Burundi - Emergency Energy Project from IDA CRW

Development Objective

The project's development objective (PDO) is to improve the capacity and reliability of electricity generation, transmission, and distribution.

Key Details

Project Details

  • P122217

  • Closed

  • Miarintsoa Rakotondramanana

  • N/A

  • Burundi

  • August 19, 2010

  • (as of board presentation)

    September 30, 2010

  • February 23, 2011

  • US$ 15.40 million

  • B

  • Not Applicable

  • January 31, 2014

  • BANK APPROVED

  • November 15, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 15.40

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 15.40
IBRD + IDA Commitment 15.40
Lending Instrument
Grant Amount N/A
Total Project Cost** 15.40

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 5, 2014 IDA-H6170 Loan Disb 108,102.22
Sep 30, 2010 IDA-H6170 Loan Commitment 15,400,000.00
May 19, 2014 IDA-H6170 Loan Disb -40,217.28
May 30, 2014 IDA-H6170 Loan Disb 164,093.44
May 31, 2014 IDA-H6170 Loan Cancel 58,262.38
Sep 10, 2013 IDA-H6170 Loan Disb 1,092,313.40
Nov 27, 2013 IDA-H6170 Loan Disb 283,415.22
Feb 3, 2014 IDA-H6170 Loan Disb 851,604.94
Jan 24, 2014 IDA-H6170 Loan Disb 1,446,361.90
Oct 15, 2013 IDA-H6170 Loan Disb 26,963.01
Sep 25, 2013 IDA-H6170 Loan Disb 599,986.60
Feb 21, 2014 IDA-H6170 Loan Disb 1,005,180.60
Jan 9, 2014 IDA-H6170 Loan Disb 70,242.97
Jan 3, 2014 IDA-H6170 Loan Disb 722,203.30
Jan 29, 2014 IDA-H6170 Loan Cancel 292,499.30

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Counterpart Funding Satisfactory 2014-02-11
Progress towards achievement of PDO Moderately Satisfactory 2014-02-11
Financial Management Satisfactory 2014-02-11
Monitoring and Evaluation Satisfactory 2014-02-11
Overall Implementation Progress (IP) Moderately Satisfactory 2014-02-11
Procurement Moderately Satisfactory 2014-02-11
Project Management Satisfactory 2014-02-11

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 08-28-2014
OutcomesModerately Satisfactory
Risk to Development OutcomeModest
Bank PerformanceModerately Satisfactory
Borrower PerformanceModerately Satisfactory
Government PerformanceModerately Satisfactory
Implementing AgencyModerately Satisfactory

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 10-30-2015PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Satisfactory N/a
Risk To Development OutcomeSignificantN/a
Bank PerformanceModerately SatisfactoryN/a
Borrower PerformanceModerately UnsatisfactoryN/a
Government PerformanceModerately UnsatisfactoryN/a
Implementing AgencyModerately UnsatisfactoryN/a
Icr QualitySatisfactoryN/a
M&e QualitySubstantialN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Average unplanned interruptions frequency in BujumburaValue51.0044.0030.00
    DateDecember 31, 2009December 31, 2013January 31, 2014
    Commentdata quality is verified through annual performance contract auditsThe end target has not been met. In addition, 20 interruptions due to the problem of the Bukavu-Goma transmission line in DRCwhich supplies Burundi were recorded by REGIDESO but have not been included here.
  • Increased electricity generation from the Bujumbura thermal power plantValue6.0023.4025.00
    DateDecember 31, 2010December 31, 2013January 31, 2014
    CommentThe 5MW thermal plant was installed in July 2013 and commissioned on August, 18 2013. The total thermal generation hassignificantly increased compared to the situation in March 2013 (2.17GWh) and in October 2013 (14.6GWh). The end target will bereached by the closing date.
  • Direct project beneficiariesValue270000.00456552.00318000.00
    DateDecember 31, 2009December 31, 2013January 31, 2014
    Comment50% female50% female50% female
  • Female beneficiariesValue50.0050.0050.00
    DateDecember 31, 2009December 31, 2013January 31, 2014
    Comment
  • Average interruption frequency per year in the project areaValue51.0044.0030.00
    DateDecember 31, 2009December 31, 2013January 31, 2014
    CommentCSI Retrofit Dec. 2013The end target has not been met. In addition, 20 interruptions due to the problem of the Bukavu-Goma transmission line in DRCwhich supplies Burundi were recorded by REGIDESO but have not been included here.
  • Customers served in the project areaValue55000.0076188.0075000.00
    DateDecember 31, 2009December 31, 2013January 31, 2014
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Generation capacity of conventional generation constructedValue5.5010.5010.50
    DateDecember 31, 2009December 31, 2013January 31, 2014
    Commentbaseline does not include short term emergency rental power unitsThe 5Mw thermal plant was commissioned in August 2013. The value includes both the newly installed 5Mw and the existing 5.5Mw inBujumbura
  • Generation capacity of renewable energy rehabilitatedValue0.0020.0020.00
    DateDecember 31, 2009December 31, 2013January 31, 2014
    CommentThe rehabilitation of the electromechanical equipment of the existing Rwegura and Nyemanga hydro plants which was financed underthe project was completed in July 2013
  • MV and HV-substations rehabilitatedValue0.001.001.00
    DateDecember 31, 2009December 31, 2013January 31, 2014
    CommentThe rehabilitation works at the RN1 substation were completed in March 2013.
  • Pre-payment electricity meters installed by REGIDESOValue10000.0045077.0043000.00
    DateDecember 31, 2009December 31, 2013January 31, 2014
    CommentIt includes both meters installed by REGIDESO under and outside the project as stated in the PAD. In fact, the end target includesmeters installed both by the project and REGIDESO itself. The objective has been met.
  • Electricity collection rateValue64.0081.7085.00
    DateDecember 31, 2009December 31, 2013January 31, 2014
    Commentcalculated as billing revenues divided by amounts billedREGIDESO has accumulated unpaid bills from earlier years that need to be written off. The actual value is an estimated one (thevalue of the year 2012). The exact value for the year 2013 will be known by March 2014. The rate is likely to be improved due tothe fully installation of prepaid meters.
  • Increased availability of power supply from the extended Bujumbura thermal power plant (hours/week)Value0.00140.0056.00
    DateDecember 31, 2009December 31, 2013January 31, 2014
    CommentThe end target has been surpassed. The average running hours of the thermal plant is about 140hours/week
  • Generation Capacity of Conventional Generation constructed under the projectValue0.005.005.00
    DateDecember 31, 2009December 31, 2013January 31, 2014
    CommentCSI Retrofit Dec. 2013The plant was installed in July 2013. The end target has been met.