Georgia: Third Development Policy Operation

Abstract*

The Third Development Policy Operation (DPO-3) Program is the third in a series of three programmatic development policy operations intended to support the Government of Georgia's policy reform program to: mitigate the impact of the economic downturn in the short-term; and facilitate recovery and prepare Georgia for post-crisis growth in the medium-term. In addition to a satisfactory macroeconomic and fiscal framework, the main policy areas supported...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Third Development Policy Operation (DPO-3) is the third in a series of three programmatic development policy operations to support Government's policy reform program to (i) mitigate the impact of the economic downturn in the short-term; and (ii) facilitate recovery and prepare Georgia for post-crisis growth in the medium-term. DPO-3 emphasizes the second objective, to sustain the economic recovery and prepare the conditions for post-crisis growth. In addition to a satisfactory macroeconomic and fiscal framework, themain policy areas supported are: (i) improving the efficiency and effectiveness of public finances; (ii) improving the effectiveness of the social safety net; and (iii) improving external competitiveness.

Key Details

Project Details

  • P122202

  • Closed

  • Faruk Khan

  • N/A

  • Georgia

  • August 15, 2011

  • (as of board presentation)

    July 21, 2011

  • November 15, 2011

  • US$ 40.00 million

  • N/A

  • February 26, 2024

  • March 31, 2012

  • BANK APPROVED

  • P112700

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 40.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 40.00
IBRD + IDA Commitment 40.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 40.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Oct 15, 2016 IDA-50080 Loan Repay 788,485.44
Oct 15, 2016 IDA-50080 Int Charges 129,247.50
Apr 15, 2020 IDA-50080 Int Charges 98,524.00
Apr 15, 2020 IDA-50080 Int Charges 98,524.00
Apr 15, 2020 IDA-50080 Int Charges 164,206.75
Apr 15, 2020 IDA-50080 Loan Repay 3,764.16
Apr 15, 2020 IDA-50080 Loan Repay 864,549.50
Oct 15, 2020 IDA-50080 Int Charges 97,238.37
Oct 15, 2020 IDA-50080 Loan Repay 915.51
Oct 15, 2020 IDA-50080 Int Charges 97,238.37
Oct 15, 2020 IDA-50080 Int Charges 161,227.23
Oct 15, 2020 IDA-50080 Loan Repay 581,336.50
Oct 15, 2020 IDA-50080 Int Charges 156.51
Oct 15, 2020 IDA-50080 Int Charges 156.51
Oct 15, 2016 IDA-50080 Int Charges 129,247.50
Oct 15, 2016 IDA-50080 Int Charges 215,412.53
Apr 15, 2017 IDA-50080 Int Charges 112,125.86
Apr 15, 2017 IDA-50080 Int Charges 112,125.86
Apr 15, 2017 IDA-50080 Int Charges 196,015.10
Apr 15, 2017 IDA-50080 Int Charges 11,038.77
Apr 15, 2017 IDA-50080 Int Charges 11,038.77
Apr 15, 2017 IDA-50080 Loan Repay 1,102,637.00
Oct 15, 2017 IDA-50080 Loan Repay 15,755.52
Apr 15, 2017 IDA-50080 Loan Repay 18,199.77
Oct 15, 2017 IDA-50080 Int Charges 123,880.80
Oct 15, 2017 IDA-50080 Int Charges 123,880.80
Oct 15, 2017 IDA-50080 Int Charges 198,573.98
Oct 15, 2017 IDA-50080 Int Charges 9,642.27
Oct 15, 2017 IDA-50080 Loan Repay 1,151,429.80
Apr 15, 2018 IDA-50080 Loan Repay 4,674.99
Apr 15, 2018 IDA-50080 Int Charges 8,115.23
Apr 15, 2018 IDA-50080 Loan Repay 1,195,221.50
Apr 15, 2018 IDA-50080 Int Charges 122,853.00
Apr 15, 2018 IDA-50080 Int Charges 122,853.00
Apr 15, 2018 IDA-50080 Int Charges 204,755.05
Oct 15, 2018 IDA-50080 Int Charges 174,505.70
Oct 15, 2018 IDA-50080 Loan Repay 4,402.79
Oct 15, 2018 IDA-50080 Loan Repay 1,141,288.50
Oct 15, 2018 IDA-50080 Loan Repay 7,534.96
Oct 15, 2018 IDA-50080 Int Charges 113,750.04
Apr 15, 2016 IDA-50080 Int Charges 131,774.06
Apr 15, 2016 IDA-50080 Int Charges 3,538.97
Oct 15, 2016 IDA-50080 Loan Repay 58.07
Oct 15, 2016 IDA-50080 Loan Repay 348,834.47
Oct 15, 2018 IDA-50080 Int Charges 113,750.04
Oct 15, 2014 IDA-50080 Int Charges 949.38
Oct 15, 2014 IDA-50080 Int Charges 139,156.88
Oct 15, 2014 IDA-50080 Int Charges 139,156.88
Oct 15, 2014 IDA-50080 Int Charges 231,928.16
Oct 15, 2013 IDA-50080 Int Charges 4,913.61
Oct 15, 2013 IDA-50080 Int Charges 4,913.61
Oct 15, 2013 IDA-50080 Int Charges 138,525.77
Oct 15, 2013 IDA-50080 Int Charges 138,525.77
Oct 15, 2013 IDA-50080 Int Charges 236,098.17
Apr 15, 2014 IDA-50080 Int Charges 145,128.75
Apr 15, 2014 IDA-50080 Int Charges 145,128.75
Apr 15, 2014 IDA-50080 Int Charges 240,891.16
Apr 15, 2014 IDA-50080 Int Charges 3,002.44
Apr 15, 2015 IDA-50080 Int Charges 117,476.09
Apr 15, 2015 IDA-50080 Int Charges 214,470.34
Apr 15, 2015 IDA-50080 Int Charges 117,476.09
Apr 15, 2015 IDA-50080 Int Charges 11,206.10
Apr 15, 2015 IDA-50080 Int Charges 11,206.10
Oct 15, 2015 IDA-50080 Int Charges 10,722.50
Oct 15, 2015 IDA-50080 Int Charges 10,722.50
Oct 15, 2015 IDA-50080 Int Charges 122,207.50
Oct 15, 2015 IDA-50080 Int Charges 122,207.50
Oct 15, 2015 IDA-50080 Int Charges 217,980.02
Apr 15, 2016 IDA-50080 Int Charges 219,623.47
Apr 15, 2016 IDA-50080 Int Charges 131,774.06
Apr 15, 2023 IDA-50080 Loan Repay 43,560.82
Apr 15, 2023 IDA-50080 Loan Repay 1,073,975.90
Apr 15, 2023 IDA-50080 Int Charges 29,362.57
Apr 15, 2023 IDA-50080 Int Charges 29,362.57
Apr 15, 2023 IDA-50080 Int Charges 51,531.81
Apr 15, 2023 IDA-50080 Int Charges 51,531.81
Apr 15, 2023 IDA-50080 Int Charges 117,885.08
Oct 15, 2023 IDA-50080 Int Charges 16,380.35
Oct 15, 2023 IDA-50080 Loan Repay 879,218.60
Oct 15, 2023 IDA-50080 Int Charges 74,174.22
Oct 15, 2023 IDA-50080 Int Charges 74,174.22
Oct 15, 2023 IDA-50080 Int Charges 123,623.73
Oct 15, 2023 IDA-50080 Loan Repay 201,465.36
Apr 15, 2024 IDA-50080 Loan Repay 897,172.75
Apr 15, 2024 IDA-50080 Loan Repay 22,172.16
Apr 15, 2024 IDA-50080 Int Charges 70,466.89
Apr 15, 2024 IDA-50080 Int Charges 70,466.89
Apr 15, 2024 IDA-50080 Int Charges 117,444.90
Apr 15, 2024 IDA-50080 Loan Repay 166,660.38
Jul 21, 2011 IDA-50080 Loan Commitment 40,000,000.00
Apr 15, 2021 IDA-50080 Int Charges 1,110.85
Apr 15, 2021 IDA-50080 Loan Repay 589,297.50
Apr 15, 2021 IDA-50080 Int Charges 0.01
Apr 15, 2021 IDA-50080 Int Charges 0.01
Apr 15, 2021 IDA-50080 Int Charges 3,901.02
Apr 15, 2021 IDA-50080 Int Charges 3,901.02
Apr 15, 2021 IDA-50080 Int Charges 92,462.51
Apr 15, 2021 IDA-50080 Int Charges 92,462.51
Apr 15, 2021 IDA-50080 Int Charges 160,605.90
Oct 15, 2021 IDA-50080 Int Charges 10,700.67
Oct 15, 2021 IDA-50080 Int Charges 10,700.67
Oct 15, 2021 IDA-50080 Loan Repay 7,206.80
Oct 15, 2021 IDA-50080 Loan Repay 575,193.70
Oct 15, 2021 IDA-50080 Int Charges 82,351.01
Oct 15, 2021 IDA-50080 Int Charges 82,351.01
Oct 15, 2021 IDA-50080 Int Charges 155,086.19
Apr 15, 2022 IDA-50080 Int Charges 146,567.72
Apr 15, 2022 IDA-50080 Loan Repay 4,982.47
Apr 15, 2022 IDA-50080 Loan Repay 235,436.64
Apr 15, 2022 IDA-50080 Loan Repay 323,220.90
Apr 15, 2022 IDA-50080 Int Charges 87,940.63
Apr 15, 2022 IDA-50080 Int Charges 87,940.63
Oct 15, 2022 IDA-50080 Loan Repay 20,117.24
Oct 15, 2022 IDA-50080 Loan Repay 1,032,995.25
Oct 15, 2022 IDA-50080 Int Charges 56,326.49
Oct 15, 2022 IDA-50080 Int Charges 56,326.49
Oct 15, 2022 IDA-50080 Int Charges 23,853.66
Oct 15, 2022 IDA-50080 Int Charges 23,853.66
Oct 15, 2022 IDA-50080 Int Charges 133,633.62
Apr 15, 2019 IDA-50080 Int Charges 14,998.56
Apr 15, 2019 IDA-50080 Loan Repay 1,128,921.80
Apr 15, 2019 IDA-50080 Loan Repay 18,249.05
Apr 15, 2019 IDA-50080 Int Charges 108,850.82
Apr 15, 2019 IDA-50080 Int Charges 108,850.82
Apr 15, 2019 IDA-50080 Int Charges 177,302.62
Oct 15, 2019 IDA-50080 Int Charges 103,061.76
Oct 15, 2019 IDA-50080 Int Charges 103,061.76
Oct 15, 2019 IDA-50080 Int Charges 171,769.62
Oct 15, 2019 IDA-50080 Int Charges 4,056.92
Oct 15, 2019 IDA-50080 Loan Repay 275,576.06
Oct 15, 2019 IDA-50080 Loan Repay 855,276.20
Oct 15, 2019 IDA-50080 Int Charges 0.01
Oct 15, 2019 IDA-50080 Int Charges 0.01
Apr 15, 2020 IDA-50080 Loan Repay 259,139.60

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Program Management Satisfactory 2011-12-05
Progress towards achievement of PDO Satisfactory 2011-12-05
Monitoring and Evaluation Satisfactory 2011-12-05
Overall Implementation Progress (IP) Satisfactory 2011-12-05

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 12-27-2012
OutcomesSubstantial
Risk to Development OutcomeModest
Bank PerformanceSubstantial
Borrower PerformanceSubstantial
Government PerformanceSubstantial
Implementing AgencySubstantial

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 06-14-2018PROJECT PERFORMANCE ASSESSMENT REPORT: 06-23-2016
Outcome RatingSatisfactory Satisfactory
Risk To Development OutcomeModerateModerate
Bank PerformanceSatisfactorySatisfactory
Borrower PerformanceSatisfactorySatisfactory
Government PerformanceSatisfactory
Implementing AgencySatisfactorySatisfactory
Icr QualitySatisfactory
M&e QualitySubstantialSubstantial

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Programming of public investment over medium term horizon: Procedures for preparing, prioritizing, selecting, and monitoring publicinvestment projects.ValueNo standard guidelines for programming public inveIncreased accountability for implementation of pubIncreased accountability for implementation of pub
    DateDecember 31, 2008June 30, 2011December 31, 2011
    Comment
  • Number of first-level spending units and programs covered by results-oriented budgets, with improved performance indicators and reporting on annual performance.ValueNo first-level government spending units or prograFive first-level government spending units, each iFive first-level government spending units, each i
    DateDecember 31, 2008June 30, 2011December 31, 2011
    Comment
  • Stable tax revenue performance: no significant decline in tax revenue/GDP ratio.ValueTax revenues24.9% of GDP in 2008Tax revenues projected at 24.9% of GDP in 2011Tax revenues projected to remain stable at about 2
    DateDecember 31, 2008November 15, 2011December 31, 2011
    Comment
  • Time required to import and export.ValueTime to export: 12 daysTime to import: 14 days.Time to export: 10 days, down 17%;Time to import:Reduction in time to trade across borders by at le
    DateDecember 31, 2008December 31, 2010December 31, 2011
    Comment
  • Lay basis to create improved conditions for access of Georgian products to European and international markets.ValueNo framework for trade-related reforms to improve Priority trade-related reforms implemented to lay Priority trade-related reforms implemented to lay
    DateDecember 31, 2008June 30, 2011December 31, 2011
    Comment
  • Percent of bottom quintile and in particular, bottom decile receiving Targeted Social Assistance.Value31.6% of bottom decile; 21.7% of bottom quintile38.9% of bottom decile;27.4% of bottom quintileApproaching 45% of the bottom decile.
    DateDecember 31, 2007December 31, 2009December 31, 2011
    Comment
  • Percent of TSA recipients who are in the bottom quintile and bottom decile.Value47% goes to bottom decile; 65% goes to bottom quin44% goes to bottom decile62% goes to bottom quintAt least 60% or more goes to bottom quintile.
    DateDecember 31, 2007December 31, 2009December 31, 2011
    Comment
  • Share of bottom two quintiles with access to publicly subsidized health insurance.Value20.7%36.9%At least 35% at the end of the program.
    DateDecember 31, 2007December 31, 2010December 31, 2011
    Comment
  • Share of population with access to health insurance.Value12.3%29.4%At least 35% or better.
    DateDecember 31, 2007December 31, 2010December 31, 2011
    Comment
  • Increase in accountability and efficiency of the institutional framework for state-funded health programs.ValueLimited public stewardship measures for promoting Information platform for efficiency improvements eInformation platform for efficiency improvements e
    DateDecember 31, 2008November 15, 2011December 31, 2011
    Comment
  • Time required for tax compliance.Value387 hours per yearTime remains at 387 hours in 2010 in Doing BusinesReduction in number of hours used for paying taxes
    DateDecember 31, 2008December 31, 2010December 31, 2011
    Comment
  • Increased reliability and independence of statistics, streamlined institutional structures, and improved human capacity and public outreach.ValueUneven reliability and independence of statistics,Reliability of statistics and human capacity of stReliability of statistics and human capacity of st
    DateDecember 31, 2008November 15, 2011December 31, 2011
    Comment