Financier | Commitments |
---|---|
IDA Grant | 15.40 |
P122217
Closed
Miarintsoa Rakotondramanana
N/A
August 19, 2010
(as of board presentation)
September 30, 2010
February 23, 2011
US$ 15.40 million
N/A
2011
US$ 15.40 million
B
Not Applicable
January 31, 2014
BANK APPROVED
November 15, 2023
Financier | Commitments |
---|---|
IDA Grant | 15.40 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 15.40 |
IBRD + IDA Commitment | 15.40 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 15.40 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 5, 2014 | IDA-H6170 | Loan Disb | 108,102.22 |
Sep 30, 2010 | IDA-H6170 | Loan Commitment | 15,400,000.00 |
May 19, 2014 | IDA-H6170 | Loan Disb | -40,217.28 |
May 30, 2014 | IDA-H6170 | Loan Disb | 164,093.44 |
May 31, 2014 | IDA-H6170 | Loan Cancel | 58,262.38 |
Sep 10, 2013 | IDA-H6170 | Loan Disb | 1,092,313.40 |
Nov 27, 2013 | IDA-H6170 | Loan Disb | 283,415.22 |
Feb 3, 2014 | IDA-H6170 | Loan Disb | 851,604.94 |
Jan 24, 2014 | IDA-H6170 | Loan Disb | 1,446,361.90 |
Oct 15, 2013 | IDA-H6170 | Loan Disb | 26,963.01 |
Sep 25, 2013 | IDA-H6170 | Loan Disb | 599,986.60 |
Feb 21, 2014 | IDA-H6170 | Loan Disb | 1,005,180.60 |
Jan 9, 2014 | IDA-H6170 | Loan Disb | 70,242.97 |
Jan 3, 2014 | IDA-H6170 | Loan Disb | 722,203.30 |
Jan 29, 2014 | IDA-H6170 | Loan Cancel | 292,499.30 |
Name | Review | Date |
---|---|---|
Counterpart Funding | Satisfactory | 2014-02-11 |
Progress towards achievement of PDO | Moderately Satisfactory | 2014-02-11 |
Financial Management | Satisfactory | 2014-02-11 |
Monitoring and Evaluation | Satisfactory | 2014-02-11 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2014-02-11 |
Procurement | Moderately Satisfactory | 2014-02-11 |
Project Management | Satisfactory | 2014-02-11 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 08-28-2014 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | Modest |
Bank Performance | Moderately Satisfactory |
Borrower Performance | Moderately Satisfactory |
Government Performance | Moderately Satisfactory |
Implementing Agency | Moderately Satisfactory |
INDICATOR | ICR REVIEW: 10-30-2015 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Moderately Satisfactory | N/a |
Risk To Development Outcome | Significant | N/a |
Bank Performance | Moderately Satisfactory | N/a |
Borrower Performance | Moderately Unsatisfactory | N/a |
Government Performance | Moderately Unsatisfactory | N/a |
Implementing Agency | Moderately Unsatisfactory | N/a |
Icr Quality | Satisfactory | N/a |
M&e Quality | Substantial | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Average unplanned interruptions frequency in Bujumbura | Value | 51.00 | 44.00 | 30.00 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment | data quality is verified through annual performance contract audits | The end target has not been met. In addition, 20 interruptions due to the problem of the Bukavu-Goma transmission line in DRCwhich supplies Burundi were recorded by REGIDESO but have not been included here. |
Increased electricity generation from the Bujumbura thermal power plant | Value | 6.00 | 23.40 | 25.00 |
Date | December 31, 2010 | December 31, 2013 | January 31, 2014 | |
Comment | The 5MW thermal plant was installed in July 2013 and commissioned on August, 18 2013. The total thermal generation hassignificantly increased compared to the situation in March 2013 (2.17GWh) and in October 2013 (14.6GWh). The end target will bereached by the closing date. |
Direct project beneficiaries | Value | 270000.00 | 456552.00 | 318000.00 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment | 50% female | 50% female | 50% female |
Female beneficiaries | Value | 50.00 | 50.00 | 50.00 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment |
Average interruption frequency per year in the project area | Value | 51.00 | 44.00 | 30.00 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment | CSI Retrofit Dec. 2013 | The end target has not been met. In addition, 20 interruptions due to the problem of the Bukavu-Goma transmission line in DRCwhich supplies Burundi were recorded by REGIDESO but have not been included here. |
Customers served in the project area | Value | 55000.00 | 76188.00 | 75000.00 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Generation capacity of conventional generation constructed | Value | 5.50 | 10.50 | 10.50 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment | baseline does not include short term emergency rental power units | The 5Mw thermal plant was commissioned in August 2013. The value includes both the newly installed 5Mw and the existing 5.5Mw inBujumbura |
Generation capacity of renewable energy rehabilitated | Value | 0.00 | 20.00 | 20.00 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment | The rehabilitation of the electromechanical equipment of the existing Rwegura and Nyemanga hydro plants which was financed underthe project was completed in July 2013 |
MV and HV-substations rehabilitated | Value | 0.00 | 1.00 | 1.00 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment | The rehabilitation works at the RN1 substation were completed in March 2013. |
Pre-payment electricity meters installed by REGIDESO | Value | 10000.00 | 45077.00 | 43000.00 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment | It includes both meters installed by REGIDESO under and outside the project as stated in the PAD. In fact, the end target includesmeters installed both by the project and REGIDESO itself. The objective has been met. |
Electricity collection rate | Value | 64.00 | 81.70 | 85.00 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment | calculated as billing revenues divided by amounts billed | REGIDESO has accumulated unpaid bills from earlier years that need to be written off. The actual value is an estimated one (thevalue of the year 2012). The exact value for the year 2013 will be known by March 2014. The rate is likely to be improved due tothe fully installation of prepaid meters. |
Increased availability of power supply from the extended Bujumbura thermal power plant (hours/week) | Value | 0.00 | 140.00 | 56.00 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment | The end target has been surpassed. The average running hours of the thermal plant is about 140hours/week |
Generation Capacity of Conventional Generation constructed under the project | Value | 0.00 | 5.00 | 5.00 |
Date | December 31, 2009 | December 31, 2013 | January 31, 2014 | |
Comment | CSI Retrofit Dec. 2013 | The plant was installed in July 2013. The end target has been met. |