 11, 2020
Financier | Commitments |
---|---|
IDA Credit | 220.00 |
Borrower/Recipient | 39.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 220.00 |
IBRD + IDA Commitment | 220.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 259.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 15, 2014 | IDA-48020 | Int Charges | 151,411.47 |
Dec 27, 2013 | IDA-48020 | Loan Cancel | 50,064,804.00 |
May 2, 2014 | IDA-48020 | Loan Disb | 10,000,000.00 |
Nov 5, 2014 | IDA-48020 | Loan Disb | 6,426,101.50 |
Jul 15, 2013 | IDA-48020 | Int Charges | 134,789.40 |
Jul 15, 2013 | IDA-48020 | Int Charges | 134,789.40 |
Jul 15, 2013 | IDA-48020 | Int Charges | 955.76 |
Jul 15, 2013 | IDA-48020 | Int Charges | 955.76 |
Jan 15, 2019 | IDA-48020 | Int Charges | 296,765.78 |
Jan 15, 2019 | IDA-48020 | Int Charges | 296,765.78 |
Jan 3, 2019 | IDA-48020 | Loan Cancel | 41,043,528.00 |
Jan 15, 2019 | IDA-48020 | Loan Repay | 81,892.54 |
Jan 15, 2019 | IDA-48020 | Loan Repay | 3,978,488.80 |
Nov 7, 2018 | IDA-48020 | Loan Disb | 8,983,479.00 |
Jan 15, 2018 | IDA-48020 | Int Charges | 66,820.12 |
Jan 15, 2018 | IDA-48020 | Int Charges | 66,820.12 |
Jun 26, 2018 | IDA-48020 | Loan Disb | 4,128,569.20 |
Jul 15, 2018 | IDA-48020 | Int Charges | 323,516.28 |
Jul 15, 2018 | IDA-48020 | Int Charges | 323,516.28 |
Jul 15, 2018 | IDA-48020 | Int Charges | 62,261.97 |
Jul 15, 2018 | IDA-48020 | Int Charges | 62,261.97 |
Jul 15, 2018 | IDA-48020 | Loan Repay | 4,079,791.00 |
Mar 9, 2018 | IDA-48020 | Loan Disb | 2,601,933.80 |
Apr 5, 2018 | IDA-48020 | Loan Disb | 2,366,719.00 |
Jan 15, 2018 | IDA-48020 | Loan Repay | 4,169,884.50 |
Jan 15, 2018 | IDA-48020 | Int Charges | 256,803.69 |
Jan 15, 2018 | IDA-48020 | Int Charges | 256,803.69 |
Jun 16, 2017 | IDA-48020 | Loan Disb | 2,809,779.00 |
Feb 22, 2017 | IDA-48020 | Loan Disb | 4,743,285.00 |
Jul 15, 2017 | IDA-48020 | Loan Repay | 4,007,912.00 |
Jul 15, 2017 | IDA-48020 | Int Charges | 237,015.14 |
Jul 15, 2017 | IDA-48020 | Int Charges | 237,015.14 |
Oct 27, 2017 | IDA-48020 | Loan Disb | 3,746,672.20 |
Jul 15, 2017 | IDA-48020 | Loan Repay | 38,355.59 |
Nov 2, 2017 | IDA-48020 | Loan Disb | 1,950,214.50 |
Oct 19, 2016 | IDA-48020 | Loan Disb | 470,959.62 |
Jan 15, 2017 | IDA-48020 | Loan Repay | 3,883,954.50 |
Jan 15, 2017 | IDA-48020 | Int Charges | 281,521.47 |
Jan 15, 2017 | IDA-48020 | Int Charges | 281,521.47 |
Jan 15, 2017 | IDA-48020 | Loan Repay | 48,182.89 |
Jun 28, 2017 | IDA-48020 | Loan Disb | 768,637.00 |
Jul 15, 2016 | IDA-48020 | Int Charges | 274,026.56 |
Jul 15, 2016 | IDA-48020 | Int Charges | 274,026.56 |
Jul 15, 2016 | IDA-48020 | Int Charges | 4,669.21 |
Jul 15, 2016 | IDA-48020 | Int Charges | 4,669.21 |
Jul 15, 2016 | IDA-48020 | Loan Repay | 4,056,307.20 |
Oct 13, 2016 | IDA-48020 | Loan Disb | 5,334,528.00 |
May 23, 2016 | IDA-48020 | Loan Disb | 4,450,837.00 |
Nov 30, 2015 | IDA-48020 | Loan Disb | 6,633,991.50 |
Jan 15, 2016 | IDA-48020 | Loan Repay | 4,026,130.50 |
Jan 15, 2016 | IDA-48020 | Int Charges | 242,572.40 |
Jan 15, 2016 | IDA-48020 | Int Charges | 242,572.40 |
Mar 17, 2016 | IDA-48020 | Loan Disb | 6,754,484.00 |
May 15, 2015 | IDA-48020 | Loan Disb | 6,208,701.00 |
Jan 15, 2016 | IDA-48020 | Int Charges | 4,918.95 |
Jan 15, 2016 | IDA-48020 | Int Charges | 4,918.95 |
Jul 15, 2015 | IDA-48020 | Int Charges | 202,812.31 |
Jul 15, 2015 | IDA-48020 | Int Charges | 202,812.31 |
Jul 15, 2015 | IDA-48020 | Int Charges | 4,747.10 |
Jul 15, 2015 | IDA-48020 | Int Charges | 4,747.10 |
Jan 15, 2015 | IDA-48020 | Int Charges | 185,082.89 |
Jan 15, 2015 | IDA-48020 | Int Charges | 185,082.89 |
Jul 15, 2014 | IDA-48020 | Int Charges | 654.58 |
Jul 15, 2014 | IDA-48020 | Int Charges | 654.58 |
Jul 15, 2014 | IDA-48020 | Int Charges | 167,970.86 |
Jul 15, 2014 | IDA-48020 | Int Charges | 167,970.86 |
May 6, 2015 | IDA-48020 | Loan Disb | 6,754,484.00 |
Jan 15, 2015 | IDA-48020 | Int Charges | 274.76 |
Jan 15, 2015 | IDA-48020 | Int Charges | 274.76 |
Jan 15, 2014 | IDA-48020 | Int Charges | 1,859.60 |
Jan 15, 2014 | IDA-48020 | Int Charges | 1,859.60 |
Jan 15, 2014 | IDA-48020 | Int Charges | 151,411.47 |
Sep 9, 2010 | IDA-48020 | Loan Commitment | 220,000,000.00 |
Jul 15, 2024 | IDA-48020 | Int Charges | 21,398.05 |
Jul 15, 2024 | IDA-48020 | Int Charges | 21,398.05 |
Jul 15, 2024 | IDA-48020 | Loan Repay | 2,656,255.00 |
Jul 15, 2024 | IDA-48020 | Int Charges | 246,122.73 |
Jul 15, 2024 | IDA-48020 | Int Charges | 246,122.73 |
Jan 15, 2024 | IDA-48020 | Loan Repay | 2,673,846.50 |
Jan 15, 2024 | IDA-48020 | Int Charges | 245,002.62 |
Jan 15, 2024 | IDA-48020 | Int Charges | 245,002.62 |
Jan 15, 2024 | IDA-48020 | Int Charges | 26,434.95 |
Jan 15, 2024 | IDA-48020 | Int Charges | 26,434.95 |
Jan 15, 2023 | IDA-48020 | Loan Repay | 2,650,817.00 |
Jan 15, 2023 | IDA-48020 | Int Charges | 217,366.50 |
Jan 15, 2023 | IDA-48020 | Int Charges | 217,366.50 |
Jan 15, 2023 | IDA-48020 | Loan Repay | 47,765.50 |
Jul 15, 2023 | IDA-48020 | Int Charges | 253,590.44 |
Jul 15, 2023 | IDA-48020 | Int Charges | 253,590.44 |
Jul 15, 2023 | IDA-48020 | Loan Repay | 2,710,790.50 |
Jul 15, 2023 | IDA-48020 | Int Charges | 72,206.30 |
Jul 15, 2023 | IDA-48020 | Int Charges | 72,206.30 |
Jul 15, 2022 | IDA-48020 | Int Charges | 3,233.52 |
Jul 15, 2022 | IDA-48020 | Int Charges | 3,233.52 |
Jul 15, 2022 | IDA-48020 | Loan Repay | 2,620,331.50 |
Jul 15, 2022 | IDA-48020 | Int Charges | 290,686.50 |
Jul 15, 2022 | IDA-48020 | Int Charges | 290,686.50 |
Jan 15, 2022 | IDA-48020 | Loan Repay | 16,819.36 |
Jan 15, 2022 | IDA-48020 | Loan Repay | 1,313,850.50 |
Jan 15, 2022 | IDA-48020 | Int Charges | 314,087.97 |
Jan 15, 2022 | IDA-48020 | Int Charges | 314,087.97 |
Jan 15, 2021 | IDA-48020 | Int Charges | 0.01 |
Jan 15, 2021 | IDA-48020 | Int Charges | -0.01 |
Jan 15, 2021 | IDA-48020 | Int Charges | 7,941.90 |
Jan 15, 2021 | IDA-48020 | Int Charges | 7,941.90 |
Jan 15, 2021 | IDA-48020 | Loan Repay | 1,362,940.80 |
Jan 15, 2021 | IDA-48020 | Int Charges | 310,950.00 |
Jan 15, 2021 | IDA-48020 | Int Charges | 310,950.00 |
Jul 15, 2021 | IDA-48020 | Loan Repay | 1,346,434.90 |
Jul 15, 2021 | IDA-48020 | Int Charges | 326,376.47 |
Jul 15, 2021 | IDA-48020 | Int Charges | 326,376.47 |
Jul 15, 2021 | IDA-48020 | Int Charges | 24,110.08 |
Jul 15, 2021 | IDA-48020 | Int Charges | 24,110.08 |
Aug 4, 2020 | IDA-48020 | Loan Cancel | 533,025.60 |
Jul 15, 2020 | IDA-48020 | Int Charges | 245,261.90 |
Jul 15, 2020 | IDA-48020 | Int Charges | 245,261.90 |
Aug 4, 2020 | IDA-48020 | Loan Disb | -533,025.60 |
Jul 15, 2020 | IDA-48020 | Int Charges | 18,608.21 |
Jul 15, 2020 | IDA-48020 | Int Charges | 18,608.21 |
Jul 15, 2020 | IDA-48020 | Int Charges | 53,913.14 |
Jul 15, 2020 | IDA-48020 | Int Charges | 53,913.14 |
Jul 15, 2020 | IDA-48020 | Int Charges | 15,802.41 |
Jul 15, 2020 | IDA-48020 | Int Charges | 15,802.41 |
Jan 15, 2020 | IDA-48020 | Int Charges | 318,091.38 |
Jan 15, 2020 | IDA-48020 | Int Charges | 318,091.38 |
Jan 15, 2020 | IDA-48020 | Int Charges | 5,514.61 |
Jan 15, 2020 | IDA-48020 | Int Charges | 5,514.61 |
Jan 15, 2020 | IDA-48020 | Loan Repay | 2,781,603.50 |
Jul 15, 2019 | IDA-48020 | Int Charges | 42,857.32 |
Jul 15, 2019 | IDA-48020 | Int Charges | 42,857.32 |
Jul 15, 2019 | IDA-48020 | Loan Repay | 2,788,207.80 |
Jul 15, 2019 | IDA-48020 | Int Charges | 339,513.00 |
Jul 15, 2019 | IDA-48020 | Int Charges | 339,513.00 |
Jul 15, 2019 | IDA-48020 | Int Charges | -6,827.63 |
Jul 15, 2019 | IDA-48020 | Int Charges | 6,827.63 |
Jan 3, 2019 | IDA-48020 | Loan Disb | 552,811.00 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Satisfactory | 2018-06-15 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2018-06-15 |
Counterpart Funding | Highly Satisfactory | 2018-06-15 |
Project Management | Moderately Satisfactory | 2018-06-15 |
Progress towards achievement of PDO | Moderately Satisfactory | 2018-06-15 |
Procurement | Moderately Satisfactory | 2018-06-15 |
Monitoring and Evaluation | Moderately Satisfactory | 2018-06-15 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-17-2018 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Moderately Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 06-03-2019 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | Not Rated | N/a |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of flood affected households having new houses in project area | Value | 0.00 | 62644.00 | 56758.00 |
Date | September 9, 2010 | June 30, 2018 | June 30, 2018 | |
Comment |
Number of villages having access to restored linkages | Value | 0.00 | 100.00 | 100.00 |
Date | September 9, 2010 | June 30, 2018 | June 30, 2018 | |
Comment |
Strengthened embankment to arrest breaches during flood (km) | Value | 0.00 | 12.00 | 13.50 |
Date | June 28, 2013 | June 30, 2018 | June 30, 2018 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Roads constructed, Rural | Value | 0.00 | 259.30 | 254.57 |
Date | January 11, 2011 | June 30, 2018 | June 30, 2018 | |
Comment |
Effective disbursement of contingent emergency response financing in case of future disasters | Value | 0.00 | 0.00 | 0.00 |
Date | January 11, 2011 | June 30, 2018 | June 30, 2018 | |
Comment |
Completion of technical studies and establishment of center of excellence to better understand the flood and sediment management | Value | 0 | 100 | 90 |
Date | January 11, 2011 | June 30, 2018 | June 30, 2018 | |
Comment |
Km of roads constructed | Value | 0.00 | 259.30 | 254.57 |
Date | January 11, 2011 | June 30, 2018 | June 30, 2018 | |
Comment |
Number of bridges constructed | Value | 0.00 | 69.00 | 69.00 |
Date | January 11, 2011 | June 30, 2018 | June 30, 2018 | |
Comment |
1st tranche of housing support released to beneficiaries | Value | 0.00 | 100.00 | 100.00 |
Date | January 11, 2011 | June 30, 2018 | June 30, 2018 | |
Comment |
2nd tranche of housing suport released to beneficiaries | Value | 0.00 | 100.00 | 92.00 |
Date | January 11, 2011 | June 30, 2018 | June 30, 2018 | |
Comment |
3rd tranche released to beneficiaries | Value | 0.00 | 100.00 | 89.00 |
Date | January 11, 2011 | June 30, 2018 | June 30, 2018 | |
Comment |
Contract awarded for structural intervention | Value | 0.00 | 6.00 | 6.00 |
Date | January 11, 2011 | June 30, 2018 | June 30, 2018 | |
Comment |